Bridge_Inspection_Report_STR__4290-022P.pdf
PDF 5 MB Posted
- Attached to
- Colonial National Historical Park Federal contract opportunity
- Solicitation number
- 693C73-18-B-000028
About this file
Bridge Inspection Report_STR# 4290-022P
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Results_of_Bid_Opening_-_NP-COLO_1B37,_1D46.pdf | ||
| Plans_-_NP-COLO_1B37,_1D46.pdf | ||
| Kings_Creek_As-Built.pdf | ||
| Bridge_Inspection_Report_STR__4290-012P.pdf | ||
| FP14_Eng.pdf | ||
| Halfway_Creek_As-Built.pdf | ||
| Bridge_Inspection_Report_STR__4290-011P.pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| IFB_Solicitation_-_NP-COLO_1B37,_1D46.pdf | ||
| Felgate's_Creek_As-Built.pdf | ||
| Certification_Program_for_Bridge_Temporary_Works.pdf | ||
| VETS-4212_Form.pdf | ||
| NEPA_(Categorical_Exclusion_Form).pdf | ||
| Synopsis_-_NP-COLO_1B37,_1D46.doc | DOC document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STRUCTURE SUMMARY STRUCTURE NO. 4290-022P
HALFWAY CREEK BRIDGE INSPECTION DATE: 6/14/17
BRIDGE IDENTIFICATION AND DESCRIPTION
MAIN SPAN MATERIAL: ....... CONCRETE NO. OF MAIN SPANS:
MAIN SPAN TYPE: ............... TEE BEAM NO. OF APPR. SPANS:
# OF BEAMS, MAIN SPAN: .. 5 STRUCT. TOTAL LENGTH: .. 851.7 FT (259.6 M)
DECK TYPE: ......................... CONCRETE CAST-IN-PLACE MAX. SPAN LENGTH: .......... 56.7 FT (17.3 M)
WEARING SURFACE: .......... MONOLITHIC CONCRETE DECK WIDTH: ...................... 36.7 FT (11.2 M)
ABUT. FOUNDATIONS: ........ SPREAD FOOTING ON PILES CURB TO CURB WIDTH: ..... 30.0 FT (9.1 M)
PIER FOUNDATION(S): ........ SPREAD FOOTING ON PILES YEAR BUILT:
ABUTMENT / PIER MAT'L: ... CONCRETE YEAR RECONSTRUCTED: .. N/A
PROJ./PLAN REF. NO: ......... 1D4 / NONE SKEW ANGLE: ..................... 0 °
NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD FRACTURE CRITICAL: ........ NO
STRUCTURE HISTORY: ...... 1985-Joint repair. 2004-Railing repair. 2003, 2008-Underwater insp. 2011-Concrete repairs to deck, super, and subst; Riprap placed at N Abut; Deck exp joints sealed.
LOCATION
COLONIAL NATIONAL HISTORICAL PARK MILE POINT: ..................... 15.36 (KM PT 24.72)
STATE: ................................. VIRGINIA LOCATION: 0.9 MILES SOUTH OF ROUTE 199.
FACILITY CARRIED: ............ COLONIAL PARKWAY
FEATURE INTERSECTED: .. HALFWAY CREEK
STRUCTURE EVALUATION SUMMARY
This concrete tee-beam bridge has some problem areas that are pressing and need to be addressed. Several areas of concrete spalling are present, primarily in the deck underside, beams, and substructure, and several previously repaired (in 2011) areas are deteriorating as well.
The delamination and spalling of the bearing areas at the pier caps appears to be progressing, as evidenced by a new spall on the south side of the west end of the Pier #14 cap. The spall has resulted in a loss of bearing for the full width of the steel bearing plate by up to 1/2" wide. The bridge plans indicate the bearing plate as actually the top flange of an embedded tee section, which provides significant capacity for the bearing for the time being. Regardless, to help ensure safe use of the bridge, this and other delaminated and spalled bearing areas should be addressed with a more comprehensive and effective repair project in the near future.
