660-20-102 ELEC DIST P1 SPECS.pdf
PDF 4 MB Posted
- Attached to
- Z2DA--T2_Electrical Distribution Phase 1 (660-20-102)_(VA-22-00047012) Federal contract opportunity
- Solicitation number
- 36C25922R0084
About this file
This solicitation is for an electrical distribution phase 1 project at the George E. Wahlen VA Medical Center in Salt Lake City, Utah. The solicitation seeks bids for general construction and electrical work. The general construction work includes temporary generators and chillers, while the electrical work encompasses all labor, materials, and equipment to perform the required electrical construction indicated in the drawings, specifications, and contract. Bids are due by January 20, 2023, with an estimated period of performance from February 2023 to February 2024. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Meeting Doc.docx | DOCX document | |
| Site Visit Attendance.pdf | ||
| 36C25922R0084 0001.docx | DOCX document | |
| 660-20-102 ELEC DIST P1 DRAWINGS.pdf | ||
| 36C25922R0084_1.docx | DOCX document | |
| Wage Determination UT20220085.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
750 West Hampden Avenue
Suite 300
Englewood, CO 80110
Ph: (720) 550-6307
Department of Veterans Affairs George E. Wahlen VA Medical Center
Salt Lake City, UT
Project Number 660-20-102
(VEG 21.06)
Electrical Distribution Phase 1
100% Documents
Technical Specifications
9/1/2021
750 West Hampden Avenue
Suite 300
Englewood, CO 80110
Ph: (720) 550-6307
01-01-21
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 01-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 07-20
01 35 26 A 660-20-102 Electrical Distribution Phase 1 CSRA
01 35 26 B 660-20-102 Electrical Distribution Phase 1 ILSM
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 74 19 Construction Waste Management 01-21
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping
07 92 00 Joint Sealants 10-17
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-20
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 21 13 Hydronic Piping 02-20
23 64 00 Packaged Water Chillers 03-20
DIVISION 25 – INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-10
01-01-21
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 13 Medium-Voltage Cables 01-17
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 41 Underground Electrical Construction 01-17
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 11 16 Secondary Unit Substations 01-18
26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 01-18
26 24 13 Distribution Switchboards 01-18
26 24 16 Panelboards 01-18
26 24 19 Motor Control Centers 01-18
26 25 11 Busways 01-17
26 43 13 Surge Protective Devices 01-17
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
DIVISION 34 – TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
SHEET NO. SHEET NAME
GENERAL
GI001 COVER SHEET
GI002 APPLICABLE CODES CHECKLISTS
GI003 APPLICABLE CODES CHECKLISTS CONTINUED
ELECTRICAL
E-001 ELECTRICAL SYMBOLS & ABBREVIATIONS
ES101 ELECTRICAL SITE PLAN - BUILDINGS 14 & 42
ES102 ELECTRICAL SITE PLAN - BUILDINGS 27 & 40
E-601 ONE-LINE DIAGRAMS - BUILDINGS 14
E-602 ONE-LINE DIAGRAMS - BUILDINGS 27 & 40
E-603 ONE-LINE DIAGRAMS - BUILDING 27 EMERGENCY
E-604 BUILDING 14 - SWITCHBOARD ELEVATIONS
E-605 BUILDING 27 - MCC ELEVATIONS
ED101 BUILDING 14 DEMOLITION PLAN
ED102 BUILDING 42 DEMOLITION PLAN
ED103 BUILDING 27 DEMOLITION PLAN
ED104 BUILDING 40 DEMOLITION PLAN
EP101 BUILDING 14 POWER PLANS
EP102 BUILDING 42 POWER PLAN
EP103 BUILDING 27 POWER PLAN
EP104 BUILDING 40 POWER PLAN
EP105 TEMPORARY CHILLER POWER PLAN
E-501 ELECTRICAL DETAILS
E-502 ELECTRICAL DETAILS
E-503 ELECTRICAL SEISMIC DETAILS
MECHANICAL
M-001 MECHANICAL ABBREVIATIONS & GENERAL NOTES
M-002 MECHANICAL SYMBOLS
M-501 MECHANICAL SCHEDULE AND DETAILS
MP105 MECHANICAL PIPING TEMPORARY CHILLER PLAN
- - - END - - -
05-01-20
00 01 15 - 2
THIS PAGE LEFT BLANK INTENTIONALLY
03-01-20
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Electrical Distribution Ph. 1
(Salt Lake City, UT)as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
COR.
C. Offices of Valhalla Engineering, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items. Work includes temporary generators and chillers for chiller plant work along with temporary connections.
ITEM II, Electrical Work: Work includes all labor, material, equipment, and supervision to perform the required electrical construction work on this project required by the drawings, specifications, and contract.
