20007_Sec_J_ATTH_5_Task_1_RDT E_for_Advanced_Energy_Storage_ _Mgt_2012-10-01.docx
DOCX document 30 KB Posted
- Attached to
- Environmental Quality, Energy & Power Technology
- Solicitation number
- 5TP57120007
- Issued by
-
GSA Federal Acquisition Service
About this file
20007 Sec J ATTH 5 Task 1 RDT E for Advanced Energy Storage Mgt 2012-10-01 to be evaluated as part of the IDIQ contract award and concurrently awarded with the IDIQ contract. This Task 1 replaces the previously provided sample task.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5TP57120007 Past Performance Questionnaire 2012-08-20.doc | DOC document | |
| 5TP57120007 RFQ Sec B 2012-08-20.doc | DOC document | |
| 5TP57120007 RFQ 2012-08-20.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Task 01
Research Development Test & Evaluation for Advanced Energy Storage and Management For U.S. Air Force High Energy Demand Operations and Facilities
01 October 2012
Air Force Research Laboratory Advanced Power Technology Office (APTO) Department of the Air Force Wright-Patterson Air Force Base (WPAFB), OH
POCs:
APTO Program Manager:
Thomas Naguy, AFRL/RXSC (AFRL COTR) Phone: (937) 656-5709 Fax: (937) 656-4378 E-mail: Thomas.Naguy@wpafb.af.mil
GSA:
Benny Reyes Phone: (937) 937-431-5530 Fax: (937) 431-0137 E-mail: benny.reyes@gsa.gov
| (X) New Task | ( ) Renewal | ( ) Revision |
| (X) Work Request | ( ) Fixed Price | |
| ( ) On-Site | (X) Off-Site |
1. BACKGROUND: The Air Force Advanced Power Technology Office (AFRL/RXS) is seeking proposals for the Research Development Test and Evaluation (RDT&E) of Advanced Energy Storage and Management for U.S. Air Force high energy demand and/or challenged facilities such as High Performance Computing Centers or other Air Force critical operational facilities with high energy demands or special needs. The intent is to demonstrate Advanced Energy Storage and Management concepts and technologies in an operational environment that furthers the Air Force move toward Net Zero bases, energy independence, assurance, and security. Significantly more development, testing, and evaluation is required at Air Force and DoD installations to demonstrate the capabilities and pay-off of implementing Advanced Energy Storage and Management on a broad scale.
2. SCOPE OF WORK/OBJECTIVE: The scope of this RDT&E effort is to develop a capability and operationally demonstrate, validate and document Advanced Energy Storage technology. The program will demonstrate power quality enhancement, reduce cost of operations, and provide assured access to energy for high energy demand and/or challenged Air Force operations. The proposed technology shall be compatible with existing and synergistic with AF energy efficiency and renewable energy efforts. The demonstration proposed shall provide the AF the capability to identify and document operational, technical, and maintenance characteristics as well as the economic viability of the proposed Advanced Energy Storage and Management technology and concept. The contractor shall:
2.1. Perform AF technology integrator role successfully executing the AF approved program on schedule, fulfilling the technical requirements and within budget.
2.2. Select a high energy demand or energy challenged Air Force Facility for demonstration.
2.3. Provide a detailed infrastructure and operational study documenting analysis of needs and requirements to successful host and execute this task.
2.4. Develop a multifaceted preliminary design and demonstration test plan to provide the Air Force with the capability to generate data needed to evaluate implementation of the Advanced Energy Storage and Management Technology and Concept.
2.5. Finalize the Design, develop/procure the Advanced Energy Storage and Management System Components, install the system and execute the demonstration and test plan, evaluate and analyze the resultant data generated and provide the Air Force with a technology assessment of the Advanced Energy Storage. If there are no technical implementation issues, then the contractor shall provide an infrastructure transition checklist, technology transition and AF installation training plan.
2.6. The contractor shall keep the APTO informed on program status via the deliverables and meetings/teleconferences. These meetings are to be held monthly at a minimum. The contractor shall provide clear government visibility into program’s cost, schedule, and technical performance and risk during execution.
2.7. Contractor shall collect and report contract results in a responsible manner to ensure customer confidence in the data.
3. CONTRACTOR REQUIREMENTS: The contractor shall propose a Phased approach which includes the following:
3.1. Phase I Study, Analysis, Facility Selection, Preliminary Design & Demonstration Plan
3.1.1. Study & Analysis.
The contractor shall conduct a detailed study, analysis and assessment for implementing Advanced Energy Storage technology and concepts at a high energy demand and/or energy challenged U.S. Air Force facility, location or installation.