This structure is scheduled for rehabilitation under Project No. COLO 1B37, 1D46. The scope of this project includes repair of all deteriorated concrete on the piers, deck underside, abutments, beams and diaphragms, install scupper extensions, and reseal the deck expansion joints.
INSPECTION TEAM: G. GOODLIN, Z. BAILEY
CONDITION ASSESSMENT:
GARY J. GOODLIN, FIELD TEAM LEADER 703-404-6253
REPORT REVIEW:
MARCUS MILLER, P.E., BRIDGE INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 10/31/17
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 4290-022P
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure exhibits severe deterioration, presents a safety hazard, or is designated a high priority due to age and/or condition.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
C226 PRIORITY OF IMPROVEMENT
ITEM
NO.
MAINTENANCE RECOMMENDATIONS
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT COST
UNIT
ESTIMATE
COST
PRELIM.
PRELIM. MAINTENANCE TOTAL :
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS)
QTY. UNIT
UNIT
COST ESTIMATES
PRELIM. COST
REHAB. RECONSTR.
60.13,15 REMOVE UNSOUND CONCRETE FROM PIER CAPS AND COLUMNS,
CLEAN REBAR, AND PLACE NEW CONCRETE TO ORIGINAL
DIMENSIONS.
1 LS
58.1 CLEAN AND SEAL DECK SURFACE. 1 LS
58.2 CLEAN AND RESEAL DECK EXPANSION JOINTS AS NECCESSARY. 1 LS
58.7, 59.2 EXTEND SCUPPERS TO ALLOW DRAINAGE TO CLEAR CONCRETE
BEAMS.
1 LS
58.1,5,6, 59.2
CLEAN EXPOSED REBAR THROUGHOUT DECK UNDERSIDE,
RAILINGS, AND BEAMS AND COAT WITH AN APPROVED SEALANT.
1 LS
58.1 SEAL CRACKS IN DECK SURFACE AS NECESSARY. 1 LS
58, 59, 60 CONTRACT COSTS FOR MOBILIZATION, TRAFFIC CONTROL, AND
DESIGN CONSTRUCTION ENGINEERING (70% TOTAL REHAB COST)
PLUS PARK LOCATION FACTOR.
1 LS
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
REMARKS: Cost estimates assume that the recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 4290-022P
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
Fatigue cracks in steel or shear cracks in concrete may be present.
CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
“IMMINENT” FAILURE CONDITION - major deterioration or sec ion loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.
FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
NOT APPLICABLE
EXCELLENT CONDITION
VERY GOOD CONDITION - no problems noted.
GOOD CONDITION - some minor problems.
SATISFACTORY CONDITION - structural elements show some minor deterioration.
FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
POOR CONDITION - advanced section loss, deterioration, spalling, or scour.
N
58. DECK ITEM REFERENCE AND REMARKS
OTHER
ALIGNMENT
DEFLECTION AND/OR VIBRATION
FASCIA(E)
DIAPHRAGMS AND BRACING
TRUSSES
FLOOR BEAMS AND STRINGERS
ARCH(ES) OR SLAB(S)
GIRDERS OR BEAMS
BEARING DEVICES
59. SUPERSTRUCTURE
OTHER
DEFLECTION AND/OR VIBRATION
UTILITIES
DRAINS AND DRAINAGE
PARAPETS AND/OR RAILINGS
CURBS, SIDEWALKS, AND MEDIAN
RIDEABILITY
WEARING SURFACE
EXPANSION JOINTS
DECK SLAB
OTHER
SETTLEMENT OR DEFLECTION
EROSION AND/OR SCOUR
FOUNDATIONS
CAPS AND/OR BEARING SEATS
PILE BENTS
WALLS AND/OR COLUMNS
PIER(S)
OTHER
SLOPE PROTECTION
SETTLEMENT OR DEFLECTION
EROSION AND/OR SCOUR
EXPANSION JOINTS
WEEP HOLES
WINGWALLS
FOUNDATIONS
BACKWALLS AND/OR BULKHEADS
CAPS AND/OR BEARING SEATS
PILE BENTS
BREASTWALLS OR COLUMNS
ABUTMENTS
60. SUBSTRUCTURE
1.
