Bid Tabs.pdf

PDF 676 KB Posted

Attached to
CA ERFO FS PLMAS 2021-02(1) North Fork Feather River Bridge Federal contract opportunity
Solicitation number
6982AF23B000012
Issued by
Department of Transportation Federal Highway Administration

About this file

This document is a tabulation of bids report for solicitation number 6982AF23B000012 to replace the North Fork Feather River Bridge. The bids were opened on September 28, 2023 by the Department of Transportation Federal Highway Administration.

The report provides pricing from four contractors for the base schedule and a single option. For the base schedule, SEB Engineering Inc. dba Stewart Engineering Inc. provided the lowest bid at $3,270,486, followed by Steelhead Constructors JV at $3,792,051, STPG Malcom JV LLC at $4,211,274.46, and the engineer's estimate was $3,980,000. For the single option, pricing ranged from $431,000 by Steelhead Constructors JV to $471,000 by SEB Engineering Inc. dba Stewart Engineering Inc., with an engineer's estimate of $498,000. The award date is to be determined. The report includes line item details for all pricing provided.

View the file

Other files for this federal contract opportunity

Other files attached to CA ERFO FS PLMAS 2021-02(1) North Fork Feather River Bridge, newest first.
File Type Posted
Bid Opening Summary.doc DOC document
Amendment A003 CA ERFO FS PLMAS 2021-02(1).pdf PDF
Amendment A002 CA ERFO FS PLMAS 2021-02(1).pdf PDF
6982AF23B000012 Q and A 9-13-23.pdf PDF
Amendment A001 CA ERFO FS PLMAS 2021-02(1).pdf PDF
6982AF23B000012 Q and A 9-6-23.pdf PDF
6982AF23B000012 Q and A 8-31-23.pdf PDF
CA ERFO FS2021-2 Final Plans.pdf PDF
CA.ERFO.FS PLMAS.2021-02.North Fork Feather River Bridge.Geotech Rpt FINAL.rev.pdf PDF
6982AF23B000012.pdf PDF
FP-14_Eng.pdf PDF
CA ERFO FS 2021 N. Fork Feather River Bridge Final Hydraulics Report_rev.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 10/03/23

1 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Contractor Responsive?

Engineer's Estimate

SEB Engineering Inc. dba Stewart Engineering Inc.

Steelhead Constructors JV

STPG Malcom JV LLC

Base Schedule A

$3,980,000.00

$3,270,486.00

$3,792,051.00

$4,211,274.46

Option: X

$498,000.00

$471,000.00

$431,000.00

$453,170.00

Contractor Responsive?

Engineer's Estimate

SEB Engineering Inc. dba Stewart Engineering Inc.

Steelhead Constructors JV

STPG Malcom JV LLC

Total Base Schedule A and Option(s): X

$4,478,000.00

$3,741,486.00

$4,223,051.00

$4,664,444.46

2 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF23B000012

Division: Central Federal Lands

State: CA County: Plumas

Federal Land: Plumas National Forest Opened at: Lakewood, CO

Opened by: Eric Grosskreuz

Date: 09/28/23

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

SEB Engineering Inc. dba Stewart Engineering Inc. $3,270,486.00 P.O. Box 990010 Redding, CA 96099

Steelhead Constructors JV $3,792,051.00 PO Box 536 Palo Cedro, CA 96073

STPG Malcom JV LLC $4,211,274.46 3700 Centerpoint Drive, Suite 8155 Anchorage, AK 99503

Engineer's Estimate $3,980,000.00

3 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1000 15101-0000 MOBILIZATION

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $330,000.00 Steelhead Constructors JV Lump Sum $650,000.00 STPG Malcom JV LLC Lump Sum $420,000.00 Engineer's Estimate ALL LPSM Lump Sum $429,792.50

A1020 15214-1000 SURVEY AND STAKING, BRIDGE (NORTH FORK FEATHER RIVER BRIDGE)

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $16,200.00 Steelhead Constructors JV Lump Sum $8,000.00 STPG Malcom JV LLC Lump Sum $9,125.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A1040 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

