OPTION_CLIN_SOW_Addendum_Pricing_Sheet.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- TS GOLDEN BEAR Dry Docking Federal contract opportunity
- Solicitation number
- 6991PE18Q000013
About this file
Addendum Pricing Sheet for the Option Clin
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_2.pdf | ||
| BASE_CLIN_SOW_Addendum_Pricing_Sheet.xlsx | XLSX spreadsheet | |
| SOW_Addendum.pdf | ||
| 2018_Planned_Dry_Dock_Entry_Condition.pdf | ||
| Questions_and_Answers.docx | DOCX document | |
| Documents_List.JPG | JPG image | |
| Ship_Check_Supplemental_Work_items.pdf | ||
| Amendment_1.pdf | ||
| 6991PE18Q000013.pdf | ||
| OPTION_Completion_Date_10_Aug_2018_Drydock_Quote_Sheet.xlsx | XLSX spreadsheet | |
| Completion_Date_24_Aug_2018_Drydock_Quote_Sheet.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Job Name Cal Maritime / Golden Bear | Report | Inspection | Inspection | Palfinger | Palfinger | Shipyard | Pricing |
| TASK | Palfinger | USCG | Man Days | ||||
| LIFEBOAT DAVITS 1, 2, 3, 4, 5 & 6 | MARAD | ||||||
| Remove all lifeboat equipment from each boat and neatly stow in a location designated by the vessel's Chief Mate. Palfinger Marine to check inventory for damaged items, missing items, expiration dates and proper quantities. This should be completed within 72 hours of being removed from the lifeboats to allow time for replacement if needed. Upon completion of all work and placement of the lifeboats back into the davits transfer all equipment back into each boat and stow under the direction of the Chief Mate. | X | X | Inspect and report | 3.00 | Perform | ||
| Perform basic function test on each davit by lowering and raising each boat to identify any operational issues. | X | X | X | Observe and report | 2.00 | Perform | |
| Verify proper operation of all limit switches. Order replacements for any switches found defective. Limit switches will need to be removed or protected during the sandblasting of the davit structure. | X | X | Observe and report | 1.00 | Perform | ||
| Check condition of wiring for the limit swtches, Wiring found defective will be immediately tagged for replacement. Replacement to be completed by shipyard. | X | X | Observe and report | 0.50 | Perform | ||
| Remove lifeboats from davits and block on the hard. Palfinger service engineers must be on site to ensure enough room is left for access around and under the lifeboats for painting and engine change outs. | 1.00 | Perform | |||||
| Davit / Winch Controllers: Inspect each winch controller for each davit. Open inspection covers to conduct inspection which is to include at a minimum of removing all debris from within, terminal connections and any worn components. After completion of overhaul reinstall covers. It is essential that this be completed early in the yard period to identify and order replacement parts / components as needed. Free up and lubricate the controller door fastening clips and hardware. | X | X | Report | 1.00 | Perform with shipyard electrician | ||
| Remove fall wire from winch drums and davits and properly dispose of all. (Shipyard to handle disposal) | Supervise | 1.00 | Perform | ||||
| Shut off and Tag and Lock-out power to the davits. With power tagged out on davits 1, 2 ,3 ,5 & 6 disconnect power from winch electric motors. | 0.25 | Perform | |||||
| Visually inspect all gripes and long links for lifeboats and replace as needed. | X | X | Perform and submit CFR | 2.00 | |||
| Remove, & mark each fall block to allow re-installation on correct davit arm. Remove to shop shoreside to allow complete disassembly of fall block sheave and bushings, inspection of lower fall block swivel / Master link connection point inspection. Replace sheave bearings/bushings and other parts as needed. | X | X | Supervise and report on other parts needed. Provide new sheave bearings/bushings. | 5.00 | Provide suitable shop space and perform. Note: No spares needed - Covered | ||
| Turnbuckles and clevises to be replaced as needed. Degrease and clean all as needed as to identify which must be ordered and replaced. | X | X | Inspect and report | 2.50 | Perform | ||
| Winches 1-6 | |||||||
| Remove winch and winch electric motors from the davits. Transport to facility for disassembly and refurbishment. | Provide suitable shop space and perform. | ||||||