10.
2.
3.
4.
5.
6.
7.
8.
9.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
PAINT
11.
F F N N N F N N G
N F
G N G G N G N N G G G
G(ENCLOSED SPAN)
F N F N G G N
11.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
12.
13.
14.
15.
16.
17.
18.
19.
58.1 WIDESPREAD MINOR TO MODERATE MAP, LONGITUDINAL, AND
DIAGONAL CRACKING (UP TO 1/16"W) AND WIDESPREAD SCALING
OF DECK SURFACE. MINOR TRANSVERSE CRACKING OF DECK
SURFACE IN SPANS #1 AND #2. MINOR EDGE SPALLING OF DECK
SURFACE ALONG EXPANSION JOINTS AT ISOLATED LOCATIONS.
NUMEROUS REPAIRED AREAS IN DECK SURFACE; ISOLATED AREAS
OF DELAMINATION AND SPALLING REMAIN. MAP CRACKING OF
REPAIRS AT ISOLATED LOCATIONS.
NUMEROUS REPAIRED AREAS IN DECK UNDERSIDE; MINOR
CRACKING OF REPAIRS. MINOR SPALLING OF DECK UNDERSIDE
WITH EXPOSED REBAR DUE TO INADEQUATE CONCRETE COVER AT
ISOLATED LOCATIONS, ESPECIALLY NEAR SCUPPERS. MINOR
DELAMINATION OF DECK UNDERSIDE AT ISOLATED LOCATIONS.
MINOR TRANSVERSE, LONGITUDINAL, AND DIAGONAL CRACKING,
SOME WITH EFFLORESCENCE, ON DECK UNDERSIDE; SOME
CRACKS HAVE REFLECTED THROUGH FROM DECK SURFACE.
MINOR VERTICAL CRACKING OF OUTSIDE FACES OF DECK;
NUMEROUS REPAIRED AREAS.
58.2 ISOLATED LOCATIONS OF MINOR TEARS OR MISSING SECTIONS
AND ADHESION FAILURE OF DECK EXPANSION JOINT SEALANT.
58.5 MINOR VERTICAL AND MAP CRACKING AND SCALING OF CURBS.
NUMEROUS REPAIRED AREAS IN CURBS; ISOLATED AREAS OF
MINOR SPALLING REMAIN.
SURVEY MARKER ON EAST CURB AT BOTH APPROACHES.
58.6 MINOR CRACKING OF RAILINGS AT EXPANSION JOINTS AND
ELSEWHERE. MINOR SPALLING WITH EXPOSED REBAR ON
RAILINGS AT ISOLATED AREAS.
58.7 MINOR ACCUMULATION OF SAND AND GRAVEL ALONG CURBLINES.
MINOR TO MODERATE ACCUMULATION OF SAND AND DEBRIS
ALONG SIDEWALK. SEE ALSO 59.2.
59.1 MODERATE RUSTING OF STEEL BEARING PLATES WITH MINOR
SECTION LOSS.
N G G G F N
N
F
G
F
ITEM REFERENCE AND REMARKS
STREAM BED COMPOSITION : 9.
AVERAGE CLEAR OPENING 8.
NORMAL VELOCITY 7.
ADEQUACY OF OPENING 6.
OTHER 5.
WATERWAY OBSTRUCTIONS 4.
CHANNEL PROTECTION 3.
EROSION AND/OR SCOUR 2.
ALIGNMENT 1.
61. CHANNEL 8
G G N G G
LOW
SUFF
12 FT.
SILT
222. APPROACHES 6
OTHER 9.
ALIGNMENT 8.
SIGNS 7.
SETTLEMENT 6.
EROSION 5.
SURFACING 4.
APPROACH GUARDRAIL 3.
RELIEF JOINTS 2.
1. APPROACH SLABS F
G G G G G F G N
223. RETAINING WALL N
OTHER 6.