SEB Engineering Inc. dba Stewart Engineering Inc. $174,000.00 $7,656.00 Steelhead Constructors JV $204,545.45 $9,000.00 STPG Malcom JV LLC $311,120.00 $13,689.28 Engineer's Estimate 0.044 MILE $75,000.00 $3,300.00

A1060 15236-2000 SURVEY CONTROL, GRADE FINISHING

SEB Engineering Inc. dba Stewart Engineering Inc. $139,000.00 $12,093.00 Steelhead Constructors JV $103,448.28 $9,000.00 STPG Malcom JV LLC $104,890.00 $9,125.43 Engineer's Estimate 0.087 MILE $65,000.00 $5,655.00

A1080 15301-0000 CONTRACTOR QUALITY CONTROL

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $346,000.00 Steelhead Constructors JV Lump Sum $75,000.00 STPG Malcom JV LLC Lump Sum $267,785.00 Engineer's Estimate ALL LPSM Lump Sum $121,300.00

A1100 15401-0000 CONTRACTOR TESTING

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $6,500.00 Steelhead Constructors JV Lump Sum $75,000.00 STPG Malcom JV LLC Lump Sum $45,625.00 Engineer's Estimate ALL LPSM Lump Sum $103,125.00

4 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1120 15501-0000 CONSTRUCTION SCHEDULE

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $14,600.00 Steelhead Constructors JV Lump Sum $15,000.00 STPG Malcom JV LLC Lump Sum $12,720.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A1140 15701-0000 SOIL EROSION CONTROL (NORTH FORK FEATHER RIVER BRIDGE)

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $55,000.00 Steelhead Constructors JV Lump Sum $25,000.00 STPG Malcom JV LLC Lump Sum $36,920.00 Engineer's Estimate ALL LPSM Lump Sum $33,650.00

A1160 20103-0000 CLEARING AND GRUBBING

SEB Engineering Inc. dba Stewart Engineering Inc. $15.00 $33,000.00 Steelhead Constructors JV $5.00 $11,000.00 STPG Malcom JV LLC $37.00 $81,400.00 Engineer's Estimate 2,200 SQYD $33.00 $72,600.00

A1180 20301-2400 REMOVAL OF SIGN

SEB Engineering Inc. dba Stewart Engineering Inc. $165.00 $165.00 Steelhead Constructors JV $250.00 $250.00 STPG Malcom JV LLC $2,375.00 $2,375.00 Engineer's Estimate 1 EACH $350.00 $350.00

A1200 20304-2000 REMOVAL OF BRIDGE (NORTH FORK FEATHER RIVER BRIDGE)

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $35,000.00 Steelhead Constructors JV Lump Sum $25,000.00 STPG Malcom JV LLC Lump Sum $76,100.00 Engineer's Estimate ALL LPSM Lump Sum $125,000.00

A1220 20315-0000 SAWCUTTING PAVEMENT

SEB Engineering Inc. dba Stewart Engineering Inc. $21.00 $630.00 Steelhead Constructors JV $40.00 $1,200.00 STPG Malcom JV LLC $40.00 $1,200.00 Engineer's Estimate 30 LNFT $14.00 $420.00

5 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1240 20420-0000 EMBANKMENT CONSTRUCTION

SEB Engineering Inc. dba Stewart Engineering Inc. $151.00 $49,075.00 Steelhead Constructors JV $200.00 $65,000.00 STPG Malcom JV LLC $286.00 $92,950.00 Engineer's Estimate 325 CUYD $212.00 $68,900.00

A1260 20801-0000 STRUCTURE EXCAVATION

SEB Engineering Inc. dba Stewart Engineering Inc. $157.00 $20,410.00 Steelhead Constructors JV $220.00 $28,600.00 STPG Malcom JV LLC $357.00 $46,410.00 Engineer's Estimate 130 CUYD $300.00 $39,000.00

