653-23-104 SOW Final.pdf

PDF 289 KB Posted

Attached to
H261--653-23-104 Electrical Study & Testing and Maintenance of Breakers and Panels
Solicitation number
36C26023R0019
Issued by

About this file

This statement of work outlines requirements for an electrical study and testing and maintenance of circuit breakers and panels at the Roseburg VA Medical Center in Oregon. The contractor will conduct an electrical survey, field inspection, short circuit and protective device coordination studies, arc flash analysis, and maintenance including replacement of faulty circuit breakers and panels. Key deliverables include submittals at 60%, 90%, 100% completion with coordination study curves, arc flash labels, cost estimates, and as-built drawings. The maintenance work will be performed following survey completion under planned outages scheduled three weeks in advance. The performance period is estimated at 238 calendar days following a 14 day kickoff period.

View the file

Other files

File Type Posted
36C26023R0019 0001.docx DOCX document
36C26023R0019 LineItems.xlsx XLSX spreadsheet
36C26023R0019.docx DOCX document
Wage Determination 2015-5579 Rev. No. 19 Dated 12.27.pdf PDF
653-23-104 SOW APPENDIX 1- COMPONENTS LISTING.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

653-23-104 ELECTRICAL STUDY FY23

Roseburg VAMC

BACKGROUND:

The project is located at the Roseburg, Oregon VA Medical Center (VAMC). The Contractor shall conduct an electrical system, study, field inspection, testing and maintenance. The purpose of this survey and maintenance work is to ensure 100% compliance with VHA Directive 1028.

GENERAL REQUIREMENTS:

1. All work shall be accomplished in strict compliance with current editions of NFPA-70E, (Standard for Electrical Safety in the Workplace), NFPA-70B (Recommended Practice for

Electrical Equipment Maintenance), ANSI-MTS (American National Standards Institute –

Maintenance Testing Specifications – for electrical); and IEEE 242-2001, Recommended

Practice for Protection and Coordination of Industrial and Commercial Power Systems. All survey work will be accomplished on energized equipment unless an outage is required due to specific equipment safety conditions. All maintenance and repairs will require an equipment outage. All requests for outages must be submitted to and approved by the Contracting Officer’s

Representative (COR). Appropriate personal protective equipment (PPE) shall be used in all situations where it is necessary to remove covers/open equipment thereby exposing live buses or other energized components.

2. Due to necessary project phasing the contractor shall conduct an entrance briefing upon arrival at the VAMC. The Contractor shall use the entrance meeting to introduce staff and to discuss the procedures for obtaining the necessary drawings and field information. All information obtained during site visits, or any conditions discovered during subsequent calculations shall be kept in strict confidence.

3. The electrical study Team shall be in accordance with VA Directive 1028

4. The electrical system documentation shall be compatible with SKM Power Tools and AutoCAD software. A copy of the software model and data files used to develop the study shall be turned over to the VAMC for the facility’s use and modification for future facility work (e.g., creation of updated arc flash hazard warning labels).

5. Provide documents for VAMC Review at 60%, 90%, 100% and Final submissions. Submit the review comments to the COR before shipping the scheduled submission. Incorporate the COR comments and the responses to the reports.

6. Baseline Review (BR).

a. Approximately 15-30 days after submitting the 90% documents but before completing the

Final Submission documents, the Contractor shall coordinate and conduct a Baseline Review meeting with the COR and additional VAMC staff deemed necessary by the COR. This meeting may be held in person or virtually.

b. At this meeting, the Contractor shall provide the COR a prioritized overview of the deficiencies found and the potential consequences if such deficiencies are not corrected. In short, the Contractor shall review the findings of the study with the COR to explain inherent risks and respond to any questions regarding the study.

c. At conclusion of the BR, the Contractor shall document the meeting in minutes indicating the

VAMC has received the study and have been informed of any associated risks. Copies of these minutes shall be included in the Final Submission documents.

https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=&ved=2ahUKEwi0wvb5-4n_AhWPLUQIHTpxAhwQFnoECA4QAQ&url=https%3A%2F%2Fwww.va.gov%2Fvhapublications%2FViewPublication.asp%3Fpub_ID%3D8723&usg=AOvVaw1z-5wj9wuPCbtznDXJfKCf

Roseburg VAMC

7. Upon reaching 75% of the contracted value for each breaker and panel individually the

Contractor shall notify the COR and CO immediately if testing remains for that specific amperage rating. Testing will not continue if no more replacement parts are available until direction received from CO.