SETTLEMENT OR DEFLECTION 5.
EROSION AND/OR SCOUR 4.
FOUNDATION 3.
WEEP HOLES 2.
1. WALL
36. TRAFFIC AND SAFETY FEATURES
APPROACH GUARDRAIL ENDS D.
APPROACH GUARDRAILS C.
TRANSITIONS B.
BRIDGE RAILINGSA. 1
TRAFFIC SAFETY RATING CODES
0 - Does not meet standards or a safety feature is required and none is provided.
1 - Meets currently acceptable standards.
N - Not applicable or a safety feature is not required.
59.2,6 REINFORCED CONCRETE TEE-BEAM SUPERSTRUCTURE;
SCUPPERS DRAIN DIRECTLY ONTO INSIDE FACE OF EXTERIOR
BEAMS, RESULTING IN MODERATE SCALING.
NUMEROUS REPAIRED AREAS IN BEAMS AND DIAPHRAGMS; MINOR
CRACKING OF REPAIRS. MINOR DELAMINATION ON UNDERSIDE OF
BEAMS AT ISOLATED LOCATIONS. WIDESPREAD MINOR CRACKING
AND ISOLATED AREAS OF MINOR SPALLING WITH EXPOSED REBAR
ON BEAMS AND DIAPHRAGMS. MINOR VERTICAL CRACKING OF
EXTERIOR FACE OF BEAMS. MINOR TO MODERATE DIAGONAL
CRACKING AND MINOR DELAMINATION OF ENDS OF EXTERIOR
BEAMS. MODERATE SPALLING OF BEAM ENDS DUE TO RUSTING OF
BEARING PLATES AT ISOLATED LOCATIONS. SEE ALSO 59.1.
MODERATE CRACKING, DELAMINATION, AND SPALLING OF WEST
FACE OF BEAM #1 AT NORTH ABUTMENT. MINOR LONGITUDINAL
CRACK WITH EFFLORESCENCE ALONG INTERFACE BETWEEN BOTH
SIDES OF BEAM #2 AND DECK NEAR NORTH ABUTMENT.
MINOR VERTICAL CRACKING OF END DIAPHRAGMS.
59.10 DECK AND SUPERSTRUCTURE APPEAR TO HAVE SHIFTED
LATERALLY AT SEVERAL SPANS (UP TO 1"); NO CHANGE SINCE LAST
INSPECTION.
60.1 MINOR VERTICAL AND MAP CRACKING OF ABUTMENT
BREASTWALLS. MINOR CRACKING WITH EFFLORESCENCE ON
SOUTH ABUTMENT BREASTWALL, BOTH SIDES.
60.6 MINOR TO MODERATE HORIZONTAL AND MAP CRACKING WITH
EFFLORESCENCE ON WINGWALLS.
60.11 NORTH ABUTMENT SLOPE PROTECTED WITH RIPRAP.
60.12 ENCLOSED SPANS AT BOTH ABUTMENTS.
ADDITIONAL ITEM REFERENCE AND REMARKS
60.13,15 NUMEROUS REPAIRED AREAS IN PIER COLUMNS; MINOR CRACKING OF REPAIRS. MINOR VERTICAL CRACKING, DELAMINATION, AND SPALLING OF PIER COLUMNS (BOTH CONCRETE AND GRANITE PORTIONS);
EFFLORESCENCE AND RUST STAINING AT SOME LOCATIONS. MODERATE SPALLING WITH EXPOSED REBAR AT
ISOLATED LOCATIONS .
NUMEROUS REPAIRED AREAS IN PIER CAPS. MINOR CRACKING, SPALLING, AND DELAMINATION OF SEVERAL PIER CAPS DUE TO INADEQUATE CONCRETE COVER AT ISOLATED LOCATIONS. MINOR TO MODERATE SPALLING WITH EXPOSED REBAR BELOW BEARINGS AT ISOLATED LOCATIONS. MODERATE SPALL (21"W X 38"H X 6"D) WITH EXPOSED REBAR IN PREVIOUSLY REPAIRED AREA AT SOUTHWEST CORNER OF PIER #14, RESULTING IN LOSS OF
BEARING FOR FULL WIDTH OF BEARING PLATE X UP TO 1/2"W.