The study shall result in recommendations and rationale for the technology and demonstration plan. APTO shall approve the contractor proposed development, test and evaluation (DT&E) plan before proceeding to Phase II. Issues to be addressed by the study and demonstration plan include, at a minimum:
· AF test facility/location selected, criteria and justification
· Develop test facility/location operational energy requirements and historical outages
· Recommend energy storage purpose addressing to include, but not limited to, back-up power or supplemental energy applications
· Document new/emerging specific component, system integration and proposed governing control’s technical and manufacturing maturity level
· Recommended renewable energy addition or integration with existing or planned renewable projects at the designated location
· Identify key technology parameters and test metrics
· Justify DT&E recommendations
· Gather, record and analyze validated test data
· Infrastructure requirements and current shortfalls
· Training and Manpower Requirements
· Operations and Maintenance Requirements Scale-Up Considerations
· Permits, Regulatory, and AFB Coordination & Approvals
· Base Support Requirements for the Demonstration
· Economic Considerations
· Cost Benefit Analysis
· Preliminary Design for the Advanced Energy Storage and Management system to be demonstrated
· Program Cost & Schedule
3.1.2. Demonstration and Test Plan Requirements.
At the completion of the Study and Analysis, the contractor shall present a proposed 24 Month Demonstration and Test Plan to the Air Force. The proposed plan shall address, at a minimum, all of the details described in section 3.1.1. The proposed executable test plan shall use established DOD systems engineering principles for tracking, documenting, evaluating, and analyzing the data and resultant knowledge gained from this program. The contractor shall define and execute all the technical and legal paperwork and assessments required to install, test and, if required, dismantle the test system and related infrastructure.
3.1.3 Plan Approval and Phase II: The APTO will Review and approve the plan and Phase II. Approval will constitute authorization to proceed with Phase II. Approval for long lead items will be identified as early as possible and will be approve by APTO as necessary to meet the requirements of this task.
3.2. Phase II: Advanced Energy Storage and Management System Demonstration
3.2.1. Advanced Energy Storage and Management System: The contractor shall execute the APTO approved Test Plan resulting from Phase I. This includes all actions required to finalize the system design, execute the plan, procure and supply the necessary equipment, obtain permits and authorizations, install equipment, execute or train the installation/facility staff to execute and ensure documentation personnel, operations and maintenance of the system(s), monitoring all aspects of the demonstration and reporting the results to the Air Force.
3.2.2. Demonstration Assessment: At the end of the demonstration the contractor will provide an overall assessment of the technical, installation, infrastructure and operational Advanced Energy Storage and Management demonstration. Unless directed otherwise, the contractor shall develop a technology assessment and potential AF scale-up plan for the test installation. Develop a comprehensive strategic AF technology maturation timeline that discusses resolving/maturing the technology shortfalls noted in the DT&E.
3.3. Project Close-Out: Prior to the completion of the contract, the contractor will work with the Air Force to determine the final disposition of the test equipment. Contractor is to track purchased GFE equipment until disposition completed. .
4. DELIVERABLES
Data Item Number
Data Item Title
Description
Due Date
| A001 |
| Status Report |
Monthly
| A002 |
| Funds and Man-Hour Expenditure Report |
Monthly
| A003 |
| Scientific and Technical Reports |
| Contractor’s Billing Voucher |
| As required |
| A007 |
| Presentation Materials |
| Meeting & Review Slides |
Monthly Status Review – Telecon
Quarterly Program Management Review
Final Review & Stakeholder Briefing As required
120 days after award of contract
Every 120 days
30 days after Demonstration complete
| Operational/maintenance manual and training documents |
| NLT 45 days before turnover to the government or planned training |
| A008 |
| Scientific and Technical Reports |
| Final Technical Report and deliver electronic data compatible with current Air Force database |
| NLT 45 days after completion of task |
| A009? |
| Final Cost Benefit Analysis |
NLT 45 days prior to contract ending
Invoices
5 days following the monthly financial report. Submitted to ITSS.
5. MEETING ATTENDANCE/TRAVEL
5.1. Kick-Off Meeting The contractor shall conduct a kick-off meeting with the Government, 30 days after contract award (Data Item A007). The meeting topics will include, but not be limited to the following: overall project management plan, detailed scheduled and milestones, project team profile, funding spend plan, draft demonstration plan requirements, and an outline of Contractor vs. Government project responsibilities.
5.2. Meetings The contractor shall be responsible for coordinating and scheduling all meetings; however, the PM will maintain approval authority for date, time, and location of all meetings. The contractor shall prepare briefing materials, brief project status and technical data, and coordinate in advance of any meeting for PM approval. The PM has authority to attend or not attend any scheduled meetings.
6. GOVERNMENT FURNISHED FACILITIES AND INFORMATION: Based on analysis in Phase II
7. PLACE OF PERFORMANCE: Based on analysis in Phase II
8. SECURITY CLASSIFICATION: None anticipated
9. PERIOD OF PERFORMANCE: 40 Months
10. SPECIAL INSTRUCTIONS: None