6991PE20Q000029 FB-668 and FB-671 DDX FY20 SOW 07.16.20.pdf

PDF 367 KB Posted

Attached to
SBRF FB-668 & FB-671 Hauling & Coating
Solicitation number
6991PE20Q000029
Issued by

About this file

This specification outlines requirements for hauling, drydocking, cleaning, coating, and performing general repairs on two deck cargo barges, FB-668 and FB-671, owned by the U.S. Department of Transportation Maritime Administration. The contractor will be responsible for tug and pilotage services to move the barges from storage to their shipyard, drydocking, interior and exterior hull cleaning and inspection, ultrasonic hull gauging, abrasive grit blasting of hulls and decks, application of various coatings, renewal of cathodic protection anodes, and estimated supplemental repair work. For FB-671, the specification calls for removal of ten existing zinc anodes and installation of twenty-two new 37-pound aluminum bar anodes. For FB-668, the requirement is to remove fifty-six existing zinc anodes and install fifty-six new six-pound aluminum anodes. The solicitation number for this opportunity is 6991PE20Q000029 and was issued by the DOT Maritime Administration Suisun Bay Reserve Fleet.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FB-668 & FB-671 DDX 2020 Page 1

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

GENERAL INFORMATION

FB-668 & FB-671 HAULING & COATING

1. The subject vessels are owned by the United States of America acting through the

Maritime Administration, Department of Transportation (herein after called Marad).

2. The contractor shall provide all labor, material, and equipment necessary to make all removals and restorations; remove and replace interferences; rig and unrig; make all disassembles and subsequent reassemblies to accomplish the work specified herein.

All work shall be in compliance with the latest Regulatory Body requirements. The term, “Regulatory Bodies” includes the American Bureau of Shipping, United States

Coast Guard, United States Public Health Service, the Department of Labor

Occupational Safety and Health Administration, and the Institute of Electrical and

Electronic Engineers.

3. If, in the performance of any work required in these Specifications, it becomes necessary to remove or disturb any structural part of the vessels, the contractor shall, upon completion of that work, reinstall or renew if necessary any affected structural part and restore to original conditions of durability, appearance, and seaworthiness.

All temporary removals in the way of the work are to be replaced in good order.

4. Any and all removed equipment or parts remain the property of the government and is to be left aboard the vessels. The contractor shall re-deliver the vessels in the same clean and orderly condition as when received.

5. All work specified shall be accomplished and completed in conformity with the highest standards of shipbuilding practices. All items contained in these

Specifications must be proved to the satisfaction of the Contracting Officer’s

Representative (COR).

6. The term “or equal” means that components, equipment or material shall be equivalent in terms of performance, services required, compatibility with interrelated systems and arrangements and supportability over the service life of the components or equipment.

In the case of component or equipment substitution for those components or equipment noted on the Contract Guidance Drawings or Specification, the Contractor shall submit a written request delineating the design and the performance data on both the specified and substituted piece of equipment for COR approval and if approved, the Contractor shall take full contractual and technical responsibility for ensuring installation of components or equipment’s or both and compatibility with interrelated systems.

7. The terms “Replace” or “Renew” mean to remove the existing unit, equipment, or systems, including all interferences and to install a new unit, equipment or system which is either identical to or equal to that which was removed; the installation shall include at

FB-668 & FB-671 DDX 2020 Page 2 a minimum all hook-up, supports, and adapters which are required to effect a fully operational installation complete in all respects.

8. Any repairs or other work resulting from recommendations or other discoveries after the vessels are docked are to be brought to the attention of the COR immediately by use of a contractor generated inspection report. Any such additional work will be subject to a delivery order. Additional work to be accomplished ONLY WHEN

AUTHORIZED IN WRITING.

9. Because these craft are not considered deep-sea worthy, all repair/upgrade work must be performed on these vessels in the San Francisco Bay area, such area to include the up-river areas of Sacramento and Stockton. The contractor shall be responsible for delivery from and to the Reserve Fleet, and shifting the vessels to and from drydock and within the contractor’s facility during the course of work.

10. The contractor shall gas-free or inert all spaces affected by the work described in this

Specification and is responsible for determining all spaces requiring gas freeing. All safety precautions contained in the United States Department of Labor Safety and

Health Regulations for Ship Repairing, Title 29 CFR Parts 1501.10, 1501.11, 1501.12, 1501.14, and 1501.15 must be strictly observed. A copy of the gas-free certificate is to be presented to the COR before beginning work on the repairs. Initial

Certificates are to be issued by a Certified Chemist, as will re-certifications if conditions change which will affect the Certificate. Gas-Free Certificates shall be updated daily by competent persons.

11. All welding shall meet ABS and USCG requirements and conform to American

Welding Society (AWS) standards. All welds shall be cleaned prior to painting. All surfaces which have been cut, drilled, welded, or otherwise modified shall be cleaned, free of grease, slag and foreign matter; and painted in accordance with the coating sections of these Specifications. Prior to any surface preparations the contractor will conduct a joint inspection of the welding repairs with the COR.

12. All dirt and debris resulting from the work required by these Specifications shall be removed from the vessels and disposed of at contractor’s expense. All affected areas shall be left clean and in good order at the end of the dry-docking period.

13. The FB-668 (BC-6310) is a deck cargo barge, steel construction, of the U.S. Army

BC-type, built in 1944. Vessel particulars are as follows:

• Length, overall: 110 feet

• Breadth, molded: 30 feet

• Depth, molded: 9 feet

• Draft, light: 4 feet

14. The FB-671 (BC-2819) is a deck cargo barge, steel construction, of the U.S. Army

BC-type, built in 1944. Vessel particulars are as follows:

FB-668 & FB-671 DDX 2020 Page 3

• Length, overall: 130 feet

• Breadth, molded: 30 feet

• Depth, molded: 9 feet

• Draft, light: 4 feet

Intent

The intent of this specification is to drydock the vessels, abrasive grit blast and preserve the hull and main deck surfaces, renew anodes and perform general repairs.

The following CLINs are applicable to both the FB-668 and FB-671

0001.1 DELIVERY

Provide tug(s), pilotage and riding crew as necessary, and any other services required to move the barges from their current berth in the SBRF to the contractor’s shipyard.

Provide assist tugs as required to place the barge in and out of the Contractor’s drydock.

Upon completion of repairs, return the barges to SBRF.

0001.2 DRY-DOCKING

A. Drydock the vessels for inspection, coating and repairs as described herein. At the completion of the required work, undock the vessels. All movement of the vessels on to and off of the drydock shall be the contractor’s responsibility.

B. Fleet the vessels for access to hull areas obstructed by docking blocks to assure

100% coating coverage on hull bottom.

C. Provide drydocking reports to the COR showing both locations of blocks and anode locations prior to re-delivery and Government acceptance of the vessel.

0001.3 EXTERIOR HULL CLEANING AND INSPECTION

This section deals with the cleaning and inspection of each vessel’s exterior, which includes the entire hull (underwater and freeboard), main deck, vents and fittings.

A. Assure all manhole covers and vent pipes are secure. Water wash the entire barge exterior using high-pressure fresh water at a minimum of 3000 PSI to remove dirt, growth and salts. Examine hull and deck for apparent damage and coating failure.

Submit a written report within one day of conditions found showing discrepancies found and their location to the COR.

FB-668 & FB-671 DDX 2020 Page 4

B. Handling, storage and disposal of hazardous waste, if any, generated as a result of the cleaning operation shall be the responsibility of the contractor, as being the generator. Disposal of any hazardous waste shall be at the contractor’s expense and in accordance with all local, state and federal regulations.

0001.4 INTERIOR HULL INSPECTION

A. Contractor, with the COR, shall inspect internal structural and coating conditions of internal voids / spaces. Provide a written report within one day to the COR of all conditions found and any recommended repairs.

0001.5 HULL ULTRASONIC HULL GAUGING

A. Perform an ultrasonic hull gauging survey of each vessel’s hull to determine thickness and integrity. For estimating purposes, assume 250 shots for each vessel are to be taken. Provide a written report of the survey.

0001.6 EXTERIOR SURFACE PREPARATION

A. Remove existing anodes and grind smooth the remaining welds so as to present a clean, smooth surface. If removing anodes with a cutting torch, exercise great care not to undercut into the shell plating. For estimating purposes, assume the remnants of 56 ea., 22 pound zinc anodes are installed to each hull.

B. Prior to blasting secure all watertight doors, cover and protect all tank and deck house vents and other openings to prevent ingress of blasting grit. After protective measures have been accomplished, abrasive grit blast the entire hull and exterior main deck of the vessels to SSPC SP-6 commercial blast standards.

C. Upon completion of grit blasting, the Contractor is to make a visual inspection of the entire hull and main deck. Contractor is to submit a written report of the conditions found during this inspection and make recommendations, if any to the

COR. Steel work will be addressed with the supplemental CLIN.

D. Handling, storage and disposal of hazardous waste, if any, generated as a result of surface preparation shall be the responsibility of the contractor, as being the generator. Disposal of any hazardous waste shall be at the contractor’s expense and in accordance with all local, state and federal regulations.

0001.7 EXTERIOR COATING

Contractor is to provide all labor, equipment and material to accomplish the following surface coating. All coating shall be applied in accordance with the coating

FB-668 & FB-671 DDX 2020 Page 5 manufacturer’s recommendations and under the supervision of the coating manufacturer’s representative.

A. UNDERWATER BODY (Keel to Deep Load Line)

1. Apply one (1) full coat of Intershield 300V or equal.

2. Apply one (1) stripe coat of Intershield 300V or equal to all welds and hard corners. Alternate colors between coats to assure proper coverage.

3. Apply a second full coat of Intershield 300V or equal after stripe coat has dried.

4. Apply two (2) full coats of Interspeed 6400NA or equal, first coat Black, second coat Red.

B. FREEBOARD (Deep Load Line to Main Deck)

2. Apply one (1) stripe coat of Intershield 300V or equal to all welds and hard

3. Apply a second full coat of Intershield 300V or equal after stripe coat has dried.

4. Apply one (1) full coat of Interthane 990HS or equal, Black.

5. Draft markings are to be hand painted where bead-welded with two (2) coats of Interthane 990HS or equal, White.

6. Paint in the vessel’s hull number “FB-668” and “FB-671”where bead-welded port side, stbd side, fore and aft using two (2) coats of Interthane 990HS or equal, White.

C. MAIN DECK

2. Apply one (1) stripe coat of Intersheld 300V or equal to all welds and hard

3. Apply one stripe coat around manhole covers, bitts, cleats, vents, and any structure welded perpendicular to the deck. When dry, mask a 2” margin around these areas.

FB-668 & FB-671 DDX 2020 Page 6

4. Apply a second full coat of Intershield 300V or equal to deck. While this coat is still wet, uniformly broadcast aluminum oxide abrasive on deck areas.

5. Remove masking and any loose abrasive in the masked area so it is clean before the final coat.

6. Apply one full coat of Interthane 990H or equal to the entire deck, Deck Gray.

For all coatings, care is to be taken so overspray does not come in contact with unintended surfaces on the vessel.

0001.8 CATHODIC PROTECTION

FB-671: The following section pertains to FB-671 only.

A. Prior to surface preparation and coating, remove and scrap the remains of ten (10)

ea. twenty-two (22) lb. welded zinc anodes from the barge hull. Grind smooth all weld remnants in preparation for blasting and coating.

B. Provide and install 22 ea. Reliance AMD-3365 or equal 37 lb. aluminum bar anodes. Weld ½” stainless steel bolts to the hull for attaching anodes. Anode tabs may need to be drilled. If anode tabs need to be drilled, maintain a uniform distance between bolt centers. Arrange the anodes according to the referenced cathodic protection plan. Install anodes to studs and secure using new stainless steel flat washers and nylock nuts.

FB-668: The following section pertains to FB-668 only.

A. Prior to surface preparation and coating, remove and scrap fifty-six (56) each, twenty-two (22) pound, zinc, bolt-on anodes. Protect the stainless steel studs prior to blasting.

B. Provide fifty-six (56) each, Martyr CMDIVERHA or equivalent, six (6) pound, aluminum, 6” x 12” x 1”, anodes with two (2) cast-in cored holes on 6” centers for the vessel’s hull. Install anodes to stainless steel studs using 316L stainless steel flat washers, lock washers, and nylock nuts.

0002 SUPPLEMENTAL

A. The contractor is to estimate the cost of two hundred hours (200) of supplemental repair work to be performed on this vessel in terms of a yard-wide man-hour (MH) labor rate.

B. An additional estimate of $15,000.00 may be utilized for material acquisition costs exclusive of other materials already specified in these repair specifications.