01 00 00 -2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Guards: NA
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
01 00 00 -3
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
01 00 00 -4
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as directed by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR.
01 00 00 -5
G. Phasing:
Specific phasing as follows:
Bldg. 14 – all materials and equipment will be delivered to site prior to any work. New 1000 KVA transformers and associated work including new medium voltage feeds, bus duct to location of existing transformers
(secondary feeds) and all associated work with new transformers shall be completed first. Testing of transformers and primary wiring shall be completed. An outage to connect to C and D medium voltage loops will require off hour coordination with COR and schedules at least two weeks in advance. On one weekend the Medical Center will go to generator power. Remove one old transformer and associate wire, etc.
Install new secondary wire connected to bus duct. Replace service disconnect and switchboards and tie break. Test and provide new system prior to start of business on Monday morning. Multiple crews and off hour work will be required.
On another weekend the Medical Center will go to generator power. Remove the other old transformer and associate wire, etc. Install new secondary wire connected to bus duct. Replace service disconnect and switchboards and tie break. Test and provide new system prior to start of business on Monday morning. Multiple crews and off hour work will be required.
Bldg. 27 – provide a temporary emergency generator and chiller to provide chilled water while all work in building 27 is completed. This will take place during winter months when chiller load is minimal. An outage to connect to C and D medium voltage loops will require off hour coordination with COR and schedules at least two weeks in advance.
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
01 00 00 -6
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.
H. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge.
Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 14 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center . Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 14 calendar days prior to the desired time and shall be performed as directed by the COR.
01 00 00 -7
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
I. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped, or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
J. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
K. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
L. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m
(seven feet) minimum height, around the construction area.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
01 00 00 -8
1.7 ALTERATIONS – N/A
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by COR as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261........Identification and Listing of Hazardous Waste
40 CFR 262........Standards Applicable to Generators of Hazardous
Waste
40 CFR 263........Standards Applicable to Transporters of
Hazardous Waste
40 CFR 761........PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
49 CFR 172........Hazardous Material tables and Hazardous
Material Communications Regulations
49 CFR 173........Shippers - General Requirements for Shipments and Packaging
01 00 00 -9
49 CRR 173........Subpart A General
49 CFR 173........Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173........Subpart J Other Regulated Material; Definitions and Preparation
TSCA..............Compliance Program Policy Nos. 6-PCB-6 and 6-
PCB-7
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter, or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to
01 00 00 -10 be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA – N/A
1.12 PROFESSIONAL SURVEYING SERVICES – N/A
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer
01 00 00 -11 may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications, and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
01 00 00 -12
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed, and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.17 RESIDENT ENGINEER'S FIELD OFFICE – N/A
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light, and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e., transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
01 00 00 -13
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained, and inspected prior to acceptance by the Government. //
Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS – N/A
1.20 TEMPORARY USE OF NEW ELEVATORS – N/A
1.21 TEMPORARY TOILETS
A. Contractor may have for use of Contractor's workers; such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall provide and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final
01 00 00 -14 acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
1.23 NEW TELEPHONE EQUIPMENT – N/A
1.24 TESTS – REFER TO DIVISION 26 SPECIFICATIONS
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
1.26 GOVERNMENT-FURNISHED PROPERTY – N/A
1.27 RELOCATED EQUIPMENT - N/A
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
A. Contractor shall provide for all storage as needed for project and in compliance with VA direction and instructions.
1.29 CONSTRUCTION SIGN – N/A
1.30 SAFETY SIGN NA
1.31 PHOTOGRAPHIC DOCUMENTATION – N/A
1.32 FINAL ELEVATION DIGITAL IMAGES – N/A
1.33 HISTORIC PRESERVATION
Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
- - - E N D - - -
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
PART 1- GENERAL1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications. A detailed plan is needed with sufficient number of crews to meet short turnaround times to keep building 14 fully operational meeting time requirements.
All materials will be available prior to any scheduled shutdowns. See phasing plan in the General Requirements.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review, and progress reporting with and to the Contracting Officer's Representative (COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 CONTRACTOR'S CONSULTANT:
A. The Contractor shall submit a qualification proposal to the COR, within
10 days of bid acceptance. The qualification proposal shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.
01 32 16.15 - 2
3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The Contracting Officer has the right to approve or disapprove the proposed consultant and will notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal.
In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The
Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans
Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced reports to the
Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Contracting Officer’s representative, to correct errors which affect the payment and schedule for the project.
01 32 16.15 - 3
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the
Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved
CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost.
Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate written detailed request to the Contracting
Officer identifying these date constraints and secure the Contracting
Officer’s written approval before incorporating them into the network diagram. The Contracting Officer’s separate approval of the Project
Schedule shall not excuse the contractor of this requirement. Logic events (non-work) will be permitted where necessary to reflect proper logic among work events but must have zero duration. The complete working schedule shall reflect the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract changes or delays which may have been incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents.
These changes/delays shall be entered at the first update after the final Project Schedule has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT
COMPLETION.
01 32 16.15 - 4
B. Within 30 calendar days after receipt of the complete project interim
Project Schedule and the complete final Project Schedule, the
Contracting Officer, or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit three blue line copies of the revised Project Schedule, three copies of the revised computer-produced activity/event ID schedule and a revised electronic file as specified by the Contracting Officer. The revised submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved.
C. The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
1.6 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance
01 32 16.15 - 5 with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER
FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.232
C. In accordance with FAR 52.236 – 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR) and VAAR 852.236 – 72 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
1.7 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor
Shall:
1. Show activities/events as:
a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.
b. Contracting Officer's and Architect-Engineer's review and approval of shop drawings, equipment schedules, samples, template, or similar items.
c. Interruption of VA Facilities utilities, delivery of Government furnished equipment, and rough-in drawings, project phasing and any other specification requirements.
d. Test, balance and adjust various systems and pieces of equipment, maintenance and operation manuals, instructions and preventive maintenance tasks.
e. VA inspection and acceptance activity/event with a minimum duration of five workdays at the end of each phase and immediately preceding any VA move activity/event required by the contract phasing for that phase.
2. Show not only the activities/events for actual construction work for each trade category of the project, but also trade relationships to indicate the movement of trades from one area, floor, or building, to another area, floor, or building, for at least five trades who are performing major work under this contract.
01 32 16.15 - 6
3. Break up the work into activities/events of a duration no longer than 20 work days each or one reporting period, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the COR may approve the showing of a longer duration. The duration for VA approval of any required submittal, shop drawing, or other submittals will not be less than
20 workdays.
4. Describe work activities/events clearly, so the work is readily identifiable for assessment of completion. Activities/events labeled
"start," "continue," or "completion," are not specific and will not be allowed. Lead and lag time activities will not be acceptable.
5. The schedule shall be generally numbered in such a way to reflect either discipline, phase, or location of the work.
B. The Contractor shall submit the following supporting data in addition to the project schedule:
1. The appropriate project calendar including working days and holidays.
2. The planned number of shifts per day.
3. The number of hours per shift.
Failure of the Contractor to include this data shall delay the review of the submittal until the Contracting Officer is in receipt of the missing data.
C. To the extent that the Project Schedule or any revised Project Schedule shows anything not jointly agreed upon, it shall not be deemed to have been approved by the COR. Failure to include any element of work required for the performance of this contract shall not excuse the
Contractor from completing all work required within any applicable completion date of each phase regardless of the COR’s approval of the
Project Schedule.
D. Compact Disk Requirements and CPM Activity/Event Record Specifications:
Submit to the VA an electronic file(s) containing one file of the data required to produce a schedule, reflecting all the activities/events of the complete project schedule being submitted.
01 32 16.15 - 7
1.8 PAYMENT TO THE CONTRACTOR:
A. Monthly, the contractor shall submit an application and certificate for payment reflecting updated schedule activities and cost data in accordance with the provisions of the following Article, PAYMENT AND
PROGRESS REPORTING, as the basis upon which progress payments will be made pursuant to Article, FAR 52.232 – 5 PAYMENT UNDER FIXED-PRICE
CONSTRUCTION CONTRACTS and VAAR 852.232 The Contractor shall be entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated project schedule.
Monthly payment requests shall include: a listing of all agreed upon project schedule changes and associated data; and an electronic file
(s) of the resulting monthly updated schedule.
B. Approval of the Contractor’s monthly Application for Payment shall be contingent, among other factors, on the submittal of a satisfactory monthly update of the project schedule.
1.9 PAYMENT AND PROGRESS REPORTING
A. Monthly schedule update meetings will be held on dates mutually agreed to by the COR and the Contractor. Contractor and their CPM consultant
(if applicable) shall attend all monthly schedule update meetings. The
Contractor shall accurately update the Project Schedule and all other data required and provide this information to the COR three workdays in advance of the schedule update meeting. Job progress will be reviewed to verify:
1. Actual start and/or finish dates for updated/completed activities/events.
2. Remaining duration for each activity/event started, or scheduled to start, but not completed.
3. Logic, time and cost data for change orders, and supplemental agreements that are to be incorporated into the Project Schedule.
4. Changes in activity/event sequence and/or duration which have been made, pursuant to the provisions of following Article, ADJUSTMENT OF
CONTRACT COMPLETION.