MODERATE VERTICAL CRACKING WITH HEAVY EFFLORESCENCE AT CENTERLINE OF BOTH EXTERIOR FACES OF
EACH PIER EXTENDING FULL HEIGHT OF COLUMNS AND CAPS.
61.2 MINOR EROSION OF SOUTH CHANNEL BANK BELOW STRUCTURE.
222.1 MINOR EDGE SPALLING OF BOTH ABUTMENT SLABS ALONG JOINTS. MINOR MAP AND TRANSVERSE CRACKING OF NORTH ABUTMENT SLAB; MODERATE FULL-DEPTH DIAGONAL CRACKING OF SOUTHEAST CORNER.
222.2 MINOR DETERIORATION OF RELIEF JOINT SEALS AT BOTH APPROACHES. MINOR VEGETATION GROWTH AT
SOUTH APPROACH RELIEF JOINTS.
222.3 MINOR TO MODERATE CHECKING AND SPLINTERING OF TIMBER APPROACH GUARDRAILS; VEGETATION GROWTH
AT TRANSITIONS.
222.7 REFLECTORS ON ENDS OF NORTHWEST AND SOUTHEAST PARAPETS ARE NOT VISIBLE BEHIND TIMBER
APPROACH GUARDRAILS.
"HALFWAY CREEK" SIGN AT WEST SIDE OF NORTH APPROACH AND EAST SIDE OF SOUTH APPROACH.
STRUCTURE LOAD RATING STRUCTURE NO. 4290-022P
TRUCK TYPE
INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)
TONS METRIC TONS TONS METRIC TONS
H 20 18 33 30
HS 25 23 42 38
TYPE 3 23 21 39 35
TYPE 3S2 36 33 60 54
TYPE 3-3 44 40 74 67
DESIGN LOADING: H15 (M13.5)
X CAPACITY MEETS OR EXCEEDS DESIGN LOAD
CAPACITY IS LESS THAN DESIGN LOAD
ORIGINAL LOAD RATING CALCULATION APPLICABLE
ORIGINAL LOAD RATING CALCULATION REVISED
DATE OF LOAD RATING CALCULATION: 1/15
LOAD RATING CONTROLLED BY: BEAM MOMENT CAPACITY
REMARKS: RATING IS BASED ON DESIGN LOAD OF STRUCTURE.
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 4290-022P
STRUCTURE IDENTIFICATION
(201) PARK: COLONIAL NATIONAL HISTORICAL PARK (1) STATE: ....................................... 513 - VIRGINIA (VA)
(202) STRUCTURE NAME: .......... HALFWAY CREEK BRIDGE (2) STATE HWY. AGENCY DIST:
(203) STRUCTURE KIND: ............ 1 - BRIDGE (3) COUNTY CODE: ........................ 095 - JAMES CITY
(204) STRUCTURE NUMBER: ..... 4290-022P (4) CITY/PLACE CODE:
(205) NPS REGION: .................... 3 - NORTHEAST (5) INVENTORY ROUTE:
(206) ROUTE CODE NUMBER: ... 1 (6) FEATURES INTERSECTED:....... HALFWAY CREEK
(207) ROAD SECTION NO: .......... 022P (7) FACILITY CARRIED: .................. COLONIAL PARKWAY
(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 4290022P0000000
(209) WITHIN NPS BNDRY?: ....... YES (9) LOCATION: ................................ 0.9 MILES SOUTH OF ROUTE
(210) OPERATING UNIT: ............. PARK (10) INV. RTE. - MIN. VERT. CLR: .. 99.99 FT (99.99 M)
(211) PROJECT NO(S): ................ 1D4 (11) MILE POINT: ............................. 15.36 (KM PT 24.72)
(212) DRAWING NUMBERS: ....... NONE (27) YEAR BUILT:
(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED: .... N/A
(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................ 3 - FREE ROAD
(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL: ..
