Amendment A002.pdf
PDF 2 MB Posted
- Attached to
- MT 14203(1), Maiden Road Federal contract opportunity
- Solicitation number
- 69056720B000025
About this file
This document is an amendment to a solicitation for a federal highway construction project. The amendment revises plans and special contract requirements for Project MT 14203(1), Maiden Road located in Fergus County, Montana. The work consists of asphalt paving, aggregate stabilization, full depth reclamation, grading, drainage, pavement marking, and signing along 9.458 miles of roadway. The estimated price range for the project is $5 million to $7 million. The tentative fixed completion date is Fall 2021. The amendment provides revisions to specification sections including work schedule requirements, wage determination applicability, utility agreement timing, culvert installation restrictions, sign material and fabrication specifications, and plan sheet revisions. The Department of Transportation Federal Highway Administration is the contracting agency.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 02/25/2021 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056720B000025
9B. DATED (SEE ITEM 11)
01/28/2021
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
MT 14203(1), Maiden Road
See Page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 02-25-2021 MT 14203(1) Solicitation No. 69056720B000025 Maiden Road
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Page E-16, Subsection 108.01, Commencement, Prosecution, and Completion of Work.
Revises Subsection (c).
Page E-26, Subsection 152.04, General. Revises Subsection (a).
Page E-45, Subsection 157.10, Diversions. Revises Subsection (e).
Page F-40, Subsection 633.04, Sign Posts. Revises Subsection.
PLANS
Plan Sheet A.2 Revises Sheet Numbers for Plan Section I.
Plan Sheet I.4 Deletes Sheet.
Plan Sheets I.4a through I.4d Adds Sheets.
ENCLOSURES
Pages:
E-16 / E-26 / E-45 F-40
Plan Sheets:
A.2 I.4 / I.4a through I.4d
E-16 DIVISION 100
Special Contract Requirements Project: MT DOT 14203(1), Maiden Road
Section 108. — PROSECUTION AND PROGRESS
04/03/20– FP-14
108.01 Commencement, Prosecution, and Completion of Work. Add the following:
Furnish at least a 48-hour advanced notice before changing the current work schedule. Work schedule changes that include additional shifts require a 14-day advanced notice.
Perform work under this contract according to the following.
(a) Limit work as provided for in Sections 104, 105, 107, 156, and 157.
(b) Do not perform work within the following durations.
(1) Between 6:00 p.m. Friday and 6:00 a.m. the following Tuesday of the Memorial Day and Labor Day weekends.
(2) Between 6:00 p.m. July 2, and 6:00 a.m. July 6.
(3) On any holiday, or between 6:00 p.m. Friday and 6:00 a.m. the following Monday, unless approved by the CO.
(c) Work at box culvert 293+61 cannot be performed until an executed utility agreement from the Century Link (Lumen) is received (see Subsection 107.02), which is anticipated to occur before the Notice to Proceed date. Do not perform work associated with the box culvert at 293+61 until receiving written approval from the CO. Do not perform work associated with the box culvert at 374+92 until receiving written approval from the CO. Associated work includes ordering any materials associated with the work. Notice to Proceed for the Project does not constitute approval for work on the culvert culverts at 293+61. and 374+92.
108.01A Labor. (Added Subsection).
Follow the requirements of FAR Clause 52.222-6 Construction Wage Rate Requirements.
Adjacent or virtually adjacent work sites, as used in FAR Clause 52.222-6, are defined to be work sites within ½ mile of the project. Application of Construction Wage Rate Requirements (Davis- Bacon Act) for work sites beyond ½ mile of the project will be determined by the CO.
Pay rates and zone pay used in the General Wage Decision are based on the “Center of the job.”
The “Center of the job” is:
(a) The geographic center of the project when construction sites are contiguous; or,
(b) The geographic center of the project when construction sites are noncontiguous and separated by no more than 1-mile from edge to edge.
Construction sites that are noncontiguous and separated by greater than 1-mile will each have a separate “Center of the job” for the purposes of determining pay rates and zone pay.
Revised by Amendment A002
E-26 DIVISION 150
Project: MT DOT 14203(1), Maiden Road
At the preconstruction conference, submit a cost breakdown of the work included in the lump sum item for the purpose of making progress payments.
(a) Government set reference lines and points. The Government has set horizontal and vertical control points for the project. The location and identity of each control point are shown on the plans.
The CO will also identify the beginning of the project.
Before beginning construction, notify the CO of any missing control points or stakes. The Government will reestablish control points and stakes missing before the beginning of construction.
