Ash Street Widening/Resurfacing LAP/SCOP Project - RFP Summary

This is a Request for Proposals (RFP) issued by the Taylor County Board of County Commissioners in Perry, Florida for the construction of the Ash Street Widening/Resurfacing LAP/SCOP Project. The project involves widening an existing approximately 19-20 foot wide road to a 24 foot wide paved roadway along Ash Street in Taylor County. The scope of work includes installing limerock widening strips, reclaiming existing asphalt, resurfacing approximately 1.3 miles of roadway, reworking existing and constructing new concrete sidewalks, reshaping ditches, extending/removing/adding stormwater culverts, performance turf installation, signage, and pavement markings. Sealed proposals must be submitted to the Clerk of Court by 4:00 P.M. on August 14, 2026, with bids to be opened at 6:10 P.M. on August 18, 2026. The base bid timeline is 365 calendar days for substantial completion. Five copies of each proposal are required. No pre-bid conference will be held; however, bidders may submit written questions to the County Engineer at county.engineer@taylorcountygov.com by 5:00 P.M. on July 31, 2026, with responses provided by August 7, 2026. The contract will be awarded to the bidder deemed to offer the best overall service, not necessarily the lowest price.

Bid security of five percent of the maximum bid price is required in the form of a certified check, bank money order, or bid bond. All proposals must include documentation of current Florida Department of Transportation prequalification, valid business/contractor licensing, proof of E-Verify enrollment, certificates of liability and workers' compensation insurance (or exemption certificates), and compliance with federal certifications regarding debarment, lobbying, and non-collusion. The successful bidder must execute the contract within 15 days of award and provide performance and payment bonds. Bid security for unsuccessful bidders not deemed to have a reasonable chance of award will be returned within seven days of bid opening. No faxed proposals will be accepted. The project is funded through FDOT LAP and SCOP funding sources, with the owner exempt from Florida sales and use taxes on direct-purchased materials and equipment incorporated into the work.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID DOCUMENTS

Ash Street Widening/Resurfacing FDOT LAP And SCOP Project Taylor County, Florida

2016-006-ENG

June 2026

Prepared for:

Taylor County Board of County Commissioners 108 N. Jefferson St.

Perry, Florida 32347

Prepared by:

Taylor County Engineering NV5, Inc.

201 East Green Street 11801 Research Drive Perry, FL 32347 Alachua, FL 32615

850.838.3500 352.331.1976

FDOT LAP and SCOP Project: Ash Street 2016-006-ENG

TABLE OF CONTENTS

PART 1 - BIDDING REQUIREMENTS

Invitation to Bid Instructions to Bidders Bid Forms Hold Harmless, Release and Indemnity Agreement Public Entity Crimes Statement Affidavit Regarding Labor and Services (FDOT Form 375-030-31) Certification Regarding Debarment and Suspension (FDOT Form 375-030-32) Lobbying Certification (FDOT Form 375-030-33) Disclosure of Lobbying Activities (FDOT Form 375-030-34)

Bid Opportunity Form (FDOT Form 375-040-62) LAP Certification of Current Capacity (FDOT Form 525-010-46) Non-Collusion Declaration (FDOT Form 575-060-13) Drug-Free Workplace Program Certification, 287.087, F.S.

PART 2 - CONTRACT FORMS

Agreement between Owner and Contractor

FHWA - 1273

Bid Bond Performance Bond

Payment Bond

PART 3 – CONDITIONS OF THE CONTRACT

Standard General Conditions Supplementary Conditions

PART 4 – SUPPLEMENTAL SPECIFICATIONS

PART 5 – LAP DIVISION 1 SPECIFICATION

PART 6 – DRAWINGS (Bound Separately)

PART 1 – BIDDING REQUIREMENTS

JAMIE ENGLISH JIM MOODY MICHAEL NEWMAN PAM FEAGLE THOMAS DEMPS

District 1 District 2 District 3 District 4 District 5

GARY KNOWLES, Clerk LAWANDA PEMBERTON, County Administrator CONRAD C. BISHOP, JR., County Attorney

Post Office Box 620 201 East Green Street Post Office Box 167 Perry, Florida 32348 Perry, Florida 32347 Perry, Florida 32348

(850) 838-3506 Phone (850) 838-3500, extension 7 Phone (850) 584-6113 Phone

(850) 838-3549 Fax (850) 838-3501 Fax (850) 584-2433 Fax

INVITATION TO BID

The Taylor County Board of County Commissioners is soliciting sealed proposals for construction of the Ash Street Widening/Resurfacing LAP/SCOP Project.