8. Contractor shall phase testing based on availability of parts.

9. Qualifications

a. The short-circuit, protective device coordination and arc flash hazard analysis studies shall be conducted under the supervision and approval of a Registered Professional Electrical

Engineer skilled in performing and interpreting the power system studies.

b. The Registered Professional Electrical Engineer shall have a minimum of five years of experience in performing power system studies or a proven equivalent level of proficiency.

c. The Contractor shall demonstrate experience with Arc Flash Hazard Analysis by submitting names of actual arc flash hazard analysis it has performed in the past.

d. The lead electrician must hold a level three or higher electrical testing certification with five years of experience performing low and medium voltage repairs and maintenance. The certification shall be in accordance with ANSI/NETA ETT, Standard for Certification of

Electrical Testing Technicians.

VAMC FURNISHED ITEMS DURING PERIOD OF PERFORMANCE:

1. As-built drawings, as available, to verify existing field conditions. The 2016 Wiley Wilson campus wide electrical survey to include arc flash and coordination study will be made available to the Contractor. Contractor shall inspect and confirm the accuracy of the provided as-built drawings on site.

2. COR shall accompany the Contractor’s team members during the site visit. The contractor shall coordinate and verify schedule and personnel, with the COR, in advance of site visit(s). The

COR shall ensure that any additional medical center personnel required are available to accompany the survey team. Contractor must have skilled staffing and equipment to perform tasks without VA assistance. VA electrician support will not be provided.

3. Any electrical maintenance and testing past reports performed at the VAMC as well as any work in progress information.

4. A small conference workroom, large format, and small format plotter/copiers.

DELIVERABLES:

1. Submittals:

a. Prepare and deliver submittals for 60%, 90% and 100% and Final for the Electrical Survey.

Copies of each submittal shall be provided to the COR.

b. For each submittal provide one printed copy and two electronic copies via compact disc (CD) of the electrical study, including all data files.

c. At 100% and Final submittals drawings shall be of Size Arch C.

d. Primary one-line drawings and secondary one-line drawings using the latest version of software compatible with SKM and AutoCAD; include the Viewer on each CD.

e. For the Final Study Submittal, the VAMC shall receive PDF and “live” CAD drawing files which can be manipulated and updated.

f. Submit a proposed schedule for completion of each of the studies; 60%, 90%, and 100%.

2. Content by Submittal phase:

Roseburg VAMC

a. 60% Submission shall include:

i. Letter from local electric utility provider (Pacific Power) indicating the available fault current at the point of service.

ii. Executive Summary.

iii. Minutes of the Entrance Briefing with COR to include VHA Directive 1028 and

Compliance Survey.

iv. Analysis and calculations for the Primary Distribution System and partial Secondary

Distribution System for each building including switchgear, switchboard, and distribution panel, etc. The analysis shall include Short Circuit Study and Protective Device

Coordination Curves.

v. The analysis shall be based on the actual device data.

b. 90% Submission shall include:

i. All Revised Content from 60% submittal (including updates below).

ii. Deficiencies report and cost estimates.

iii. All comments from 60% submission with annotations and responses.

iv. All items identified in Para. 5, Specific Scope, as a separate Tab or Section to include:

1. Full Campus SKM and Traditional One-Line Diagrams

2. Note equipment not in service

3. Grounding Analysis

4. Short Circuit Study

5. Hazard-Risk Table

6. Coordination Curves

7. Voltage Drop Calculations

8. Emergency Power Analysis

9. Recommendations

10. Protective Device Settings

11. Excel spread sheet for protective devices that require adjustments

12. Cost Estimates

13. Facility Condition Assessment (FCA) Excel spreadsheet

14. Deficiency Report

15. Cost Estimate Excel spread sheet

16. MS Project outage schedule for testing and maintenance

v. Completed analysis and calculations for the entire Primary and Secondary Distribution.

vi. Completed one-line diagrams. Each building on the Building List that is attached to the

Scope of Work shall be identified on the supplied drawings.

c. The Final Submission shall include:

i. A completed report, including all corrected data from the 60% and 90% submittals. The completed report shall include an Executive Summary that includes a prioritized overview of the deficiencies found and the potential consequences if such deficiencies are not corrected.

ii. Responses to the 60% and 90% submission comments from the VAMC Peer Review including annotations and response.