A1280 20803-0000 STRUCTURAL BACKFILL

SEB Engineering Inc. dba Stewart Engineering Inc. $760.00 $30,400.00 Steelhead Constructors JV $1,400.00 $56,000.00 STPG Malcom JV LLC $1,600.00 $64,000.00 Engineer's Estimate 40 CUYD $400.00 $16,000.00

A1300 20820-0000 DEWATERING

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $17,000.00 Steelhead Constructors JV Lump Sum $35,000.00 STPG Malcom JV LLC Lump Sum $106,450.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00

A1320 25101-2200 PLACED RIPRAP, METHOD B, CLASS 2

SEB Engineering Inc. dba Stewart Engineering Inc. $220.00 $37,400.00 Steelhead Constructors JV $450.00 $76,500.00 STPG Malcom JV LLC $868.00 $147,560.00 Engineer's Estimate 170 CUYD $325.00 $55,250.00

A1340 30202-2000 ROADWAY AGGREGATE, METHOD 2

SEB Engineering Inc. dba Stewart Engineering Inc. $113.00 $46,330.00 Steelhead Constructors JV $180.00 $73,800.00 STPG Malcom JV LLC $308.00 $126,280.00 Engineer's Estimate 410 TON $132.00 $54,120.00

6 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1360 40301-0000 ASPHALT CONCRETE PAVEMENT

SEB Engineering Inc. dba Stewart Engineering Inc. $1,150.00 $74,750.00 Steelhead Constructors JV $670.00 $43,550.00 STPG Malcom JV LLC $280.00 $18,200.00 Engineer's Estimate 65 TON $1,005.00 $65,325.00

A1380 40505-3000 ANTISTRIP ADDITIVE, TYPE 3

SEB Engineering Inc. dba Stewart Engineering Inc. $5,900.00 $3,835.00 Steelhead Constructors JV $1,538.46 $1,000.00 STPG Malcom JV LLC $375.00 $243.75 Engineer's Estimate 0.65 TON $4,500.00 $2,925.00

A1400 40601-0000 FOG SEAL

SEB Engineering Inc. dba Stewart Engineering Inc. $32,000.00 $5,120.00 Steelhead Constructors JV $6,250.00 $1,000.00 STPG Malcom JV LLC $1,500.00 $240.00 Engineer's Estimate 0.16 TON $3,250.00 $520.00

A1420 41102-0000 PRIME COAT

SEB Engineering Inc. dba Stewart Engineering Inc. $13.00 $5,070.00 Steelhead Constructors JV $4.00 $1,560.00 STPG Malcom JV LLC $3.00 $1,170.00 Engineer's Estimate 390 SQYD $3.00 $1,170.00

A1440 41201-0000 TACK COAT

SEB Engineering Inc. dba Stewart Engineering Inc. $1,100.00 $187.00 Steelhead Constructors JV $1,300.00 $221.00 STPG Malcom JV LLC $1,500.00 $255.00 Engineer's Estimate 0.17 TON $2,250.00 $382.50

A1460 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

SEB Engineering Inc. dba Stewart Engineering Inc. $4,163.00 $412,137.00 Steelhead Constructors JV $5,750.00 $569,250.00 STPG Malcom JV LLC $5,530.00 $547,470.00 Engineer's Estimate 99 CUYD $3,700.00 $366,300.00

7 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1480 55401-1000 REINFORCING STEEL (NORTH FORK FEATHER RIVER BRIDGE)

SEB Engineering Inc. dba Stewart Engineering Inc. $2.30 $9,200.00 Steelhead Constructors JV $2.50 $10,000.00 STPG Malcom JV LLC $2.90 $11,600.00 Engineer's Estimate 4,000 LB $5.00 $20,000.00

A1500 55401-2000 REINFORCING STEEL, EPOXY COATED

SEB Engineering Inc. dba Stewart Engineering Inc. $3.50 $67,200.00 Steelhead Constructors JV $3.50 $67,200.00 STPG Malcom JV LLC $3.10 $59,520.00 Engineer's Estimate 19,200 LB $5.00 $96,000.00