Qualified firms or individuals desiring to provide the required products or services must submit five (5) packages in a sealed envelope or similar package marked “Sealed Proposal for Ash Street

Widening/Resurfacing LAP/SCOP Project” to the Clerk of Court, 1st Floor Courthouse, 108

North Jefferson Street, Suite 102, Perry, Florida 32347, to arrive no later than 4:00 P.M., local time, on August 14, 2026. All Proposals MUST have the respondent's name and mailing address clearly shown on the outside of the envelope or package when submitted. Proposals will be opened and respondents announced at 6:10 P.M. local time, or as soon thereafter as practical, on August 18, 2026, in the Taylor County Administrative Complex, 201 East Green

Street, Perry, Florida 32347.

RFP information MUST be obtained on-line from the following County Web Site address:

https://www.taylorcountygov.com/government/county_bids/index.php

Note that a Pre-Bid Conference will not be held for this project. See Instructions to Bidders, Article 5 for information concerning requests for additional information or clarification.

The County reserves the right, in its sole and absolute discretion, to reject any or all Proposals, to cancel or withdraw this solicitation at any time and waive any irregularities in the RFP process.

The County reserves the right to award any contract to the respondent which it deems to offer the best overall service; therefore, the County is not bound to award any contract(s) based on the lowest quoted price. The County, in its sole and absolute discretion, also reserves the right to waive any minor defects in the process and to accept the proposal deemed to be in the County’s best interest. No faxed Proposals will be accepted.

Additional Information may be obtained from:

Taylor County Engineering Department

201 East Green Street

Perry, FL 32347

850-838-3500

BY ORDER OF THE BOARD OF COUNTY COMMISSIONERS, Taylor County, Florida

TAYLOR COUNTY

BOARD OF COUNTY COMMISSIONERS

https://www.taylorcountygov.com/government/county_bids/index.php

EJCDC C-200 Suggested Instructions to Bidders for Construction Contracts Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

00200 – 1

INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

ARTICLE 1 - DEFINED TERMS

ARTICLE 2 - COPIES OF BIDDING DOCUMENTS

ARTICLE 3 - QUALIFICATIONS OF BIDDERS

ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE

ARTICLE 5 - PRE-BID CONFERENCE

ARTICLE 6 - SITE AND OTHER AREAS

ARTICLE 7 - INTERPRETATIONS AND ADDENDA

ARTICLE 8 - BID SECURITY

ARTICLE 9 - CONTRACT TIMES

ARTICLE 10 - LIQUIDATED DAMAGES

ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS

ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS

ARTICLE 13 - PREPARATION OF BID

ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS

ARTICLE 15 - SUBMITTAL OF BID

ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID

ARTICLE 17 - OPENING OF BIDS

ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

ARTICLE 20 - CONTRACT SECURITY AND INSURANCE

ARTICLE 21 - SIGNING OF AGREEMENT

ARTICLE 22 - SALES AND USE TAXES

ARTICLE 23 - RETAINAGE

ARTICLE 24 - CONTRACTS TO BE ASSIGNED

ARTICLE 1 - DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office--The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered. The issuing office for this project will be the Taylor County Clerk of Courts located at 1st Floor Courthouse, 108 N. Jefferson St., Suite 102, Perry, FL. Bidding procedures will be administered at the Taylor County Administrative Complex located at 201 East Green St., Perry, FL. Bid documents for this project are only available via download from the following web site:

www.taylorcountygov.com/government/county_bids/index.php.

B. Bidder/Respondent-- One who responds to this Solicitation by submitting a Bid directly to Owner as distinct from a sub-bidder, who submits a bid to Bidder.

C. Successful Bidder--The lowest, responsible and responsive Bidder to whom Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award.

ARTICLE 2 - COPIES OF BIDDING DOCUMENTS

00200 – 2

2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the Advertisement or Invitation to Bid may be obtained from the Issuing Office.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.