5. Completion percentage for all completed and partially completed activities/events.
01 32 16.15 - 8
6. Logic and duration revisions required by this section of the specifications.
7. Activity/event duration and percent complete shall be updated independently.
B. After completion of the joint review, the contractor shall generate an updated computer-produced calendar-dated schedule and supply the
Contracting Officer’s representative with reports in accordance with the Article, COMPUTER PRODUCED SCHEDULES, specified.
C. After completing the monthly schedule update, the contractor’s representative or scheduling consultant shall rerun all current period contract change(s) against the prior approved monthly project schedule.
The analysis shall only include original workday durations and schedule logic agreed upon by the contractor and COR for the contract change(s).
When there is a disagreement on logic and/or durations, the Contractor shall use the schedule logic and/or durations provided and approved by the COR. After each rerun update, the resulting electronic project schedule data file shall be appropriately identified and submitted to the VA in accordance to the requirements listed in articles 1.4 and
1.7. This electronic submission is separate from the regular monthly project schedule update requirements and shall be submitted to the COR within fourteen (14) calendar days of completing the regular schedule update. Before inserting the contract changes durations, care must be taken to ensure that only the original durations will be used for the analysis, not the reported durations after progress. In addition, once the final network diagram is approved, the contractor must recreate all manual progress payment updates on this approved network diagram and associated reruns for contract changes in each of these update periods as outlined above for regular update periods. This will require detailed record keeping for each of the manual progress payment updates.
D. Following approval of the CPM schedule, the VA, the General Contractor, its approved CPM Consultant, COR, and all subcontractors needed, as determined by the SRE, shall meet to discuss the monthly updated schedule. The main emphasis shall be to address work activities to avoid slippage of project schedule and to identify any necessary
01 32 16.15 - 9 actions required to maintain project schedule during the reporting period. The Government representatives and the Contractor should conclude the meeting with a clear understanding of those work and administrative actions necessary to maintain project schedule status during the reporting period. This schedule coordination meeting will occur after each monthly project schedule update meeting utilizing the resulting schedule reports from that schedule update. If the project is behind schedule, discussions should include ways to prevent further slippage as well as ways to improve the project schedule status, when appropriate.
1.10 RESPONSIBILITY FOR COMPLETION
A. If it becomes apparent from the current revised monthly progress schedule that phasing or contract completion dates will not be met, the
Contractor shall execute some or all the following remedial actions:
1. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of work.
2. Increase the number of working hours per shift, shifts per working day, working days per week, the amount of construction equipment, or any combination of the foregoing to eliminate the backlog of work.
3. Reschedule the work in conformance with the specification requirements.
B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the COR for the proposed schedule changes. If such actions are approved, the representative schedule revisions shall be incorporated by the Contractor into the Project
Schedule before the next update, at no additional cost to the
Government.
1.11 CHANGES TO THE SCHEDULE
A. Within 30 calendar days after VA acceptance and approval of any updated project schedule, the Contractor shall submit a revised electronic file
(s) and a list of any activity/event changes including predecessors and successors for any of the following reasons:
1. Delay in completion of any activity/event or group of activities/events, which may be involved with contract changes, strikes, unusual weather, and other delays will not relieve the
01 32 16.15 - 10
Contractor from the requirements specified unless the conditions are shown on the CPM as the direct cause for delaying the project beyond the acceptable limits.
2. Delays in submittals, or deliveries, or work stoppage are encountered which make rescheduling of the work necessary.
3. The schedule does not represent the actual prosecution and progress of the project.
4. When there is, or has been, a substantial revision to the activity/event costs regardless of the cause for these revisions.
B. CPM revisions made under this paragraph which affect the previously approved computer-produced schedules for Government furnished equipment, vacating of areas by the VA Facility, contract phase(s) and sub phase(s), utilities furnished by the Government to the Contractor, or any other previously contracted item, shall be furnished in writing to the Contracting Officer for approval.
C. Contracting Officer's approval for the revised project schedule and all relevant data is contingent upon compliance with all other paragraphs of this section and any other previous agreements by the Contracting
Officer or the VA representative.
D. The cost of revisions to the project schedule resulting from contract changes will be included in the proposal for changes in work as specified in FAR 52.243 – 4 (Changes, and will be based on the complexity of the revision or contract change, man hours expended in analyzing the change, and the total cost of the change.
E. The cost of revisions to the Project Schedule not resulting from contract changes is the responsibility of the Contractor.
1.12 ADJUSTMENT OF CONTRACT COMPLETION
A. The contract completion time will be adjusted only for causes specified in this contract.
This is the start of the file's text. The full file is on GovTribe.