(b) Government furnished information. The Government will furnish the design data described below for 293+20 to 294+30, 374+00 to 375+50, 901+55 to 902+93, and 801+05 to 802+77:
(1) Proposed horizontal alignment(s) and profile grade(s) in Portable Document Format (.pdf) and LandXML (.xml) formats;
(2) Cross Sections in Portable Document Format (.pdf);
(3) Earthwork end area volume report in Portable Document Format (.pdf);
(4) Superelevation report in Portable Document Format (.pdf);
(5) Construction staking notes containing points at centerline, shoulders, and theoretical slope stake catch in Portable Document Format (.pdf);
(6) X, Y, Z coordinates of subgrade and base layer(s) points at centerline and shoulders, in Portable Document Format (.pdf);
(7) Proposed finished surface in LandXML (.xml) format; and,
(8) Proposed 3D breaklines in Drawing Exchange Format (.dxf).
Perform additional conversions and calculations as necessary for convenient use of Government-furnished data. The Contractor is responsible for the accuracy of all information converted from the Government-furnished data. Provide immediate notification of apparent errors in the furnished data.
(c) Pre-survey meeting. Before surveying or staking, discuss and coordinate the following with the CO:
(1) Surveying and staking methods;
(2) Stake marking;
(3) Grade control for courses of material;
(4) Referencing;
E-45 DIVISION 150
Project: MT DOT 14203(1), Maiden Road
Multiple culverts may be used in place of one large culvert if they have the equivalent capacity of the larger one. For crossings utilizing multiple culverts, the minimum-size individual culvert that may be used is 60-inches diameter.
Install approved scour and erosion protection at culvert inlets and outlet.
Remove temporary culverts when they are no longer required.
(e) Diversion Installation. Divert stream flow as needed for completing existing culvert removal, riprap placement, and new culvert installation. Maintain structures and systems as needed for ensuring design efficiency.
Minimum design discharges and velocities for flow diversion and barrier systems is as follows:
Warm Spring Creek 293+61
Warm Spring Creek 374+92
Discharge 260 cfs 157 cfs Velocity 7.8 ft/sec 6.7 ft/sec
Flow diversion barriers must have a minimum elevation of 2 foot above what is needed for conveying the design discharge. Do not span the stream channel and floodplain completely.
Isolate one bank first for completing riprap installation at that bank. Finish riprap installation and final grading before removing flow diversion at that bank and starting second bank. Isolate second bank for completing riprap installation of that bank. Maintain at least half-width channel flow always. Minimize disturbance of channel bed as much as possible. Flow diversion barriers must be stable using the above listed velocities for parallel flow. Leakage through and under the barrier must be small enough to allow for proposed work.
Do not dewater downstream channels during dewatering. Maintain a downstream water flow rate of at least 90 percent of the upstream water flow rate.
Use non-erosive materials for diversions and barriers. Diversion sandbags can be filled with material mined from the floodplain as long as such material is replaced at end of project. Small amounts of in-stream material can be moved to help seal and secure diversion structures.
(f) Dewatering. Dewater according to Subsection 208.07.
(g) Operation. Operate temporary water management as follows:
(1) Maintain and control water flow downstream of the isolated work area for the duration of the diversion to prevent downstream de-watering.
(2) Regularly inspect and clean coffer dams, culverts, or water-proof lined diversion ditches of excess debris or sediment accumulation.
(h) Re-watering and removal. Pre-wash reconstructed channel segments into a channel reach equipped with sediment capture devices prior to reintroducing stream to channel.
F-40 DIVISION 600
Project: MT DOT 14203(1), Maiden Road
Section 633. — PERMANENT TRAFFIC CONTROL
08/01/14–FP14
Construction Requirements
633.04 Sign Posts. Add the following:
Fabricate sign posts from aluminum, galvanized steel, or corrosion resistant steel or combination thereof.
633.05(a)(1) Panels. Amend as follows
Delete the sixth paragraph and substitute the following:
Use retroreflective sheeting as specified and according to ASTM D4956. For roadside signs, use Type III, IV, VIII, IX, or XI prismatic retroreflective sheeting. Use fluorescent yellow-green sheeting for school crossing signs.
Add the following:
Fabricate sign panels from aluminum.
Revised by Amendment A0022
I.1-3
I.4a-6
SHEET I.4 REMOVED FROM PLANS
MT DOT 14203(1) I.4a
MT I.4bDOT 14203(1)2
2 MT DOT 14203(1) I.4c
2 MT DOT 14203(1) I.4d