ARTICLE 3 - QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, within five days of Owner’s request, Bidder shall submit written evidence such as financial data, previous experience, present commitments, and such other data as may be called for below.

[A. Valid Business/Contractor Licensing/Registration Information]

[B. Proof of current qualification with the Florida Department of Transportation in Tallahassee, Florida to conduct the scope of work outlined in these specifications including Work Class: Sidewalk.]

[C. The successful Contractor and any subcontractors shall enroll in and be in compliance with the Department of

Homeland Security’s E-Verify Employment Eligibility Verification system prior to contract execution.]

ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED

DATA, AND SITE

4.01 Subsurface and Physical Conditions

A. The Supplementary Conditions identify:

1. Those reports of explorations and tests of subsurface conditions at or contiguous to the Site that Engineer has used in preparing the Bidding Documents.

2. Those drawings of physical conditions in or relating to existing surface and subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the Bidding Documents.

B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02 of the General Conditions has been identified and established in Paragraph 4.02 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions or information contained in such reports or shown or indicated in such drawings.

4.02 Underground Facilities

A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

4.03 Hazardous Environmental Condition

00200 – 3

A. The Supplementary Conditions identify those reports and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that Engineer has used in preparing the Bidding Documents.

B. Copies of reports and drawings referenced in Paragraph 4.03.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.06 of the General Conditions has been identified and established in Paragraph 4.06 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the Scope of the Work appear in Paragraph 4.06 of the General Conditions.

4.05 On request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.

4.06 Reference is made to Article 7 of the Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents. On request, Owner will provide to each Bidder for examination access to or copies of Contract Documents (other than portions thereof related to price) for such other work.

4.07 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, the other related data identified in the Bidding Documents, and any Addenda;

B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;

D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in Paragraph

4.02 of the General Conditions, and (2) reports and drawings of Hazardous Environmental Conditions at the Site which have been identified in the Supplementary Conditions as provided in Paragraph 4.06 of the General Conditions;

E. obtain and carefully study (or accept consequences of not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents, and safety precautions and programs incident thereto;

00200 – 4

F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

H. correlate the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents;

I. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and

J. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.

4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.

ARTICLE 5 - PRE-BID CONFERENCE

5.01 A Pre-Bid conference will not be scheduled for this project. Bidders shall submit all requests for additional information and clarification in writing by email to Engineer at county.engineer@taylorcountygov.com by 5:00 P.M.

local time on Friday, July 31, 2026. Engineer will post on the Project Bidding Web site and transmit to all known prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising from such requests on Friday, August 7, 2026. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 6 - SITE AND OTHER AREAS

6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.

ARTICLE 7 - INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to the County Engineer via email at county.engineer@taylorcountygov.com. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda posted, mailed or delivered to all parties recorded by Engineer as having received the Bidding Documents. Questions received less than the date specified (ten (10) days prior to the

00200 – 5 date for opening of Bids when not specified) may not be answered. Only questions answered by Addenda will be binding.

Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.

7.03 In the event of conflicting provisions within the Bid Documents and/or Contract Documents, Bidder agrees that the more restrictive requirement or provision as determined by the County shall prevail and be binding.

ARTICLE 8 - BID SECURITY

8.01 Bid security will be required for this project.

8.02 When required, A Bid must be accompanied by Bid security made payable to Owner in an amount of Five percent (5%) of Bidder’s maximum Bid price and in the form of a certified check or bank money order or a Bid bond (on the form attached) issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions.

8.03 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract Documents, furnished the required contract security and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Agreement or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be returned.

8.04 Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within seven days after the Bid opening.

ARTICLE 9 - CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.

ARTICLE 10 - LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, are set forth in the Agreement. Bidder agrees by responding to this proposal, that such terms have been reviewed prior to responding, and further, that such provisions are uncontested and acceptable.

ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration of possible substitute or “or-equal” items. Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement.

00200 – 6

ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 If the Bid Form or Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.

12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.

12.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.

12.04 Contractor shall not award work to Subcontractor(s) in excess of the limits stated in SC 6.06.

12.05 Any proposed Subcontractors shall provide proof of current licensure and prequalification in the related trade category for the work they will be performing. Further, all proposed Subcontractors shall be required to meet the same insurance requirements as that required for the Bidder either through an employee relationship or separate coverage.