Roseburg VAMC

iii. Electronic copy of the entire report including all SKM data, AutoCAD, Word, Excel files and PDF.

iv. Paper copy of completed report.

v. Color photos that show devices listed on the deficiency report.

vi. Arc Flash Hazard Warning labels compliant with requirements of latest NFPA 70E edition. NOTE: Arc Flash Hazard Warning labels need only to be provided to the COR.

vii. Provide final report with stamp and signature by the Licensed Professional Electrical

Engineer that oversaw the project.

SPECIFIC SCOPE:

1. The Contractor shall prepare and complete Short Circuit and Coordination studies including voltage drop calculations on the entire electrical system/s. The study shall begin at the incoming utility electrical service (for the normal system) and at the emergency generators (for the emergency system) and continue through to each branch circuit panelboard, motor control center or motor control panel in each building. The study shall include a system one-line diagram; Short

Circuit and ground fault analysis, protective coordination plots, voltage drop calculations and the following for each building/site location:

a. One-Line Diagrams:

i. Include all electrical equipment and wiring protected by the over current devices.

ii. Schematic wiring of the electrical distribution system for each building Calculated

Short Circuit values at each bus.

iii. Breaker and fuse ratings.

iv. Transformer kVA, voltage ratings and wiring connections.

v. Voltage at each bus.

vi. Identification of each bus.

vii. Conduit material, feeder sizes and lengths.

viii. Generator kW and voltage ratings.

ix. Room Number for each electrical equipment such as the panelboard, disconnect, and transformer, etc.

b. Ground Resistance Analysis Testing:

i. A concise qualitative description (not to exceed one (1) page of narrative) describing the overall condition of the facility ground resistance shall be provided. Any violations of NEC or other abnormalities (high ground resistance, damaged conductors or electrodes, harmonics, etc.) warranting further detailed study shall be highlighted.

Analysis of the facility ground resistance shall be based upon ground resistance testing and visual inspection of visible ground system components (made during site investigation). Include photographs of deficiencies. Data on ground system will be made available by the VAMC and knowledgeable persons of the ground systems will be made available as needed for interview.

c. Short Circuit Study:

i. Perform a Short Circuit Study in accordance with ANSI/IEEE standard 399 and the step-by-step procedures outlined in IEEE standard 141 and ANSI/IEEE 242.

Systematically calculate the fault impedance to determine the available short circuit and ground fault currents at each bus. Incorporate the motor contribution in determining the

Roseburg VAMC momentary and interrupting ratings of the protective devices. Motors less than 25 HP may be grouped together.

ii. The study shall be calculated by using SKM software or compatible. Pertinent data and the rationale employed in developing the calculations shall be incorporated in the introductory remarks of the study.

1. Use actual conductor impedances if known. If unknown, use typical conductor impedances based on IEEE Standard 141-1993.

2. Transformer design impedances shall be used when test impedances are not available.

3. Provide the following:

a. Calculation methods and assumptions

b. Selected base per unit quantities

c. SKM or compatible and Traditional One-line diagram of the system being evaluated

d. Source impedance data, including electric utility system and motor fault contribution characteristics

e. Tabulations of short circuit calculated quantities

f. Results, conclusions, and recommendations

4. Calculate short-circuit momentary and interrupting duties for a three-phase bolted fault at each:

a. Electric utility’s supply termination point

b. Incoming switchgear

c. Unit substation primary and secondary terminals

d. Low voltage switchgear

e. Motor control centers

f. Standby generators and automatic transfer switches

g. Branch circuit panelboards

h. Machine control panels

i. Bus Ducts

j. Other significant locations throughout the system

5. For grounded systems, provide a bolted line-to-ground fault current study for areas as defined for the three-phase bolted fault short-circuit study.

6. Protective Device Evaluation:

a. Evaluate equipment and protective devices and compare to Short Circuit

Ratings.

b. Adequacy of switchgear, motor control centers, and panelboard bus bars to withstand short-circuit stresses.

c. Notify VA COR in writing, of existing, circuit protective devices improperly rated for the calculated available fault current.

d. Present the data determined by the Short Circuit study in a table format, include the following:

i. Transformer kVA and voltage ratings, percent impedance, X/R ratios and wiring connections

ii. Generator kW and voltage ratings

iii. Conduit material, feeder sizes, length and X/R ratios

Roseburg VAMC

iv. Device identification (Manufacturer, Catalog No. and Device Curve No.