| Remove and provide new electric motors for davit stations 1 thru 4 | Supervise and supply motors | 2.00 | Perform | ||||
| Check condition of wiring for the motors, Wiring found defective will be immediately tagged for replacement. Replacement to be completed by shipyard. | X | X | Observe and report | 0.50 | Perform | ||
| Remove winch motors from davit stations 5 and 6 to allow evaluation and service. | X | Supervise and report findings. | 1.00 | Perform and arrange motor shop sub | |||
| Winches must be drained of gear oil and completely disassembled. Gears and shafts not to be replaced must be tagged and marked to allow installation in the same gearbox and orientation. Inspect all gears and shafts for wear and report findingsd to MARAD rep. | X | X | Perform with shipyard asistance. | 12.00 | Provide suitable shop space, provide labor assist for Palfinger tech, dispose of all oil and cleaning materials | ||
| Gear case for each station must be cleaned and inspected for defects. All bearing and seal journals, and mounting surfaces must be covered and protected for sand blasting. | X | X | Supervise and inspect | 2.00 | Perform | ||
| Gear cases, winch drums and access covers are to be sand blasted and painted as per customer specified paint schedule. | Perform | ||||||
| Assemble Winches replacing all bearings, bushings, seals and fasteners. Remove any broken fasteners and retap for proper assembly. | Supply parts and perform | 12.00 | Assist with any required machine work and support labor | ||||
| Inspect and assemble winch Centrifugal governing brakes using new linings. | Supply parts and perform | 3.00 | |||||
| Inspect and assemble winch holding stop brakes using new linings. | Supply parts and perform | 3.00 | |||||
| Replace one way clutch for 4 - BE 5.52 & 2 - BE 11.5 lifeboat davit winches. | Supply parts and perform | 3.00 | |||||
| Install new/rebuilt electric motors and check pinion gear lash adjust as needed. | Supervise | 2.00 | Perform | ||||
| Renew Gear case oil. Replace all grease fittings following manufacturers lubrication guidelines. (Oil and lubricants supplied by ship / shipyard) | 0.50 | Supply lubricants and perform | |||||
| Davits 1-4 | |||||||
| Remove all loose hardware from davit trackways including gripe assemblies, turnbuckles, harbor davit arm lock plates, wire guards, electrical wiring, limit switches, and sheaves. . The removed items are to be carefully inspected & replaced or rebuilt as necessary. Mark or tag components for each davit. | X | X | Inspect and report | 4.00 | Perform | ||
| Cut arm removal slots in the trackways. Following an approved davit drawing fabricate removable sections for installation after reassembly allowing davit arms and carriage to be easily removed for future service. Tag and remove the davit arms and transport to a suitable shop space. | Provide drawing and supervise | 2.00 | Perform. Provide a suitable shop space for the davit arms. | ||||
| Davit trackways and all removed items must be sandblasted taking care to protect machined surface areas. Inspect for metal wastage and weld cracks and report to MARAD. Pay particular attention to the hard to maintain areas such as winch mounting brackets, bracing on the superstructure, and guard mounting tabs. Generate a change order to cover the costs of any additional repairs. | X | X | X | Inspect and report | 3.00 | Perform. | |
| All Pad eyes for use with davits and davit components also must be sandblasted, inspected & replaced as necessary before repainting. | X | X | Inspect and report | 1.00 | Perform | ||
| Strip davit arms and davit arm carriage assembly to service and renew bushings on wheel assemblies. Remove all sheaves inspect for wear or corrosion. Tag all components to allow installation on assembly from which it was removed. | X | X | Provide wheel bushings and supervise | 3.00 | Perform | ||
| Remove pudding blocks and chocking. | Supply bulk material and supervise | 1.00 | Perform (cut and shape material to fit) | ||||
| Sand blast davit arms and components taking care to protect machined surface areas. Inspect for metal wastage and report findings to MARAD rep. Pay particular attention to the hard to maintain areas. | X | X | X | Supervise and inspect | 2.00 | Perform | |