A1520 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED

SEB Engineering Inc. dba Stewart Engineering Inc. $7.20 $756,000.00 Steelhead Constructors JV $10.00 $1,050,000.00 STPG Malcom JV LLC $8.75 $918,750.00 Engineer's Estimate 105,000 LB $9.00 $945,000.00

A1540 55601-0900 BRIDGE RAILING, STEEL (OREGON DOT BR206 2-TUBE CURB MOUNTED RAIL)

SEB Engineering Inc. dba Stewart Engineering Inc. $694.00 $181,828.00 Steelhead Constructors JV $600.00 $157,200.00 STPG Malcom JV LLC $403.00 $105,586.00 Engineer's Estimate 262 LNFT $400.00 $104,800.00

A1560 56401-1000 BEARING DEVICE, ELASTOMERIC

SEB Engineering Inc. dba Stewart Engineering Inc. $4,700.00 $28,200.00 Steelhead Constructors JV $4,200.00 $25,200.00 STPG Malcom JV LLC $5,930.00 $35,580.00 Engineer's Estimate 6 EACH $4,000.00 $24,000.00

A1580 56501-0300 DRILLED SHAFT, 30-INCH DIAMETER

SEB Engineering Inc. dba Stewart Engineering Inc. $1,520.00 $437,760.00 Steelhead Constructors JV $1,500.00 $432,000.00 STPG Malcom JV LLC $2,000.00 $576,000.00 Engineer's Estimate 288 LNFT $2,800.00 $806,400.00

8 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1600 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS

SEB Engineering Inc. dba Stewart Engineering Inc. $108.00 $9,720.00 Steelhead Constructors JV $350.00 $31,500.00 STPG Malcom JV LLC $325.00 $29,250.00 Engineer's Estimate 90 LNFT $115.00 $10,350.00

A1620 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

SEB Engineering Inc. dba Stewart Engineering Inc. $6,600.00 $26,400.00 Steelhead Constructors JV $8,600.00 $34,400.00 STPG Malcom JV LLC $8,070.00 $32,280.00 Engineer's Estimate 4 EACH $7,500.00 $30,000.00

A1640 61707-0000 STRUCTURE TRANSITION RAILING

SEB Engineering Inc. dba Stewart Engineering Inc. $670.00 $56,280.00 Steelhead Constructors JV $750.00 $63,000.00 STPG Malcom JV LLC $690.00 $57,960.00 Engineer's Estimate 84 LNFT $375.00 $31,500.00

A1660 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

SEB Engineering Inc. dba Stewart Engineering Inc. $300.00 $6,000.00 Steelhead Constructors JV $250.00 $5,000.00 STPG Malcom JV LLC $205.00 $4,100.00 Engineer's Estimate 20 HOUR $280.00 $5,600.00

A1680 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH

SEB Engineering Inc. dba Stewart Engineering Inc. $270.00 $5,400.00 Steelhead Constructors JV $200.00 $4,000.00 STPG Malcom JV LLC $325.00 $6,500.00 Engineer's Estimate 20 HOUR $255.00 $5,100.00

A1700 62201-2050 ROLLER

SEB Engineering Inc. dba Stewart Engineering Inc. $335.00 $6,700.00 Steelhead Constructors JV $240.00 $4,800.00 STPG Malcom JV LLC $290.00 $5,800.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00

9 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1720 62201-2800 MOTOR GRADER, 8 FOOT MINIMUM BLADE

SEB Engineering Inc. dba Stewart Engineering Inc. $450.00 $9,000.00 Steelhead Constructors JV $300.00 $6,000.00 STPG Malcom JV LLC $440.00 $8,800.00 Engineer's Estimate 20 HOUR $330.00 $6,600.00

A1740 62201-3000 HYDRAULIC EXCAVATOR

SEB Engineering Inc. dba Stewart Engineering Inc. $120.00 $2,400.00 Steelhead Constructors JV $300.00 $6,000.00 STPG Malcom JV LLC $350.00 $7,000.00 Engineer's Estimate 20 HOUR $295.00 $5,900.00

