OPTION_CLIN_SOW_Addendum_Pricing_Sheet.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
TS GOLDEN BEAR Dry Docking Federal contract opportunity
Solicitation number
6991PE18Q000013
Issued by
Department of Transportation Maritime Administration

About this file

Addendum Pricing Sheet for the Option Clin

View the file

Other files for this federal contract opportunity

Other files attached to TS GOLDEN BEAR Dry Docking, newest first.
File Type Posted
Amendment_2.pdf PDF
BASE_CLIN_SOW_Addendum_Pricing_Sheet.xlsx XLSX spreadsheet
SOW_Addendum.pdf PDF
2018_Planned_Dry_Dock_Entry_Condition.pdf PDF
Questions_and_Answers.docx DOCX document
Documents_List.JPG JPG image
Ship_Check_Supplemental_Work_items.pdf PDF
Amendment_1.pdf PDF
6991PE18Q000013.pdf PDF
OPTION_Completion_Date_10_Aug_2018_Drydock_Quote_Sheet.xlsx XLSX spreadsheet
Completion_Date_24_Aug_2018_Drydock_Quote_Sheet.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Job Name Cal Maritime / Golden BearReportInspectionInspectionPalfingerPalfingerShipyardPricing
TASKPalfingerUSCGMan Days
LIFEBOAT DAVITS 1, 2, 3, 4, 5 & 6MARAD
Remove all lifeboat equipment from each boat and neatly stow in a location designated by the vessel's Chief Mate. Palfinger Marine to check inventory for damaged items, missing items, expiration dates and proper quantities. This should be completed within 72 hours of being removed from the lifeboats to allow time for replacement if needed. Upon completion of all work and placement of the lifeboats back into the davits transfer all equipment back into each boat and stow under the direction of the Chief Mate.XXInspect and report3.00Perform
Perform basic function test on each davit by lowering and raising each boat to identify any operational issues.XXXObserve and report2.00Perform
Verify proper operation of all limit switches. Order replacements for any switches found defective. Limit switches will need to be removed or protected during the sandblasting of the davit structure.XXObserve and report1.00Perform
Check condition of wiring for the limit swtches, Wiring found defective will be immediately tagged for replacement. Replacement to be completed by shipyard.XXObserve and report0.50Perform
Remove lifeboats from davits and block on the hard. Palfinger service engineers must be on site to ensure enough room is left for access around and under the lifeboats for painting and engine change outs.1.00Perform
Davit / Winch Controllers: Inspect each winch controller for each davit. Open inspection covers to conduct inspection which is to include at a minimum of removing all debris from within, terminal connections and any worn components. After completion of overhaul reinstall covers. It is essential that this be completed early in the yard period to identify and order replacement parts / components as needed. Free up and lubricate the controller door fastening clips and hardware.XXReport1.00Perform with shipyard electrician
Remove fall wire from winch drums and davits and properly dispose of all. (Shipyard to handle disposal)Supervise1.00Perform
Shut off and Tag and Lock-out power to the davits. With power tagged out on davits 1, 2 ,3 ,5 & 6 disconnect power from winch electric motors.0.25Perform
Visually inspect all gripes and long links for lifeboats and replace as needed.XXPerform and submit CFR2.00
Remove, & mark each fall block to allow re-installation on correct davit arm. Remove to shop shoreside to allow complete disassembly of fall block sheave and bushings, inspection of lower fall block swivel / Master link connection point inspection. Replace sheave bearings/bushings and other parts as needed.XXSupervise and report on other parts needed. Provide new sheave bearings/bushings.5.00Provide suitable shop space and perform. Note: No spares needed - Covered
Turnbuckles and clevises to be replaced as needed. Degrease and clean all as needed as to identify which must be ordered and replaced.XXInspect and report2.50Perform
Winches 1-6
Remove winch and winch electric motors from the davits. Transport to facility for disassembly and refurbishment.Provide suitable shop space and perform.
Remove and provide new electric motors for davit stations 1 thru 4Supervise and supply motors2.00Perform
Check condition of wiring for the motors, Wiring found defective will be immediately tagged for replacement. Replacement to be completed by shipyard.XXObserve and report0.50Perform
Remove winch motors from davit stations 5 and 6 to allow evaluation and service.XSupervise and report findings.1.00Perform and arrange motor shop sub
Winches must be drained of gear oil and completely disassembled. Gears and shafts not to be replaced must be tagged and marked to allow installation in the same gearbox and orientation. Inspect all gears and shafts for wear and report findingsd to MARAD rep.XXPerform with shipyard asistance.12.00Provide suitable shop space, provide labor assist for Palfinger tech, dispose of all oil and cleaning materials
Gear case for each station must be cleaned and inspected for defects. All bearing and seal journals, and mounting surfaces must be covered and protected for sand blasting.XXSupervise and inspect2.00Perform
Gear cases, winch drums and access covers are to be sand blasted and painted as per customer specified paint schedule.Perform
Assemble Winches replacing all bearings, bushings, seals and fasteners. Remove any broken fasteners and retap for proper assembly.Supply parts and perform12.00Assist with any required machine work and support labor
Inspect and assemble winch Centrifugal governing brakes using new linings.Supply parts and perform3.00
Inspect and assemble winch holding stop brakes using new linings.Supply parts and perform3.00
Replace one way clutch for 4 - BE 5.52 & 2 - BE 11.5 lifeboat davit winches.Supply parts and perform3.00
Install new/rebuilt electric motors and check pinion gear lash adjust as needed.Supervise2.00Perform
