QA_15_march_21.pdf
PDF 106 KB Posted
- Attached to
- OR DOT 140(3), Mitigation Site for OR 140 Federal contract opportunity
- Solicitation number
- 69056721B000002
About this file
This document contains answers to technical questions regarding Federal Highway Administration Solicitation Number 69056721B000002 for the OR DOT 140(3) Mitigation Site for OR 140 project. Key details include that the project manager is Helen Oppenheimer, there is no prebid conference scheduled, the project has a total small business set-aside classification, and the Erosion Control Supervisor is not required to be on-site full-time. Testing requirements include maximum theoretical density and moisture content per specifications. The contractor is responsible for aquatic life salvage and rescue. Seeding is required for water and swell areas per the NPDES permit despite water level fluctuations, and all bare areas must be covered.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary_OR DOT 140(3).pdf | ||
| QA_16_march_21.pdf | ||
| QA_11_March_21.pdf | ||
| QA_8_March_21.pdf | ||
| QA_4_March_21.pdf | ||
| GR10-17 OR-140 Prelim Geotech Charact Report.pdf | ||
| or-14003 DITCH D HA-VA.pdf | ||
| or-14003 DITCH E HA-VA.pdf | ||
| Compiled OR 140 Mitigation digiESCPFinal.pdf | ||
| or-14003 DITCH A HA-VA.pdf | ||
| IFB_OR DOT 140(3).pdf | ||
| GR27-18 Final Geotech Report OR DOT 140(1) Klamath County Boat Marina to Lakeshore Dr.pdf | ||
| GM44-19 OR-140 MItigation Site Geotech Memo.pdf | ||
| or-14003 DITCH B HA-VA.pdf | ||
| or-14003 BERM HA-VA.pdf | ||
| or-14003 DITCH C HA-VA.pdf | ||
| or-14003_Control-Sheet.xlsx | XLSX spreadsheet | |
| Finalized or-14003_plans.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. OR DOT 140(3) Project: Mitigation Site for OR 140
# General Technical Question Answer Date
1 X Who is the project manager for this project? Helen Oppenheimer. See Bottom left hand side of sheet A.1 of the plan set.
4‐Mar‐21
2 X Is there going to be a pre‐bid conference? No. See The notice to Bidders
4‐Mar‐21
3 X Is there a prequalification to bid this project? This Project is a Total Small Business Set‐Aside. See Classification for this project on the Beta.Sam solicitation information. 4‐Mar‐21
4 X Is the Erosion Control Supervisor (ECS) required to be on the project site full time?
No, the ECS is required to be present on the project to perform the required duties as stipulated in Section 157 of the FP‐14 and the SCR’s
8‐Mar‐21
5 X specification 103.05 Partnering. I have read through the spec but do not feel confident that I understand it completely. Can you explain the Formal Partnering or do I need to talk to Helen Oppenheimer
FORMAL PARTNERING as used in section 103.05 the Government has agreed to pay for a portion of the direct costs (UP TO $5,000.00) that may be associated with the Partnering process. Which may include the partnering facilities, professional facilitation, copying fees, and other miscellaneous costs directly related to partnering meetings.
Please do not contact Helen Oppenheimer regarding question concerning this project. Instead contact wfl.plans‐spec: mailto:wfl.plans‐ spec@dot.gov
8‐Mar‐21
6 X Referencing Section 107.08:
If a contractor is licensed and certified by DEQ to abate asbestos; is the HAZWOPER still required?
YES 11‐Mar‐21
7 X Referencing Section 107.08:
IS HAZWOPER required for other portions of the project too? Or just the concrete rubble removal
The HAZWOPER requirement information is provided in section 107.08, Bid accordingly
11‐Mar‐21
Check General or Technical
8 X
1. Testing – What kind of testing is Fed Hwy looking for and in what areas? Are you looking for maximum theoretical density of the embanked material or are you looking for moisture testing? Some insight to the testing would be really helpful.
See FP‐14 section 204 Excavation and Embankment, Sub‐section 204.11 Compaction. AND Special Contract Requirements (SCR’s) Sub‐Section 204.10A(b)(1), (2) and (3). Bid accordingly
15‐Mar‐21
9 X
Aquatic Life Savage and Rescue – There is noting on the Bid Schedule that calls out for hours for Aquatic Life Savage. Is this something that ODFW will be taking care of or is this on the Contractor?
Contractors Responsibility. Bid Accordingly 15‐Mar‐21
10a X
18.8 Acres of Turf Establishment and Bare Areas –
a. With the lake dropping 2‐4’ during the summer is there a reason we are seeding water areas and the swells? Also the spec calls for not leaving any bare areas.
Please see Special Contract Requirements (SCR’s) Sub‐Section 625.03.
NPDES permit requires covering bare areas. Government provided seed is a native mix suited for wetlands. Bid Accordingly.
15‐Mar‐21
10b X
18.8 Acres of Turf Establishment and Bare Areas –
Continued:
b. Wouldn’t it be realistic to seed the whole project at the end of the project as the summer months would require a temporary sprinkler system and the temperatures would not allow the seed to germinate?
Please see Special Contract Requirements (SCR’s) Sub‐Section 625.03. Bid Accordingly
15‐Mar‐21