QnA_3.19.19.pdf

PDF 68 KB Posted

Attached to
NE FTFW FTNI 205(1), Buffalo Bridge Federal contract opportunity
Solicitation number
6982AF19B00001
Issued by
Department of Transportation Federal Highway Administration

View the file

Other files for this federal contract opportunity

Other files attached to NE FTFW FTNI 205(1), Buffalo Bridge, newest first.
File Type Posted
Bid_Tabs.pdf PDF
Bid_Opening_Summary_NE_FTFW_FTNI_205(1).pdf PDF
6982AF19B000001.pdf PDF
Buffalo_Bridge_Inspection_Report_2016.pdf PDF
NE_FTFW_FTNI_205(1)_Signed.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

NE FTFW FTNI 205(1) Buffalo Bridge

March 19, 2019

Questions Answers

1 In reference to the Soil Erosion Control, Filter Bag. Is it a filter bag or a filter sock? Where is the location of these items to be placed? I can’t find any information in the specifications or on the drawings.

Dewatering is the responsibility of the contractor. The filter bag is for filtering that water prior to it returning to the stream. Placement and maintenance are the responsibility of the contractor. Other erosion and sediment control measures are to be used if needed. Follow manufacturers recommendations.

2 Would it be acceptable to coffer dam one pier at a time in lieu of coffer dam both piers individually at the same time?

The contractor will need to ensure that safe passage under the bridge for non-motorized recreational use is maintained; otherwise, there are no stipulations regarding the use of the coffer dams.