A1760 62301-0000 GENERAL LABOR

SEB Engineering Inc. dba Stewart Engineering Inc. $57.00 $2,280.00 Steelhead Constructors JV $110.00 $4,400.00 STPG Malcom JV LLC $200.00 $8,000.00 Engineer's Estimate 40 HOUR $120.00 $4,800.00

A1780 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

SEB Engineering Inc. dba Stewart Engineering Inc. $153.00 $3,060.00 Steelhead Constructors JV $270.00 $5,400.00 STPG Malcom JV LLC $380.00 $7,600.00 Engineer's Estimate 20 HOUR $265.00 $5,300.00

A1800 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

SEB Engineering Inc. dba Stewart Engineering Inc. $280.00 $5,600.00 Steelhead Constructors JV $275.00 $5,500.00 STPG Malcom JV LLC $380.00 $7,600.00 Engineer's Estimate 20 HOUR $260.00 $5,200.00

A1820 62405-0400 PLACING CONSERVED TOPSOIL, 6-INCH DEPTH

SEB Engineering Inc. dba Stewart Engineering Inc. $13.00 $3,900.00 Steelhead Constructors JV $5.00 $1,500.00 STPG Malcom JV LLC $77.00 $23,100.00 Engineer's Estimate 300 SQYD $9.00 $2,700.00

10 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1840 62511-2000 SEEDING, HYDRAULIC METHOD

SEB Engineering Inc. dba Stewart Engineering Inc. $4.00 $3,400.00 Steelhead Constructors JV $5.00 $4,250.00 STPG Malcom JV LLC $16.00 $13,600.00 Engineer's Estimate 850 SQYD $4.00 $3,400.00

A1860 62516-3000 MULCHING, HYDRAULIC METHOD, BONDED FIBER MATRIX

SEB Engineering Inc. dba Stewart Engineering Inc. $2.00 $1,700.00 Steelhead Constructors JV $2.00 $1,700.00 STPG Malcom JV LLC $21.00 $17,850.00 Engineer's Estimate 850 SQYD $5.00 $4,250.00

A1880 63301-0000 SIGN SYSTEM

SEB Engineering Inc. dba Stewart Engineering Inc. $1,500.00 $4,500.00 Steelhead Constructors JV $470.00 $1,410.00 STPG Malcom JV LLC $2,500.00 $7,500.00 Engineer's Estimate 3 EACH $965.00 $2,895.00

A1900 63309-0000 DELINEATOR

SEB Engineering Inc. dba Stewart Engineering Inc. $150.00 $150.00 Steelhead Constructors JV $310.00 $310.00 STPG Malcom JV LLC $1,875.00 $1,875.00 Engineer's Estimate 1 EACH $300.00 $300.00

A1920 63403-0200 PAVEMENT MARKINGS, TYPE B

SEB Engineering Inc. dba Stewart Engineering Inc. $350.00 $5,250.00 Steelhead Constructors JV $90.00 $1,350.00 STPG Malcom JV LLC $62.00 $930.00 Engineer's Estimate 15 SQFT $28.00 $420.00

A1940 63501-0000 TEMPORARY TRAFFIC CONTROL

SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $80,000.00 Steelhead Constructors JV Lump Sum $15,000.00 STPG Malcom JV LLC Lump Sum $137,200.00 Engineer's Estimate ALL LPSM Lump Sum $185,000.00

11 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Total Schedule - All Items

SEB Engineering Inc. dba Stewart Engineering Inc. $3,270,486.00 Steelhead Constructors JV $3,792,051.00 STPG Malcom JV LLC $4,211,274.46 Engineer's Estimate $3,980,000.00

12 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: X

Schedule Type: Options

Solcitation No: 6982AF23B000012

Division: Central Federal Lands

State: CA County: Plumas

Federal Land: Plumas National Forest Opened at: Lakewood, CO

Opened by: Eric Grosskreuz

Date: 09/28/23

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Steelhead Constructors JV $431,000.00 PO Box 536 Palo Cedro, CA 96073