(43B) MAIN STR. TYPE:
(45) NO. OF MAIN SPANS:
(48) MAX. SPAN LENGTH:
(49) STRUCTURE LENGTH:
(216A) ABUTMENT #1 FDN:
(216B) ABUTMENT #2 FDN:
(217A) PREDOM. PIER FDN.: ..
(217B) SECOND. PIER FDN: ...
(107) DECK TYPE:
1 - CONCRETE
04 - TEE BEAM
56.7 FT (17.3 M)
851.7 FT (259.6 M)
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
1 - CONCRETE CAST-IN-PLACE
(44A) APPR. STR. MATERIAL: ........ 0 - OTHER
(44B) APPR. STR. TYPE: ................ 00 - OTHER
(46) NO. OF APPROACH SPANS: .. 0
(108) WEAR SURFACE/PROTECT SYSTEM:
A) TYPE WEARING SURFACE: .. 1 - MONOLITHIC CONCRETE
B) TYPE MEMBRANE: ................. 0 - NONE
C) TYPE PROTECTION: .............. 0 - NONE
(218) IS SALT USED?: ..................... YES
LOAD RATING AND POSTING
(31) DESIGN LOAD: ................. 2 - H15 (M13.5) (41) LOAD RESTRICTION: ......... A - OPEN, NO RESTRICTION
(66) INVENTORY RATING: ...... 25.0 TONS (22.7 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED
(64) OPERATING RATING: ...... 42.0 TONS (38.1 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 6/17 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO
INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE
(B) UNDERWATER: .............. YES
(221) SPECIAL STUDY DATE: INSP. EVERY: 60 MONTHS - LAST INSP. : 6/13
(C) SPECIAL INSPECTION: .. NO
INSP. EVERY: MONTHS - LAST INSP. :
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 4290-022P
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(51) CURB TO CURB WIDTH: ........... 30.0 FT (9.1 M)
(16) LATITUDE: ............................. 37°14'01.90"
(17) LONGITUDE: ......................... 76°41'49.30"
(19) DETOUR LENGTH: ............... 5 MI (8 KM)
(28A) LANES ON STRUCT:
(28B) LANES UNDER STRUCT: ... 00
(42A) SERVICE ON: ..................... 5 - HIGHWAY-PEDESTRIAN
(42B) SERVICE UNDER: .............. 5 - WATERWAY
(29) AVG. DAILY TRAFFIC:
(30) YEAR OF ADT:
(114) FUTURE ADT:
(115) YEAR OF FUTURE ADT:
(101) PARALLEL STRUCTURE: ... N - NONE
(38) NAVIGATION CONTROL?: ... 0
(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)
(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)
(111) ABUT. OR PIER PROT:
LATERAL UNDERCLEARANCE:
(55) RIGHT: ....................... 0.0 FT (0.0 M)
(56) LEFT: ......................... 0.0 FT (0.0 M)
(52) DECK WIDTH:
(32) APPR. ROADWAY WIDTH:
(213) APPR. PAVEMENT WIDTH:
LEFT SHOULDER:
RIGHT SHOULDER:
(33) BRIDGE MEDIAN:
(34) SKEW ANGLE:
(35) DECK FLARE?:
(47) TOTAL HORIZ. CLEARANCE:
(50) SIDEWALKS:
LEFT :
RIGHT :
(214) BRIDGE RAIL TYPE:
RAIL CONFIGURATION:
MATERIAL:
DESIGN TYPE:
(215) BRIDGE RAIL HEIGHT:
(53) MIN. VRT. CLEAR. OVER DECK:
(54) MIN. VRT. UNDERCLEARANCE:
36.7 FT (11.2 M)
40.0 FT (12.2 M)
30.0 FT (9.1 M)
5.0 FT (1.5 M)
5.0 FT (1.5 M)
0 - NO MEDIAN
0 °
NO
30.0 FT (9.1 M)
3.0 FT (0.9 M)
0.0 FT (0.0 M)
1 - FULL HEIGHT (NO PARAPE
1 - CONCRETE
1 - CONTINUOUS RAIL
2.50 FT (0.76 M)
99.99 FT (99.99 M)
0.00 FT (0.00 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK:
(59) SUPERSTRUCTURE:
(60) SUBSTRUCTURE:
(61) CHANNEL:
(62) CULVERT: ........................... N
(222) APPROACHES:
(223) RETAINING WALL: ........... N
(36) TRAFFIC SAFETY FEAT: ... 1111
(75A) TYPE OF WORK:
(75B) WORK DONE BY:
(76) IMPROVEMENT LENGTH: ..
