Questions and Answers
70RFPW20QW8000004
#1: Amendment 0009, page 2, section II.a states "original SF1449 marked Solicitation Package is replaced in its entirety with the attached SF1449 marked Amendment 0009". There was no SF1449 released with this amendment. Will the Government please provide this document?
Answer: Yes. Please see SF1449 provided with Amendment 10.
#2: Are Offerors to use the original version of Attachment D, Past Performance Project Form (PPPF) or should a new version have been provided with Amendment 0009?
Answer: Use the original version provided with the original solicitation documents.
#3. Due to the National problem with procurement and materials shortages, the 60 day period of performance may not be feasible depending on the start date of POP. Please advise if the Government will accommodate procurement lead times that Contractor may be subject to.
Answer: Yes, reasonable accommodations for COVID-related delays will be considered.