and ID)

v. Operating voltage

vi. Protective device

vii. Device rating

viii. Calculated Short Circuit current

ix. Hazard-Risk category at each piece of equipment for the worst-case fault condition

d. Protective Device Coordination Study:

i. Determine the extent of overcurrent protective device coordination with the objective to maximize coordination of the overcurrent protective devices. Determine applied protective device characteristics, settings or sizes which will provide a balance between equipment protection and selective device operation that is optimum for the electrical system. Provide the analysis for the existing system and needed corrections that is optimum for the VAMC electrical system. The coordination study shall follow the procedures set forth in ANSI/IEEE standard 399 and ANSI standard 242. The selection and settings of new protection devices shall comply with the NEC.

ii. Prepare the coordination curves to determine the required settings of protective devices to assure selective coordination. Graphically illustrate (using log scale) that adequate time separation exists between series devices, including the utility company upstream device. Plot the specific Time Current Characteristics (TCC) of each device in the electrical system as follows:

1. Provide TCC curve down to the last branch-circuit panelboard (regardless the protective device is an adjustable or fixed device) in the three-branches of the

Essential Electrical System (EES).

2. Provide TCC curve down to the last adjustable device (stop after the first fixed device) in the Normal System but at the minimum two-level curves from each of the building Service Entrance switchgear/switchboard shall be provided.

iii. The following specific information shall also be shown on the coordination curves at each level of power distribution system:

1. Device identification (including Manufacturer, Catalog Number, and Device

Curve Number and ID)

2. Voltage and current ratio for curves

3. 3 phase and 1 phase ANSI damage points for each transformer

4. No damage, melting, and clearing curves for fuses

5. Cable damage curves

6. Transformer inrush points

7. Maximum Short Circuit cutoff point

8. Excerpts from one-line diagram reflecting the protective devices modeled on each curve. This excerpt may be inserted onto a corner (typically top right-hand) of the curve print out or may be on the preceding facing page for ease of reference

9. Provide explanation, analysis, and recommendation to achieve better coordination

Roseburg VAMC

10. The analysis for recommended curve of a particular device shall be put right after the existing curve in the report for comparison

iv. Develop a table to summarize the settings selected for the protective devices. Include all medium voltage devices in the table, as well as all low voltage devices which require modification, showing the following data:

1. Device identification

2. Relay CT ratios, tap, time dial, and instantaneous pickup

3. Circuit breaker sensor rating, long time, short time, and instantaneous settings, and time bands

4. Fuse rating and type

5. Ground fault pickup and time delay

v. Inspection Testing and Coordination of Circuit Breakers. This includes a visual inspection and electrical testing. Inspection and Testing procedures shall follow

ANSI/NETA-MTS Chapter 7.6 for all low and medium voltage circuit breakers.

1. Record device tested

2. Provide a checklist for inspection and testing

3. Perform inspections and testing

4. Note conditions of each tested device

5. Replace faulted circuit breakers

6. Update table of summarized settings

7. Update protective devices in as one lines as needed

e. Protective Device Settings:

i. For all adjustable and fixed protective devices, provide tables to show existing settings and new settings where changes are recommended for proper protection.

ii. If adjustments will not provide adequate protection, provide recommendations to update or replace the existing underrated equipment and include cost estimates to accomplish the necessary corrections.

f. Arc Flash Hazard Analysis:

i. The Arc Flash Hazard Analysis shall be performed according to the IEEE Std. 1584-

2002. These equations can also be found in NFPA 70E (2018), Annex D.

ii. The Arc-Flash Hazard Analysis shall include all significant locations in 240 volt and

208-volt systems fed from transformers equal to or greater than 125 kVA where work could be performed on energized parts.

iii. Safe working distances shall be based upon the calculated arc flash boundary considering Incident Energy of 1.2 cal/cm2.

iv. When appropriate, the Short Circuit calculations and the clearing times of the phase overcurrent devices will be retrieved from the Short-Circuit and Coordination Study model. Ground overcurrent relays should not be taken into consideration when determining the clearing time when performing Incident Energy calculations

v. The short-circuit calculations and the corresponding Incident Energy calculations for multiple system scenarios shall be compared and the greatest Incident Energy must be uniquely reported for each equipment location. Calculations must be performed to

Roseburg VAMC represent the maximum and minimum contributions of fault current magnitude for all normal and emergency operating conditions. The minimum calculation will assume that the utility contribution is at a minimum and will assume a minimum motor contribution