Failure to provide proof of current licensure and/or insurance will be considered a violation of contract terms and conditions and result in termination of award.

ARTICLE 13 - PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents. Additional copies may be obtained from Engineer or the Issuing Office.

13.02 All blanks on the Bid Form shall be completed by printing in ink or by typewriter and the Bid signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each [section, Bid item, alternative, adjustment unit price item, and unit price item] listed therein, or the words “No Bid,” “No Change,” or “Not Applicable” entered.

13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown below the signature.

13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown below the signature.

00200 – 7

13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown below the signature.

13.06 A Bid by an individual shall show the Bidder’s name and official address.

13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown below the signature.

13.08 All names shall be typed or printed in ink below the signatures.

13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.10 The address and telephone number for communications regarding the Bid shall be shown.

13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the Contract. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents as provided for in the Bid Form. The price for each alternate will be the amount [added to] [or] [deleted from] the base Bid if Owner selects the alternate. In the comparison of Bids, alternates will be applied in the same order as listed in the Bid form.

14.02 The Bid price shall include such amounts as the Bidder deems proper for overhead and profit on account of cash allowances, if any, named in the Contract Documents as provided in Paragraph 11.02 of the General Conditions.

14.03 Bid prices will be compared after adjusting for differences in the time designated by Bidders for Substantial Completion. The adjusting amount will be determined at the rate set forth in the Contract Documents for liquidated damages for failing to achieve Substantial Completion for each day before or after the desired date appearing in Article 9.

ARTICLE 15 - SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the following data:

[A. Bid Bond (5%)]

[B. Certificates of Liability Insurance or Agency Statement]

[C. Declaration Page from Workers’ Compensation Insurance or Exemption Certificate issued by the State]

[D. Workers’ Compensation Hold Harmless Agreement (Required when submitting a W.C. exemption)]

[E. Public Entity Crimes Affidavit, signed and notarized, as required by Chapter 287.133(3)(a) ]

00200 – 8

[F. Valid Business/Contractor Licensing/Registration Information]

[G. Proof of current qualification with the Florida Department of Transportation for the designated scope of work including Work Class: Sidewalk.]

[H. List of Proposed Subcontractors and portion of work provided (Include: Scope of proposed Work, Value of work, % of total)]

[I. List of Proposed Suppliers (Include: List of proposed supplies, Value of supplies, % of total)]

[J. Proof of Contractor and any subcontractors enrollment in and compliance with the Department of Homeland

Security’s E-Verify Employment Eligibility Verification system or a statement that such compliance will be prior achieved prior to contract execution.]

[K. Affidavit Regarding Labor and Services (FDOT Form 375-030-31)]

[L. Certification Regarding Debarment and Suspension (FDOT Form 375-030-32)]

[M. Lobbying Certification (FDOT Form 375-030-33)]

[N. Disclosure of Lobbying Activities (FDOT Form 375-030-34)]

[O. Bid Opportunity Form (FDOT Form 375-040-62)]

[P. LAP Certification of Current Capacity (FDOT Form 525-010-46)]

[Q. Non-Collusion Declaration (FDOT Form 575-060-13)]

[R. Drug-Free Workplace Program Certification, 287.087, F.S.]

15.02 A Bid shall be submitted no later than the date and time prescribed and at the place indicated in the Advertisement or Invitation to Bid and shall be enclosed in an opaque sealed envelope plainly marked with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security (when required) and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “Sealed Proposal for Ash Street Widening/Resurfacing LAP/SCOP Project.”

Hand deliveries and mailed Bids shall be addressed to Clerk of Court, 1st Floor Courthouse, 108 North Jefferson Street, Suite 102, Perry, Florida 32347. Bids submitted by Overnight delivery shall also be delivered to the physical address of the Clerk of Court: Clerk of Court, 1st Floor Courthouse, 108 North Jefferson Street, Suite 102, Perry, Florida 32347.

15.03 The Taylor County Board of County Commissioners DOES NOT ACCEPT FAXED PROPOSALS.

15.04 Proposals that are not delivered to the place indicated in the Advertisement or Invitation to Bid prior to the date and time prescribed shall not be considered and will be returned to the responder unopened.