STPG Malcom JV LLC $453,170.00 3700 Centerpoint Drive, Suite 8155 Anchorage, AK 99503

SEB Engineering Inc. dba Stewart Engineering Inc. $471,000.00 P.O. Box 990010 Redding, CA 96099

Engineer's Estimate $498,000.00

13 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X1000 15101-0000 MOBILIZATION

Steelhead Constructors JV Lump Sum $187,000.00 STPG Malcom JV LLC Lump Sum $48,375.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $65,600.00

X1020 15214-1000 SURVEY AND STAKING, BRIDGE (INDIAN CREEK BRIDGE)

Steelhead Constructors JV Lump Sum $6,700.00 STPG Malcom JV LLC Lump Sum $3,600.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $7,500.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

X1040 15301-0000 CONTRACTOR QUALITY CONTROL

Steelhead Constructors JV Lump Sum $15,000.00 STPG Malcom JV LLC Lump Sum $41,445.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $65,000.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00

X1060 15401-0000 CONTRACTOR TESTING

Steelhead Constructors JV Lump Sum $3,900.00 STPG Malcom JV LLC Lump Sum $7,200.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $2,000.00 Engineer's Estimate ALL LPSM Lump Sum $11,000.00

X1080 15501-0000 CONSTRUCTION SCHEDULE

Steelhead Constructors JV Lump Sum $2,200.00 STPG Malcom JV LLC Lump Sum $2,100.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

X1100 15701-0000 SOIL EROSION CONTROL (INDIAN CREEK BRIDGE)

Steelhead Constructors JV Lump Sum $1,300.00 STPG Malcom JV LLC Lump Sum $6,500.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $3,200.00 Engineer's Estimate ALL LPSM Lump Sum $22,000.00

14 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO FS PLMAS 2021-02(1)

Project Name: North Fork Feather River Bridge

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X1120 20304-2000 REMOVAL OF BRIDGE (INDIAN CREEK BRIDGE)

Steelhead Constructors JV Lump Sum $25,000.00 STPG Malcom JV LLC Lump Sum $15,810.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $65,000.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00

X1140 55401-1000 REINFORCING STEEL (INDIAN CREEK BRIDGE)

Steelhead Constructors JV $12.00 $2,400.00 STPG Malcom JV LLC $50.00 $10,000.00 SEB Engineering Inc. dba Stewart Engineering Inc. $26.00 $5,200.00 Engineer's Estimate 200 LB $10.00 $2,000.00

X1160 55504-0000 PRE-FABRICATED STEEL BRIDGE

Steelhead Constructors JV Lump Sum $125,000.00 STPG Malcom JV LLC Lump Sum $295,100.00 SEB Engineering Inc. dba Stewart Engineering Inc. Lump Sum $176,300.00 Engineer's Estimate ALL LPSM Lump Sum $250,000.00

X1180 60101-0000 CONCRETE

Steelhead Constructors JV $30,000.00 $60,000.00 STPG Malcom JV LLC $9,520.00 $19,040.00 SEB Engineering Inc. dba Stewart Engineering Inc. $32,300.00 $64,600.00 Engineer's Estimate 2 CUYD $10,000.00 $20,000.00

X1200 62301-0000 GENERAL LABOR (INDIAN CREEK BRIDGE)

Steelhead Constructors JV $125.00 $2,500.00 STPG Malcom JV LLC $200.00 $4,000.00 SEB Engineering Inc. dba Stewart Engineering Inc. $110.00 $2,200.00 Engineer's Estimate 20 HOUR $120.00 $2,400.00

Total Schedule - All Items

Steelhead Constructors JV $431,000.00 STPG Malcom JV LLC $453,170.00 SEB Engineering Inc. dba Stewart Engineering Inc. $471,000.00 Engineer's Estimate $498,000.00

2023-10-03T13:48:49-0600
ERIC J GROSSKREUZ