(all motors off). Conversely, the maximum calculation will assume a maximum contribution from the utility and will assume the maximum quantity of motors to be operating. Calculations shall take into consideration the parallel operation of synchronous generators with the electric utility, where applicable.

vi. The Incident Energy calculations must consider the accumulation of energy over time when performing arc flash calculations on buses with multiple sources. Iterative calculations must take into account the changing current contributions, as the sources are interrupted or decremented with time. Fault contribution from motors and generators should be decremented as follows:

1. Fault contribution from induction motors should not be considered beyond 3-5 cycles.

2. Fault contribution from synchronous motors and generators should be decayed to match the actual decrement of each as closely as possible (e.g., contributions from permanent magnet generators will typically decay from 10 per unit to 3 per unit after 10 cycles).

vii. Each equipment location with a separately enclosed main device (where there is adequate separation between the line side terminals of the main protective device and the work location), calculations for Incident Energy and flash protection boundary shall include both the line and load side of the main breaker.

viii. When performing Incident Energy calculations on the line side of a main breaker (as required per 6), the line side and load side contributions must be included in the fault calculation.

ix. Mis-coordination should be checked amongst all devices within the branch containing the immediate protective device upstream of the calculation location and the calculation should utilize the fastest device to compute the Incident Energy for the corresponding location.

x. Arc Flash calculations shall be based on actual overcurrent protective device clearing time. Maximum clearing time will be capped at 2 seconds based on IEEE Std. 1584-

2002 section B.1.2. Where it is not physically possible to move outside of the flash protection boundary in less than 2 seconds during an arc flash event, a maximum clearing time based on the specific location shall be utilized.

g. Arc Flash Labeling:

i. Contractor shall produce and deliver, the Arc Flash Labeling, to the COR according to the number of distribution devices that are shown on the one-line diagram in accordance with NFPA 70 (NEC) and NFPA 70E. Labels shall be 4” x 6” (nominal) printed on industrial quality, 12 mil (0.012 inches) thickness adhesive backed vinyl. “Danger” labels shall have pre-printed headers in red; "Danger" labels shall be provided for equipment/devices having incident energy greater than or equal to 40 cal/Cm2;

“Warning” labels shall have pre-printed

Roseburg VAMC headers in orange. "Warning" labels shall be provided for equipment/devices having incident energy less than 40 cal/cm2. Electrical equipment shall be labeled IAW NFPA

70, Articles 110.16 & 100.21(B) and NFPA70E, Article 130.5.

ii. The arc flash hazard analysis to determine the Arc Flash Protection Boundary for each label shall be calculated IAW NFPA 70E Paragraph 130.5 (B).

1. Nominal system voltage

2. Arc flash boundary

3. At least one of the following:

a. Available incident energy and the corresponding working distance, or the arc flash PPE category in Table 130.7(C)(15)(A)(b) or Table

130.7(C)(15)(B) for the equipment, but not both

b. Minimum arc rating of clothing

c. Specific level of PPE

iii. In addition to the requirements of NFPA 70 and 70E, each label shall identify the corresponding piece of electrical equipment, by panelboard or device identifier and

Building number.

iv. Arc flash labels shall be provided in the following manner and all labels shall be based on recommended overcurrent device settings.

1. For each 600, 480 and applicable 208-volt panelboard, one arc flash label shall be provided.

2. For each motor control center, one arc flash label shall be provided.

3. For each low voltage switchboard, one arc flash label shall be provided.

4. For each Switchgear, one flash label shall be provided.

5. For medium voltage switches one arc flash label shall be provided

6. For each machine control panel, one arc flash label shall be provided.

7. For each bus duct plug, one arc flash label shall be provided.

8. For each compartment of the transformer, one arc flash label shall be provided.

h. Load Flow and Voltage Drop Calculations and Study:

i. Determine active and reactive power, voltage, current and power factor throughout the electrical system. Provide an analysis of the current operating scenario and recommendations for improvement. The load flow study shall follow the recommended procedures of ANSI/IEEE standard 399.

ii. Provide voltage drop calculations for all three-phase branch and feeder circuits. Show calculated voltages at each bus and voltage drops on each feeder.

iii. Calculations shall be based on the maximum values of kVA, kW, kvar, power factor and amperes for each power circuit.