15.05 Incomplete Bid proposals that do not provide the required information and/or the required number of copies, may be deemed incomplete by the Board of County Commissioners and not considered during the Bid Evaluation.

00200 – 9

ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.

16.02 Once opened, no Bid may be withdrawn prior to the Board of County Commissioners action without written consent of the Clerk of Court.

ARTICLE 17 - OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the Advertisement or Invitation to Bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right, in its sole and absolute discretion, to reject any or all Bids, to cancel or withdraw this bid solicitation at any time and waive any irregularities in the Bid process. Owner reserves the right to award any contract to the respondent which it deems to offer the best overall service; therefore, Owner is not bound to award any contract based on the lowest quoted price. Owner, in its sole and absolute discretion, also reserves the right to waive any minor defects in the process and to accept the bid deemed to be in the County’s best interest.

19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.

19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.

19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the Contract Documents.

19.06 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project.

19.07 Should the solicitation result in a tie between two or more bidders, the County shall initiate the following action:

00200 – 10

Award to Bidder that has certified it has implemented a drug-free workplace program in accordance with Section 287.087, F.S.

Years of experience of Prime Contractor or Reject all Bids and re-solicit the service.

ARTICLE 20 - CONTRACT SECURITY AND INSURANCE

20.01 Article 5 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds.

20.02 All Proposals submitted require General Liability and Workmen’s Compensation Insurance, and must include a Certificate of Insurance showing the coverage(s) required, listing Taylor County as an additional insured, or a sworn statement from an insurance agent, verifying that if the prospective respondent is awarded the bid, a Certificate of Insurance will be issued to the successful respondent within thirty (30) days of the acceptance of the proposal, in the amount stated. Also include the Declaration Page from the insurance policy, showing Workmen’s Compensation Insurance on all employees working on the project. Any respondent, who does not furnish the required insurance documents within thirty (30) days after the bid award, is hereby advised that the bid will be given to the next lowest respondent who meets all proposal specifications. Workers’ Compensation exemptions will be accepted upon providing a current certificate, Articles of Incorporation, and a signed Taylor County Workers’ Compensation Hold Harmless Agreement. Any responder who does not furnish the required insurance documents will not be considered.

ARTICLE 21 - SIGNING OF AGREEMENT

21.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.

ARTICLE 22 - SALES AND USE TAXES

22.01 Owner is exempt from Florida state sales and use taxes on all Direct Purchased materials and equipment to be incorporated in the Work. Said taxes for such items shall not be included in the Bid. Refer to Paragraph SC-6.10 of the Supplementary Conditions for additional information.

22.02 Owner is exempt from payment of sales and compensating use taxes of the State of Florida and of cities and counties thereof on all materials to be incorporated into the Work which are Direct Purchased by Owner. Contractor purchases are not eligible for this exemption and such costs shall be accounted for within the Bid.

1. Owner will furnish the required certificates of tax exemption to Contractor for use in the purchase of Direct Purchased supplies and materials to be incorporated into the Work.

2. Owner’s exemption does not apply to supplies, materials, or construction tools, machinery, equipment, or other property purchased by or leased by Contractor, or to supplies or materials not incorporated into the Work.

00200 – 11

ARTICLE 23 - RETAINAGE

23.01 Provisions concerning Contractor’s rights to deposit securities in lieu of retainage are set forth in the Agreement.

ARTICLE 24 - CONTRACTS TO BE ASSIGNED

24.01 Owner as “buyer” will execute a contract with the successful Bidder as “seller” for the procurement of goods and special services for Ash Street Widening/Resurfacing LAP/SCOP Project. The materials and equipment provided for in the procurement contract are to be furnished and delivered to the Site [or other location] for installation by Contractor. The said procurement contract will be assigned by Owner to Contractor as set forth in the Agreement.

Contractor will accept the assignment and assume responsibility for the “seller”, who will become a Subcontractor to Contractor.

24.02 Bidders may examine the contract documents for the procurement of goods and special services for Project at the Issuing Office.

EJCDC C-410 Suggested Bid Form for Construction Contracts Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

00410 - 1

BID FORM

Ash Street Widening/Resurfacing LAP/SCOP Project

2016-006-ENG

TABLE OF ARTICLES

Article Article No.

