QA_11_March_21.pdf
PDF 102 KB Posted
- Attached to
- OR DOT 140(3), Mitigation Site for OR 140 Federal contract opportunity
- Solicitation number
- 69056721B000002
About this file
This document contains technical questions and answers related to solicitation number 69056721B000002 from the Department of Transportation Federal Highway Administration for the OR DOT 140(3) Mitigation Site for OR 140 project. The questions and answers provide clarification on project details such as the project manager, whether there will be a pre-bid conference or prequalification requirement, specifications regarding an Erosion Control Supervisor and partnering, and confirmation that hazardous waste operations and emergency response certification is required for asbestos abatement and other portions of the concrete rubble removal work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary_OR DOT 140(3).pdf | ||
| QA_16_march_21.pdf | ||
| QA_15_march_21.pdf | ||
| QA_8_March_21.pdf | ||
| QA_4_March_21.pdf | ||
| GR10-17 OR-140 Prelim Geotech Charact Report.pdf | ||
| or-14003 DITCH D HA-VA.pdf | ||
| or-14003 DITCH E HA-VA.pdf | ||
| GR27-18 Final Geotech Report OR DOT 140(1) Klamath County Boat Marina to Lakeshore Dr.pdf | ||
| GM44-19 OR-140 MItigation Site Geotech Memo.pdf | ||
| or-14003 DITCH B HA-VA.pdf | ||
| or-14003 BERM HA-VA.pdf | ||
| or-14003 DITCH C HA-VA.pdf | ||
| or-14003_Control-Sheet.xlsx | XLSX spreadsheet | |
| Finalized or-14003_plans.pdf | ||
| Compiled OR 140 Mitigation digiESCPFinal.pdf | ||
| or-14003 DITCH A HA-VA.pdf | ||
| IFB_OR DOT 140(3).pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. OR DOT 140(3) Project: Mitigation Site for OR 140
# General Technical Question Answer Date
1 X Who is the project manager for this project? Helen Oppenheimer. See Bottom left hand side of sheet A.1 of the plan set.
4‐Mar‐21
2 X Is there going to be a pre‐bid conference? No. See The notice to Bidders
4‐Mar‐21
3 X
Is there a prequalification to bid this project? This Project is a Total Small Business Set‐Aside. See Classification for this project on the Beta.Sam solicitation information.
4‐Mar‐21
4 X Is the Erosion Control Supervisor (ECS) required to be on th
No, the ECS is required to be present on the project to perform the required duties as stipulated in Section 157 of the FP‐14 and the SCR’s
8‐Mar‐21
5 X specification 103.05 Partnering. I have read through the spec but do not feel confident that I understand it completely. Can you explain the Formal Partnering or do I need to talk to Helen Oppenheimer
FORMAL PARTNERING as used in section 103.05 the Government has agreed to pay for a portion of the direct costs (UP TO $5,000.00) that may be associated with the Partnering process. Which may include the partnering facilities, professional facilitation, copying fees, and other miscellaneous costs directly related to partnering meetings.
Please do not contact Helen Oppenheimer regarding question concerning this project. Instead contact wfl.plans‐spec: mailto:wfl.plans‐ spec@dot.gov
8‐Mar‐21
6 X Referencing Section 107.08:
If a contractor is licensed and certified by DEQ to abate asbestos; is the HAZWOPER still required?
YES 11‐Mar‐21
7 X Referencing Section 107.08:
IS HAZWOPER required for other portions of the project too? Or just the concrete rubble removal
The HAZWOPER requirement information is provided in section 107.08, Bid accordingly
11‐Mar‐21