1. For branch circuit level, use 80% of nameplate rating.

2. For incoming service and distribution level, use 50% of the nameplate rating or actual maximum peak demand load collected in the field if it is available.

iv. Provide tabular information showing the sizes of all cables, transformers, and other circuit data.

Roseburg VAMC

v. Provide a system one-line diagram which clearly identifies individual equipment busses, bus numbers, cable and bus connections and other circuit information.

vi. Provide a separate section or tables which provide an evaluation of the calculated voltage drops with recommendations for improvements where voltage drops exceed the allowable NEC limits.

i. Emergency Power System Analysis:

i. Currently there is an active project correcting Electrical Deficiencies (EDII) which is also replacing the old generator system with an upgraded emergency power system that will serve the medical center more effectively. If this system is not fully installed information will be provided for what is going to be installed.

ii. To evaluate the emergency electrical system please provide an analysis of the generators recently or to be installed by EDII based on the following survey required information:

1. The contractor shall provide a narrative describing the existing emergency power system(s) at the medical center, to include a description of each emergency generator, physical location, size (kW and ampacity), voltage, configuration (phase, wire), circuit number, age, and overall condition. A summary of the average loading on each generator shall be provided and then compared to projected future loads (Contractor shall develop load projections from discussing forecast projects and growth with VAMC COR), Contractor shall provide a qualitative narrative on the suitability of the existing generators to meet projected future loads. If existing Emergency Power

System, including generators, is not adequate to meet either current or future demands, recommendations shall be provided in the study. Contractor shall summarize the findings in tabular form reflecting (as a minimum), the VAMC peak demand, average demand, transformer capacity and total generator capacity.

j. Stability Studies:

i. Determine the ability of the electrical system’s synchronous machines to remain in step with one another following a disturbance. Provide an analysis of the current VAMC operating conditions and recommendations for improvement. The stability study shall be performed in accordance with ANSI/IEEE standard 399.

1. Provide tabulations and equations used to record data and model the system components.

2. Provide a one-line diagram of the stability study

3. Provide assumptions, conclusions, and recommendations based on stability study.

k. Harmonic-Analysis Study:

i. Determine the impact of nonlinear loads and associated harmonic contributions on voltage and currents throughout the electrical system. Provide an analysis of current operating conditions and provide recommendations. The harmonic analysis study shall

Roseburg VAMC be in accordance with ANSI/IEEE standard 399 and IEEE standard 3002.8 and shall include:

1. Tabulations of the data used to model the system components and one line diagram.

2. Description of the operating scenario.

3. Tabulation of rms voltages, peak voltages, rms currents and total capacitor bank loading versus associated equipment rating.

4. Identify insufficient equipment ratings for the current operating condition and the recommended best operating condition.

5. Tabulations of calculated voltage distortion factors, current distortion factors and individual harmonics versus the limits specified in IEEE standard 519.

Note values exceeding the limits specified in the IEEE standard in a spreadsheet.

6. Plots of impedance versus frequency showing resonant frequencies to be avoided.

7. Provide assumptions, conclusions, and recommendations based on Harmonic-

Analysis Study.

l. Thermographic Survey:

i. Perform a thermographic survey of electrical equipment. Reference the ANSI/NETA-

MTA to perform the thermographic survey. The thermographic survey shall be performed in accordance with NFPA 70B. Note all spots in the electrical system outside of normal operating conditions. Record results by building in a spreadsheet.

Provide a summary of findings, no more than one page.

m. Electromagnetic Field Survey:

i. Perform an electromagnetic field survey. Identify any locations of high electromagnetic field (EMF) exposure. Assess exposures to time-varying EMFs static electric fields and static magnetic fields. Reference the ANSI/NETA-MTA to perform the electromagnetic field survey. The magnetic field survey shall be performed in accordance with IEEE 644. Note significant results that may potentially cause problems for electrical equipment used in the facility. Results shall be recorded in a spreadsheet by building. Provide a summary of findings, no more than one page.

ANALYSIS, RECOMMENDATIONS, MAINTENANCE AND CORRECTIONS:

1. Analysis and Recommendations:

a. For all electrical equipment, determine if adequate code clearances exist. Note cases by site, building and specific equipment that do not include adequate code clearances and provide a cost estimate to resolve the problems. Provide information in table format.