| Paint all davit components and trackways as per the paint schedule paying attention to the original color scheme of the various components. This is to include sheaves, harbor pin, and gripe components. | X | 1.00 | Perform | ||||
| Reassemble all parts on the arms and the tracks using new CREST fasteners, bearings, and bushings. Reinstall limit switches. Fabricate and install new pudding blocks from solid rubber material. Reinstall the davit arms in the trackways. | X | Perform. Supply bearings, bushings, fasteners and bulk rubber for pudding blocks | 3.00 | Assist with part installation. Fabricate and install pudding blocks as per original shape. Install davit arms. | |||
| Davits 5-6 | |||||||
| Tag and mark davit arms and stop link assemblies and transport to shoreside facility. | Supervise | 2.00 | Provide suitable shop space and perform. | ||||
| Remove grease tubing line, stand offs, and other hardware from arms. Remove davit arm head sheaves. Disassemble sheaves and inspect bearings, bushings and pins. Inspect the davit arms main pin and bushing. Report findings to MARAD rep. Cover bearing and pin journals to allow the arms to be sandblasted. | X | X | Supervise and report | 2.00 | Perform | ||
| Sand blast davit arms and components taking care to protect machined surface areas. Inspect for metal wastage and weld cracks and report findings to MARAD rep. | X | X | X | Supervise and report | 1.00 | Perform | |
| Repaint davit arms following paint schedule provided by customer. | X | 0.25 | Perform | ||||
| Tag and remove all sheaves and gripes from the davit stands for inspection and report findings to MARAD rep. | X | 2.00 | Perform. Provide staging or other access as needed. | ||||
| Remove and replace pudding blocks with solid rubber material. | Provide bulk rubber material. | Fabricate and install pudding blocks as per original shape. | |||||
| Reassemble all parts and sheaves on the arms and the and davit stand using new CREST fasteners, bearings, and bushings. | X | Perform. Supply bearings, bushings, fasteners. | 2.00 | Assist with part installation. Provide staging or other access as needed. | |||
| Install rebuilt davit arms. | Supervise | 1.00 | Perform | ||||
| Install new/refurbished gripe assemblies, turnbuckles, harbor davit arm lock plates and misc. hardware. All moving parts must be lubricated prior to assembly. | X | Supervise | 1.00 | Perform | |||
| Reassembly | |||||||
| Install rebuilt lifeboat davit winches with new or refurbished electric motors. Replace all winch gear case to davit frame fasteners. | X | Supervise and supply fasteners | 3.00 | Perform | |||
| Coat all fasteners and disturbed paint areas with primer and paint to match equipment. | X | 0.50 | Perform | ||||
| Connect motors to ships power and verifying correct motor rotation. | X | Supervise | 2.00 | Perform | |||
| With power restored to the davits renew fall wire to all lifeboat davits and adjust lengths. Stencil fall wire renewal date on each davit frame. | X | Provide fall wire and supervise | 4.00 | Perform | |||
| Master links and complete suspension chain arrangement to be replaced for all lifeboat davits. | Supply | 1.00 | Remove old and install new | ||||
| Testing | |||||||
| Prepare davit and winch sets for operational testing. Inspect all davit winches, check operation of manual brakes, centrifugal clutch, and centrifugal brakes prior to weight testing davit/winch sets in accordance with the latest IMO and SOLAS rules. | X | Inspect and supervise | 1.00 | Perform | |||
| Install and verify position of all limit switches. | X | Perform | 2.00 | Provide electrician | |||
| Complete required 1.1 x Load 10 minute static and a 2 stop dynamic brake function test at each lifeboat station. | X | X | X | Supervise | 3.00 | Supply test weights and perform | |
| Return boats to the ship, during recovery of the lifeboats, limit switches will be checked for proper operation and position. | X | Check limit switches | 1.00 | Perform | |||
| Provide final reports detailing the work accomplished, final inspection results, and test certificates | X | Perform | 1.00 | ||||
| 110.00 | |||||||
| NOTE: DISREGARD ANY REPAIRS FOR LIFEBOATS No 5 and No 6 |