(67) STRUCTURAL EVALUATION:
(68) DECK GEOMETRY:
(69) UNDERCLEARANCES:
(71) WATERWAY ADEQUACY:
(72) APPROACH ALIGNMENT:
(113) SCOUR CRITICAL:
(225) PURPOSE OF IMPROVEMENT:
(226) PRIORITY OF IMPROVEMENT:
(227) MAINTENANCE COST:
(228) REHAB./RECONSTR. COST: ...
(229) CONSTRUCTION COST:
N
T - Tidal. Low risk. Not yet evalu
2 - REHAB/RECONSTRUCTION
C - MODERATE
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
1985-Joint repair. 2004-Railing repair. 2003, 2008-Underwater insp. 2011-Concrete repairs to deck, super, and subst; Riprap placed at N Abut;
Deck exp joints sealed.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIG. INFO.:
http:76�41'49.30 http:37�14'01.90
APPENDIX STRUCTURE NO. 4290-022P
PHOTOGRAPHS STRUCTURE NO. 4290-022P
PHOTO #1 - LOOKING NORTH TOWARD WILLIAMSBURG
FLOW
PHOTO #2 - EAST (UPSTREAM) SIDE
PHOTO #3 - GENERAL TOPSIDE VIEW OF STRUCTURE LOOKING SOUTH
PHOTO #4 - TYPICAL DIAGONAL CRACKING AND WIDESPREAD
SCALING OF DECK SURFACE, SPAN #15 SHOWN
PHOTO #5 - TYPICAL DIAGONAL CRACKING AND WIDESPREAD
SCALING OF DECK SURFACE, SPAN #1 SHOWN; ALSO NOTE EDGE
SPALLING OF DECK SURFACE ALONG EXPANSION JOINTS
PHOTO #6 - TYPICAL TRANSVERSE CRACKING OF DECK SURFACE IN
SPANS #1 AND #2, SPAN #1 SHOWN
PHOTO #7 - TYPICAL REPAIRED AREAS IN
DECK SURFACE WITH MAP CRACKING, SPAN
#10 SHOWN
PHOTO #8 - TYPICAL TEARS AND ADHESION
FAILURE OF DECK EXPANSION JOINT
SEALANT, JOINT OVER PIER #9 SHOWN
PHOTO #9 - TYPICAL SPALLING AND CRACKING REPAIRED AREA OF
CURBS, WEST CURB IN SPAN #12 AT PIER #12 SHOWN
PHOTO #10 - TYPICAL SCALING OF CURBS, WEST CURB IN SPAN #5 AT
PIER #4 SHOWN
PHOTO #11 - TYPICAL SPALLING WITH EXPOSED REBAR ON RAILINGS,
WEST RAILING IN SPAN #13 SHOWN
PHOTO #12 - DECK AND SUPERSTRUCTURE APPEAR TO HAVE SHIFTED
LATERALLY AT SEVERAL SPANS, SHIFTED RAILING IN SPAN #4 OVER
PIER #3 SHOWN
PHOTO #13 - FULL-DEPTH DIAGONAL
CRACKING OF NORTH ABUTMENT SLAB AT
SOUTHEAST CORNER
PHOTO #14 - TYPICAL DETERIORATION OF
RELIEF JOINT SEALS AT BOTH APPROACHES,
SOUTH APPROACH SHOWN
PHOTO #15 - REFLECTOR AT END OF
NORTHWEST PARAPET NOT VISIBLE BEHIND