Roseburg VAMC

b. Determine if ground fault protection exists where required by NFPA 70 Articles 215 and 517. Note all cases where this condition exists and provide cost estimates to correct. Provide information in table format.

c. For all automatic transfer switches, determine if the correct 3-pole or 4-pole switches are used. Where ground fault protection is used on the normal feed to the switch, determine if the switch is correctly wired. Note all cases where this condition exists and provide cost estimates to correct. Provide information in table format.

d. Note any use of cable limiters and provide recommendations to avoid any single phasing conditions. Note all cases where this condition exists and provide cost estimates to correct. Provide information in table format.

e. On the medium voltage switchgear, where undervoltage relays (27) are used, determine whether all 3 phases are monitored or only 2 phases are monitored. For those locations where only 2 phases are monitored, provide a cost estimate for providing adequate protection for all 3 phases.

f. Analyze the Short Circuit calculations and highlight any equipment that is determined to be underrated. Provide recommendations to effectively protect the underrated equipment.

g. After developing the coordination curves, highlight areas lacking coordination. Present a technical evaluation with a discussion of the logical compromises for best coordination.

h. Assess the equipment condition using grading method in term of A, B, C, D and F.

• Grade A - Like New Condition. Majority of useful life span remains.

"Excellent"

• Grade B - Good Condition. Over half of useful life span remains. "Good"

• Grade C - Average Condition. Less than half of useful life span remains.

"Average" or "Fair"

• Grade D - Poor Condition. Past assigned useful life. Failure is not critical.

"Poor" or "Problematic". Plan replacement prior to becoming critical.

• Grade F - Critical Condition. Needs immediate attention. "Failing" or

"Critical". “Could result in severe injury or death.”

2. Visual, Mechanical and Electrical Inspection, Cleaning, Testing and Maintenance:

a. This section of the project requires the Contractor to verify the Survey findings.

b. The Contractor shall provide a planned outage schedule for the Survey identified deficiencies. For forecasted work, parts and equipment must be available on site prior to making repairs. All electrical components shall be visually inspected, cleaned and tested mechanically and electrically. All electrical components (circuit breakers and panels) on testing schedule must have replacements on hand or acceptable availability.

c. Acceptable availability is defined as having on hand or the ability to obtain and install prior to end of shutdown as originally scheduled.

d. Inspection and testing procedures shall follow ANSI/NETA-Maintenance and Testing

Specifications. Inspection and Testing procedures are found in ANSI/NETA-MTS

Chapter 7. Testing and maintenance shall be conducted following survey data

Roseburg VAMC collection, evaluation, calculation and as built diagrams completion. Faulty circuit breakers or panels shall be replaced to The COR shall be notified about additional required repairs found during the electrical inspection and testing performed by the electrical contractor.

e. For each building record equipment condition and data as found. Perform maintenance and record equipment condition post repair. Outages will be required for maintenance; schedule outages with the COR at least three (3) weeks prior to outage for coordination with all affected parties. Record all data in a spreadsheet. The visual, mechanical, and electrical inspection and testing maintenance operation includes following items:

i. Switchgear and Switchboard Assemblies

ii. Transformers Inspection and Testing

1. Dry Type, Air Cooled, Low Voltage, Small

2. Dry Type, Air Cooled, Low Voltage, Large

3. Liquid Filled

iii. Cables Low and Medium Voltage

4. Low Voltage up to 600 Volts

5. Medium Voltage

iv. Metal Enclosed Busways

v. Switches

vi. Circuit Switchers

vii. Network Protectors

viii. Protective Relays – utilize AE provided checklist. Replace defective circuit breakers.

ix. Instrument Transformers

x. Metering Devices

xi. Regulating Apparatus

xii. Grounding Systems

6. Low Voltage Ground Fault Protection Systems

7. Medium Voltage Ground Fault Protection Systems

xiii. Rotating Machinery

8. AC Induction Motors and Generators

9. Synchronous Motors and Generators

10. DC Motors and Generators

11. Motor Control

a. Motor Starters – Low and Medium voltage

b. Motor Control Centers – Low and Medium voltage

xiv. Adjustable Speed Drive Systems

xv. Direct Current Systems - Rectifiers

12. Batteries

13. Chargers

xvi. Surge Arresters – Low and Medium Voltage

Roseburg VAMC

xvii. Capacitors and Reactors

xviii. Outdoor Bus Structures

xix. Emergency System

14. Generator Diesel Engines

15. Uninterruptable Power System

16. Automatic Transfer Switches

xx. Communications

17. Automatic Circuit Reclosers and Line Sectionalizers – oil and vacuum

xxi. Fiber Optic Cables

xxii. System Function Tests

18. Perform system function tests to prove that corrective actions are operational and meet expectations and requirements. Record the tests performed and the results of the tests in a spreadsheet.

xxiii. The Contractor shall red-line the One-line drawings with any changes made to the system.

xxiv. Contractor shall update the One-line drawings.

xxv. Contractor to provide a final report of testing and maintenance conclusions.