ARTICLE 1 – BID RECIPIENT

ARTICLE 2 – BIDDER'S ACKNOWLEDGEMENTS

ARTICLE 3 – BIDDER'S REPRESENTATIONS

ARTICLE 4 – FURTHER REPRESENTATIONS

ARTICLE 5 – BASIS OF BID

ARTICLE 6 – TIME OF COMPLETION

ARTICLE 7 – ATTACHMENTS TO THIS BID

ARTICLE 8 – DEFINED TERMS

ARTICLE 9 – BID SUBMITTAL

ARTICLE 1 – BID RECIPIENT

1.01 This Bid is submitted to:

Taylor County Board of County Commissioners Clerk of Court 1st Floor Courthouse, Suite 102 108 North Jefferson St.

Perry, Florida 32347

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – BIDDER'S ACKNOWLEDGEMENTS

2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

ARTICLE 3 – BIDDER'S REPRESENTATIONS

3.01 In submitting this Bid, Bidder represents that:

A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged.

Addendum No. Addendum Date

00410 - 2

B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.

C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work.

D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in SC-4.02, and (2) reports and drawings of Hazardous Environmental Conditions that have been identified in SC-4.06.

E. Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.

F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.

I. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.

J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.

K. Bidder will submit written evidence of its authority to do business in the state where the Project is located not later than the date of its execution of the Agreement.

ARTICLE 4 – FURTHER REPRESENTATIONS

4.01 Bidder further represents that:

A. this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

D. Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.

00410 - 3

ARTICLE 5 – BASIS OF BID

5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):

Any and all specified cash allowances are included in the price(s) set forth above and have been computed in accordance with Paragraph 11.02 of the General Conditions.

Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities, determined as provided in the Contract Documents.

Bidder also acknowledges that the award of this project or any portion thereof will be contingent upon the availability of funds. If funding is not available to award the project in its entirety, the Board of County Commissioners reserves the right to award portions thereof so as to remain within available funding. Such partial award will not relieve the Bidder from complying with the full requirements of the awarded portions as more specifically detailed within these specifications.

Total Lump Sum Bid Price $ 365 Days (words) (numerals)

West/East Ash Street $ US 19 ~ Johnson Stripling

STA 111+36.46 ~ 333+66.78

(words) (numerals)

Alt 1 - East Ash Street $ Johnson Stripling ~ Helen St

STA 333+89.22 ~ 359+91.62

(words) (numerals)

Alt 2 Rework EX Sidewalk $ Ash Street (words) (numerals)

STA 127+86.01 ~ 156+32.92

Alt 3 New Sidewalk – Ash St $ STA 111+36.46 ~ 127+86.01 (words) (numerals)

Alt 4 New Sidewalk – Ash St $ STA 156+32.92 ~ 334+04.13 (words) (numerals)

Alt 5 New Sidewalk $ Johnson Stripling Rd (words) (numerals)

Copyright © 2002 National Society of Professional Engineers for EJCDC. All rights reserved.

00410 - 4

ARTICLE 6 – TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 14.07.B of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Bidder accepts and does not contest the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the Contract Times.

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.01 The following documents are attached to and made a condition of this Bid:

A. Required Bid security in the form of .

B. Certificate of Liability Insurance or Agency Statement

C. Declaration Page form Workers’ Compensation Insurance or Exemption Issued by the State of Florida

D. Workers’ Compensation Hold Harmless Agreement (Required when submitting a W.C. exemption)

E. Public Entity Crimes Affidavit, signed and notarized, as required by Chapter 287.133(3)(a), F.S.

F. Valid Business/Contractor Licensing/Registration Information

G. Proof of current qualification with the Florida Department of Transportation in Tallahassee, Florida to conduct the scope of work outlined in these specifications.

H. List of Proposed Subcontractors and portion of work provided (Include: Scope of proposed Work, Value of work, % of total)

I. List of Proposed Suppliers (Include: List of proposed supplies, Value of supplies, % of total)

J. Proof of Contractor and any subcontractors enrollment in and compliance with the Department of Homeland Security’s E-Verify Employment Eligibility Verification system or a statement that such compliance will be prior achieved prior to contract execution.