TIMBER APPROACH GUARDRAIL; ALSO NOTE
TYPICAL CRACKING OF RAILINGS
PHOTO #16 - GENERAL UNDERSIDE VIEW OF
STRUCTURE IN SPAN #2 LOOKING NORTH
PHOTO #17 - TYPICAL DIAGONAL CRACKING, SOME WITH
EFFLORESCENCE, ON DECK UNDERSIDE, SPAN #15 BETWEEN BEAMS
#4 AND #5 SHOWN
PHOTO #18 - TYPICAL SPALLING OF DECK UNDERSIDE WITH EXPOSED
REBAR AT ISOLATED LOCATIONS, ESPECIALLY NEAR SCUPPERS,
BETWEEN BEAMS #1 AND #2 IN SPAN #4 SHOWN
PHOTO #19 - TYPICAL VERTICAL CRACKING OF
OUTSIDE FACES OF DECK AND EXTERIOR
FACE OF BEAMS, EAST SIDE IN SPAN #2
SHOWN
PHOTO #20 - SCUPPERS DRAIN DIRECTLY
ONTO INSIDE FACE OF EXTERIOR BEAMS,
SPAN #15 AT BEAM #1 SHOWN
PHOTO #21 - CRACKING, DELAMINATION, AND
SPALLING OF WEST FACE OF BEAM #1 AT
NORTH ABUTMENT
PHOTO #22 - TYPICAL DELAMINATION ON
UNDERSIDE OF BEAMS; BEAM #2 IN SPAN #4
SHOWN; ALSO NOTE TYPICAL SPALLING WITH
EXPOSED REBAR ON BEAMS
PHOTO #23 - TYPICAL LONGITUDINAL CRACK WITH EFFLORESCENCE
ALONG INTERFACE BETWEEN BOTH SIDES OF BEAM #2 AND DECK
NEAR NORTH ABUTMENT, WEST SIDE SHOWN
PHOTO #24 - TYPICAL SPALLING WITH EXPOSED REBAR ON
DIAPHRAGMS, BETWEEN BEAMS #1 AND #2 IN SPAN #3 AT PIER #2
SHOWN
PHOTO #25 - CRACKING ON EXTERIOR SIDE
OF WEST BEAM ENDING ON PIER #14
PHOTO #26 - TYPICAL CRACKING WITH
EFFLORESCENCE ON SIDES OF SOUTH
ABUTMENT BREASTWALL, EAST SIDE SHOWN
PHOTO #27 - TYPICAL HORIZONTAL AND MAP CRACKING WITH
EFFLORESCENCE ON WINGWALLS, NORTHWEST WINGWALL SHOWN
PHOTO #28 - EROSION OF SOUTH CHANNEL BANK BELOW STRUCTURE
PHOTO #29 - SPALL WITH EXPOSED REBAR IN
PREVIOUSLY REPAIRED AREA AT SOUTHWEST
CORNER OF PIER #14
PHOTO #30 - SPALL WITH EXPOSED REBAR IN
PREVIOUSLY REPAIRED AREA AT SOUTHWEST
CORNER OF PIER #14
PHOTO #31 - CLOSE-UP OF PREVIOUS PHOTO; NOTE LOSS OF
BEARING
PHOTO #32 - TYPICAL SPALLING WITH EXPOSED REBAR ON PIER CAPS
BELOW BEARINGS, SOUTH SIDE OF PIER #4 SHOWN
PHOTO #33 - TYPICAL VERTICAL CRACKING
WITH EFFLORESCENCE AT CENTERLINE OF
EXTERIOR FACES OF PIERS, EAST COLUMN AT
PIER #1 SHOWN; ALSO NOTE TYPICAL
DELAMINATION OF PIER CAPS AND COLUMNS
WITH RUST STAINING
PHOTO #34 - UPSTREAM CHANNEL
PHOTO #35 - DOWNSTREAM CHANNEL