3. Electrical Study/Deficiency Corrections:

a. Electrical deficiency corrections shall be conducted by a team of licensed electricians under the authority of the Contractor. The Contractor shall have replacement parts and equipment acceptably available at the time a component is tested should it need to be replaced. Replacement will consist predominantly of circuit breaker replacement and possible circuit breaker panel replacement as required. Upon running out of circuit breakers acceptably available for a specific amperage rating that requires further testing notify the COR and CO immediately prior to testing further on circuit breakers of that specific amperage.

b. If an electrical panel needs to be replaced a replacement must be acceptably available prior to removal of the faulty panel.

c. Maintenance and repairs shall be made by a qualified electrician in accordance with the ANSI/NETA-Maintenance and Testing Specifications.

d. Circuit breakers and panel types listing is attached as Appendix 1 to this Statement of

Work

e. The Contractor must supply equipment for all testing. General project housekeeping shall be neat and orderly to avoid creating safety hazards.

4. Cost Estimates: to address additional required repairs beyond scope:

a. For each building/site location included in the electrical study, where recommendations are to replace or update the existing electrical system to provide adequate protection, provide estimated construction costs for the necessary work that is outside the scope of contract. Necessary work is deficiencies that are found during the electrical survey and additional work found during the electrical inspection, maintenance, and testing.

Roseburg VAMC

b. Total costs for each building shall be included in addition to an itemized breakdown to identify major items requiring replacement or upgrading.

c. Cost estimates shall not include adjustments for anticipated phasing, shutdowns, or overtime work.

d. Urgent items that pose a threat to life and/or reliability of the Roseburg VAMC shall be immediately reported to the project COR.

SCHEDULE

1. Site survey work shall begin immediately after Kick-Off and the Notice to Proceed is issued.

Work shall be coordinated with COR after the award of contract. All final reports shall be completed and submitted in a timely manner.

2. The study will provide an independent and documented overview of the entire electrical infrastructure conditions in each building at the Medical Center. Contactor shall contact COR two weeks prior to on site work so that the COR may deliver necessary notification to the

VAMC.

3. Draft final reports shall be submitted 30 days before the submission of the complete final report.

The draft final report will be reviewed by the VA with comments, edits and corrections provided to the contractor within three weeks after receipt of the draft final report.

4. The contractor shall provide a schedule for the staggered start and staggered submission/completion (at least 15 days between submissions) .VA will approve schedule.

5. VA review will take 10 business days per submittal.

6. The Contractor shall submit a proposed schedule for Electrical Study Corrections. Include an outage schedule based on outages being performed outside of normal business hours (7am –

5pm) Monday – Friday excluding Federal holidays.

7. Contractor to provide weekly project report log.

8. Contractor shall set up a weekly project meeting with VA to include a three week look ahead. A checklist for all work shall be used and updated weekly and reviewed with the VA during project meetings. Meeting will be held through virtual means accessible to all parties – contractor, VA

Roseburg, and VA Network Contracting Office 20.

9. Contractor shall submit a tentative project milestone delivery schedule to the CO and COR for approval prior to any work.

10. The Contractor shall submit redlined drawings of equipment installed during Electrical Study

Corrections to the COR for review and updates to be made to the 100% as built drawings.

Updates shall be complete and submitted to the VA by the end of the 238 calendar days Period of

Performance.

Roseburg VAMC

REFERANCE MATERIAL

1. NFPA-70E, (Standard for Electrical Safety in the Workplace)

2. NFPA-70B (Recommended Practice for Electrical Equipment Maintenance)

3. ANSI/NETA-MTS (American National Standards Institute – Maintenance Testing Specifications

– for electrical)

4. IEEE 242-2001, Recommended Practice for Protection and Coordination of Industrial and

Commercial Power Systems

5. IEEE Std. 1584-2002

6. VA Directive 1028

1. Roseburg VAMC – Estimated PROJECT SCHEDULE

Kick Off

60% Submission

90% Submission

100% Submission

Testing and Maintenance

Duration in Calendar Days

14 80 65 23 Est. 56 238