Renew Gear case oil. Replace all grease fittings following manufacturers lubrication guidelines. (Oil and lubricants supplied by ship / shipyard)0.50Supply lubricants and perform
Davits 1-4
Remove all loose hardware from davit trackways including gripe assemblies, turnbuckles, harbor davit arm lock plates, wire guards, electrical wiring, limit switches, and sheaves. . The removed items are to be carefully inspected & replaced or rebuilt as necessary. Mark or tag components for each davit.XXInspect and report4.00Perform
Cut arm removal slots in the trackways. Following an approved davit drawing fabricate removable sections for installation after reassembly allowing davit arms and carriage to be easily removed for future service. Tag and remove the davit arms and transport to a suitable shop space.Provide drawing and supervise2.00Perform. Provide a suitable shop space for the davit arms.
Davit trackways and all removed items must be sandblasted taking care to protect machined surface areas. Inspect for metal wastage and weld cracks and report to MARAD. Pay particular attention to the hard to maintain areas such as winch mounting brackets, bracing on the superstructure, and guard mounting tabs. Generate a change order to cover the costs of any additional repairs.XXXInspect and report3.00Perform.
All Pad eyes for use with davits and davit components also must be sandblasted, inspected & replaced as necessary before repainting.XXInspect and report1.00Perform
Strip davit arms and davit arm carriage assembly to service and renew bushings on wheel assemblies. Remove all sheaves inspect for wear or corrosion. Tag all components to allow installation on assembly from which it was removed.XXProvide wheel bushings and supervise3.00Perform
Remove pudding blocks and chocking.Supply bulk material and supervise1.00Perform (cut and shape material to fit)
Sand blast davit arms and components taking care to protect machined surface areas. Inspect for metal wastage and report findings to MARAD rep. Pay particular attention to the hard to maintain areas.XXXSupervise and inspect2.00Perform
Paint all davit components and trackways as per the paint schedule paying attention to the original color scheme of the various components. This is to include sheaves, harbor pin, and gripe components.X1.00Perform
Reassemble all parts on the arms and the tracks using new CREST fasteners, bearings, and bushings. Reinstall limit switches. Fabricate and install new pudding blocks from solid rubber material. Reinstall the davit arms in the trackways.XPerform. Supply bearings, bushings, fasteners and bulk rubber for pudding blocks3.00Assist with part installation. Fabricate and install pudding blocks as per original shape. Install davit arms.
Davits 5-6
Tag and mark davit arms and stop link assemblies and transport to shoreside facility.Supervise2.00Provide suitable shop space and perform.
Remove grease tubing line, stand offs, and other hardware from arms. Remove davit arm head sheaves. Disassemble sheaves and inspect bearings, bushings and pins. Inspect the davit arms main pin and bushing. Report findings to MARAD rep. Cover bearing and pin journals to allow the arms to be sandblasted.XXSupervise and report2.00Perform
Sand blast davit arms and components taking care to protect machined surface areas. Inspect for metal wastage and weld cracks and report findings to MARAD rep.XXXSupervise and report1.00Perform
Repaint davit arms following paint schedule provided by customer.X0.25Perform
Tag and remove all sheaves and gripes from the davit stands for inspection and report findings to MARAD rep.X2.00Perform. Provide staging or other access as needed.
Remove and replace pudding blocks with solid rubber material.Provide bulk rubber material.Fabricate and install pudding blocks as per original shape.
Reassemble all parts and sheaves on the arms and the and davit stand using new CREST fasteners, bearings, and bushings.XPerform. Supply bearings, bushings, fasteners.2.00Assist with part installation. Provide staging or other access as needed.
Install rebuilt davit arms.Supervise1.00Perform
Install new/refurbished gripe assemblies, turnbuckles, harbor davit arm lock plates and misc. hardware. All moving parts must be lubricated prior to assembly.XSupervise1.00Perform
Reassembly
Install rebuilt lifeboat davit winches with new or refurbished electric motors. Replace all winch gear case to davit frame fasteners.XSupervise and supply fasteners3.00Perform
Coat all fasteners and disturbed paint areas with primer and paint to match equipment.X0.50Perform
Connect motors to ships power and verifying correct motor rotation.XSupervise2.00Perform
With power restored to the davits renew fall wire to all lifeboat davits and adjust lengths. Stencil fall wire renewal date on each davit frame.XProvide fall wire and supervise4.00Perform
Master links and complete suspension chain arrangement to be replaced for all lifeboat davits.Supply1.00Remove old and install new
Testing
Prepare davit and winch sets for operational testing. Inspect all davit winches, check operation of manual brakes, centrifugal clutch, and centrifugal brakes prior to weight testing davit/winch sets in accordance with the latest IMO and SOLAS rules.XInspect and supervise1.00Perform
Install and verify position of all limit switches.XPerform2.00Provide electrician
Complete required 1.1 x Load 10 minute static and a 2 stop dynamic brake function test at each lifeboat station.XXXSupervise3.00Supply test weights and perform
Return boats to the ship, during recovery of the lifeboats, limit switches will be checked for proper operation and position.XCheck limit switches1.00Perform
Provide final reports detailing the work accomplished, final inspection results, and test certificatesXPerform1.00
110.00
NOTE: DISREGARD ANY REPAIRS FOR LIFEBOATS No 5 and No 6