K. Affidavit Regarding Labor and Services (FDOT Form 375-030-31)

L. Certification Regarding Debarment and Suspension (FDOT Form 375-030-32)

M. Lobbying Certification (FDOT Form 375-030-33)

N. Disclosure of Lobbying Activities (FDOT Form 375-030-34)

O. Bid Opportunity Form (FDOT Form 375-040-62)

P. LAP Certification of Current Capacity (FDOT Form 525-010-46)

Q. Non-Collusion Declaration (FDOT Form 575-060-13)

R. Drug-Free Workplace Program Certification, 287.087, F.S.

ARTICLE 8 – DEFINED TERMS

8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

00410 - 5

ARTICLE 9 – BID SUBMITTAL

9.01 This Bid submitted by:

If Bidder is:

An Individual

Name (typed or printed):

By: (SEAL) (Individual’s signature)

Doing business as:

A Partnership

Partnership Name: (SEAL)

By:

(Signature of general partner -- attach evidence of authority to sign)

Name (typed or printed):

A Corporation

Corporation Name: (SEAL)

State of Incorporation:

Type (General Business, Professional, Service, Limited Liability):

By:

(Signature -- attach evidence of authority to sign)

Name (typed or printed):

Title: (CORPORATE SEAL)

Attest

Date of Authorization to do business in FLORIDA is / / .

A Joint Venture

Name of Joint Venture:

First Joint Venturer Name: (SEAL)

By:

(Signature of first joint venture partner -- attach evidence of authority to sign)

00410 - 6

Name (typed or printed):

Title:

Second Joint Venturer Name: (SEAL)

By:

(Signature of second joint venture partner -- attach evidence of authority to sign)

Name (typed or printed):

(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)

Bidder's Business Address

Phone No. Fax No.

SUBMITTED on , 20 .

State Contractor License No. . (If applicable)

HOLD HARMLESS, RELEASE AND INDEMNITY AGREEMENT

COMES NOW, (Contractor), after having obtained a State of

Florida Workers’ Compensation Exemption Certificate, a copy of which is attached hereto and marked Exhibit “A”, and in Consideration of Taylor County (Owner) having accepted said Worker’s Compensation exemption and Owner having agreed for Contractor to proceed with the following project, to-wit:

Taylor County, Florida

Contract: The intent of this contract is to secure all labor and equipment required for the Ash Street

Widening/Resurfacing LAP/SCOP project in Taylor County, Florida. This project consists of widening and resurfacing an existing approximately 19/20 ft wide road to a 24 ft wide paved roadway. This work effort will include installing limerock widening strips, reclaiming the existing asphalt, and resurfacing the approximate 1.3 mile roadway.

The project will also include reworking existing and constructing new concrete sidewalks, reshaping ditches, extending, removing and adding stormwater culverts, performance turf, signage and pavement markings, as more fully detailed in the project plans and specifications.

The term Contractor is hereby defined to include all owners, managing members, employees and successors contractually obligated to perform the above project.

The term Owner is hereby defined to include Taylor County Board of County Commissioners, it directors, employees, attorney(s), and designated representatives.

1. Contractor hereby agrees to indemnify, hold harmless and defend Owner from any liability, claim, demand, action, cause of action, suit, loss, damage, expense, cost, attorney fee, settlement or judgment as a result any injury while performing the above project. I will not allow anyone to subcontract and no other person will be allowed on the job site.

2. Contractor also hereby agrees to indemnify, hold harmless and release Owner, from any liability, claim, demand, action, cause of action, suit, loss, damage, expense, cost, settlement or judgment for any medical, dental, orthopedic, surgery or any expense as a result of any injury on said project.

3. Contractor hereby agrees to release Owner from liability of whatever kind of nature as a result of any injury on the above project.

4. Contractor hereby agrees that venue of any litigation, as a result of this Hold Harmless Release and

Indemnity Agreement shall be exclusively in Taylor County, Florida and the laws of the State of Florida shall govern.

5. Contractor hereby agrees that they have relied on the legal advice of an attorney and that they fully understand this agreement and have voluntarily executed same.

DONE AND EXECUTED this ______ day of , _______

WITNESS:

(Signature)

STATE OF FLORIDA

COUNTY OF TAYLOR

I hereby…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .