This Invitation to Bid (ITB) is issued by the Board of Supervisors of Louisiana State University and Agricultural & Mechanical College for the procurement of a complete Particle Image Velocimetry (PIV) system. The solicitation, numbered RFQ-0000002867, requests one integrated PIV system capable of performing two-dimensional, two-component velocity measurements in the university's open-jet wind lab facility. The system must meet specific technical requirements including a minimum field of view of 1.0 m × 1.0 m with maximum vector spacing of 2 mm, a minimum sampling rate of 625 Hz, and capability for 15-minute continuous data acquisition with latency less than 10 seconds. The system will operate in ambient daylight conditions with flow velocities up to 40 m/s and turbulence intensity up to 35%, requiring compliance with laser safety standards ANSI Z136.1 and IEC 60825-1. Bids are due on July 23, 2026, at 11:00 AM Central Time and must be submitted electronically to lsubids@lsu.edu. The electronic bid opening will be conducted via Zoom with registration required in advance. LSU reserves the right to award on an all-or-none basis to the lowest responsive and responsible bidder.

Bid prices must be quoted on a net, firm basis for a minimum of 30 days and include FOB LSU Destination pricing with all applicable shipping and handling charges included. The supplier must register in LSU's Workday procurement system prior to bid submission and provide a completed W-9 or W-8 form. Award will be made only upon issuance of an official LSU purchase order or notification of award letter. The supplier must provide onsite installation and training for one trainee not to exceed two days at the Open-jet wind lab location, along with complete technical documentation and a minimum one-year warranty. Payment will be made within 30 days of receipt of a properly executed invoice or delivery and acceptance, whichever is later. LSU is exempt from Louisiana state and local sales and use taxes, and the supplier is responsible for all other applicable taxes. No late bids will be accepted per Louisiana Administrative Code 34:XIII.515.B. The contract is governed by Louisiana state law and the University Procurement Code.

View the file

Other files

File Type Posted
50001-2867-2.pdf PDF
50001-2867-1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID BID DUE DATE AND TIME

BOARD OF SUPERVISORS OF

LOUISIANA STATE UNIVERSITY

AND AGRICULTURAL & MECHANICAL COLLEGE

07/23/2026 11:00 AM CT

SOLICITATION RFQ-0000002867

SUPPLIER #

SUPPLIER NAME AND ADDRESS

RETURN BID TO

lsubids@lsu.edu

Buyer Amy Hill Bourgeois

Buyer Phone

Buyer Email ahill5@lsu.edu

Issue Date 07/08/2026

TITLE: Particle Image Velocimetry (PIV) System

To Be Completed By Supplier

1. _______"No Bid" (sign and return this page only).

2. _______My Company does not wish to receive future solicitations for this spend category.

3. Specify your Delivery: To be made within ____________________ days after receipt of order.

4. If applicable, Supplier's Addendum Acknowledgement/Response:

As an authorized agent/signatory of the supplier, I/we acknowledge receipt of this Addendum, and _______submit no alterations/clarifications to our original bid.

_______submit superseding revisions/clarifications to our original bid as written herein or attached hereto.

General Instructions to Suppliers

1. Sealed bids for furnishing the items and/or services specified are hereby solicited, and will be received by LSU Procurement at the "Return Bid To" address stated above, until the specified due date and time.

2. Read the entire solicitation, including all terms, conditions and specifications.

3. All bid information and prices must be typed or written in ink. Any corrections, erasures or other forms of alteration to unit price are to be initialed by the supplier.

4. Bid prices are to be quoted FOB LSU/Destination and inclusive of any and all applicable shipping and handling charges unless otherwise specified in the solicitation. Any invoiced delivery charges not quoted and itemized on the LSU purchase order are subject to rejection and non-payment.

5. Payment is to be made within 30 days after receipt of properly executed invoice, or delivery and acceptance, whichever is later.

6. By signing this solicitation, the supplier certifies compliance with all general instructions to suppliers, terms, conditions and specifications; and further certifies that this bid is made without collusion or fraud.

SUPPLIER NAME MAILING ADDRESS

AUTHORIZED SIGNATURE CITY, STATE ZIP

PRINTED NAME PHONE #

TITLE FAX #

E-MAIL FEDERAL TAX ID #

LSU IS AN EQUAL OPPORTUNITY/ACCESS UNIVERSITY Rev. 2/25

SPECIAL TERMS & CONDITIONS INVITATION TO BID Page 2

SOLICITATION RFQ-0000002867 DUE DATE 07/23/2026 DUE TIME 11:00:00 AM

Bid Submission Information

All bids must be submitted electronically to LSU Procurement Services. Bids must be received at the "Return Bid To" email address no later than the due date and time specified herein. Bids must be emailed to lsubids@lsu.edu (This email address should be used for bid submissions only). Any bids sent directly to the Buyer of record will not be forwarded to the “Return Bid To” email.

When submitting electronically, the RFQ number and solicitation title should be listed in the subject line of the email. An original and redacted copy (if applicable) must be submitted electronically. Hard copies of bids will not be accepted; therefore, they will not be evaluated.

It is the responsibility of the Supplier to ensure the bid is received by LSU Procurement by the indicated due date and time. Any delays that may occur in transmission of the bid is the responsibility of the supplier. A bid will be considered late if it is not received at the “Return Bid To” email address by the indicated due date and time.

The maximum email attachment size accepted is 125 MB. It is the supplier’s responsibility to ensure bid submission is sized such that it is successfully transmitted and received by LSU. If the bid response is too large to be emailed as one document, the bid must be sent as separate documents. Each submittal should be labeled. (Example – Bid Submittal 1 out of 3 for RFQ-000000XXXX - Title; Bid Submittal 2 out of 3 for RFQ-000000XXXX - Title, etc.). If any submittal is received late, LSU will not consider the late submittal(s).

Only the submittal(s) received by the due date and time will be considered. Late bids will not be accepted per LAC 34:XIII.515.B.

Bid Opening Information

Bid openings are held electronically. There are no in-person bid openings. To electronically attend the bid opening, use the below link to register in advance:

https://lsu.zoom.us/meeting/register/QLfFfBZmRqio9DF9ESf0QA

After registering, a confirmation email will be provided containing information about joining the bid opening.

No information or opinions concerning the ultimate contract award will be given at bid opening or during the evaluation process.

If an unforeseen circumstance beyond LSU’s control prevents bid opening, the Bid will open at the next scheduled bid opening date.

Additional Information

ALL-OR-NONE-AWARD: It is the intent of the University to award all items on an all-or-none basis to the overall lowest responsive and responsible bidder.

Bid prices for shipping are to be quoted FOB LSU/DESTINATION and inclusive of any and all applicable shipping and handling charges.

LSU is a member of the National Association of Educational Procurement (NAEP) and the E&I Cooperative Purchasing Service.

A preference, if applicable, may be allowed for products produced, manufactured, assembled, grown or harvested in Louisiana. Do you claim this preference? Yes _____ No _____. Note: Preferences shall not apply to service contracts. Is your Louisiana business workforce composed of a minimum of fifty percent Louisiana residents? Yes _____ No _____. Specify Item Number and location within Louisiana where the product is/was produced, manufactured, assembled, grown or harvested:

_________________________________________________ Note: This preference is not applicable for services.

Supplier agrees to attached insurance requirements naming Board of Supervisors of Louisiana State University and Agricultural and Mechanical College as a certificate holder an additional insured on all liability policies.

mailto:lsubids@lsu.edu mailto:lsubids@lsu.edu https://lsu.zoom.us/meeting/register/QLfFfBZmRqio9DF9ESf0QA https://lsu.zoom.us/meeting/register/QLfFfBZmRqio9DF9ESf0QA

STANDARD TERMS & CONDITIONS INVITATION TO BID Page 3

These standard terms and conditions shall apply to all LSU solicitations, unless otherwise specifically amended and provided for in the special terms and conditions, specifications, or other solicitation documents. In the event of conflict between the General Instructions to Suppliers or Standard Terms & Conditions and the Special Terms & Conditions, the Special Terms & Conditions shall govern.

Bids submitted are subject to provisions of the laws of the State of Louisiana, including but not limited to: the University Procurement Code (LAC 34:XIII. Chapters 3-25) and the terms, conditions, and specifications stated in this solicitation.

1. Supplier Enrollment Suppliers providing a bid/quote in response to a LSU solicitation must be setup in the University's new procurement system (Workday) for bid tabbing and award of a purchase order. Suppliers should complete the online supplier registration form prior to submitting a bid response and/or the bid due date and time to ensure bid tabbing can be done timely after the bid deadline.

This website is used in place of a paper form and must be accompanied with an IRS Request for Taxpayer Identification Number and Certification form (W-9 or W-8 if foreign) to collect the required business and tax information that support the University's reporting and compliance requirements. To inquire if you or your company is setup or for questions regarding setup, email suppliers@lsu.edu. The supplier enrollment form can be located at: http://www.lsu.edu/administration/ofa/procurement/ supplier_registration.php

2. Bid Delivery and Receipt Bids must be received and time-stamped at the "Return Bid To" address no later than the due date and time specified herein.

To assure consideration, your bid must be submited in a sealed envelope or package and should be clearly and prominently marked with the solicitation number and bid due date, or may be submitted in the special bid return envelope if one was furnished for that purpose.

Supplier are advised that the U.S. Postal Service does not make deliveries to our physical location. USPS mail is delivered to the University's mail center and is redelivered using internal resources. Suppliers may deliver bids by hand or by a courier service to the Procurement Office. The University shall not be responsible for any delays caused by the supplier's chosen means of bid delivery. Supplier is solely responsible for the timely delivery of its bid, and failure to meet the bid due date and time shall result in rejection of the bid. Late bids cannot be accepted per LAC 34:XIII.515.B.

3. Bid Forms Bids are to be submitted on the LSU solicitation forms provided, and must be signed by an authorized agent of the supplier in accordance with LAC 34:XIII.517. Bids submitted on other forms or in other price formats may be considered informal and may be rejected in part or in its entirety. Bids submitted in pencil and/or bids containing no original signature indicating the supplier's intent to be bound will not be accepted. Bid submissions should not be spiral bound.

4. Interpretation of Solicitation/Supplier Inquiries If supplier is in doubt as to the meaning of any part or requirement of this solicitation, supplier may submit a written request for interpretation to the Buyer-of-Record at the address and/or fax number shown above. Written inquiries must be received in the Procurement Office no later than 4:30 pm CST four (4) business days prior to the opening of bids, and shall be clearly crossreferenced to the relevant solicitation/specification in question.

No decisions or actions shall be executed by any supplier as a result of oral discussions with any LSU employee or consultant.

Any interpretation of the documents will be made by formal addendum only, issued by the Procurement Office, and mailed or delivered to all suppliers known to have received the solicitation. LSU shall not be responsible for any other interpretations or assumptions made by supplier.

5. Bid Addenda Bid Addendum is to be signed and returned with your bid. If you have already submitted your bid, and this Addendum creates a need to revise/clarify your original response in any way, you are required to submit such in writing. To be considered, your addendum response must be submitted to and received by LSU Procurement at the “Return Bid To” address stated above.

Submittals for price alterations and addenda to bids must be clearly marked with the solicitation number and the bid due date/ time and returned via fax, email, courier service, hand delivery, or USPS mail. Bid revisions received after bid opening cannot be considered, whereupon the supplier must either honor or withdraw its original bid.

6. Bid Opening Suppliers may attend the public bid opening of sealed bids. No information or opinions concerning the ultimate contract award will be given at bid opening or during the evaluation process. Written bid tabulations will not be furnished.

7. Special Accommodations Any "qualified individual with a disability" as defined by the Americans with Disabilities Act, who has submitted a bid and desires to attend the public bid opening, must notify the Procurement Office in writing not later than seven days prior to the bid opening date of their need for special accommodations. If the request cannot be reasonably provided, the individual will be informed prior to the bid opening.

Rev. 2/25 mailto:suppliers@lsu.edu mailto:suppliers@lsu.edu http://www.lsu.edu/administration/ofa/procurement/supplier_registration.php http://www.lsu.edu/administration/ofa/procurement/supplier_registration.php http://www.lsu.edu/administration/ofa/procurement/supplier_registration.php http://www.lsu.edu/administration/ofa/procurement/supplier_registration.php

STANDARD TERMS & CONDITIONS INVITATION TO BID Page 4

8. Standards of Quality Any product or service bid shall conform to all applicable federal, state and local laws and regulations, and the specifications contained in the solicitation. Any manufacturer’s name, trade name, brand name, or catalog number used in the specification is for the purpose of describing the standard of quality, performance, and characteristics desired; and is not intended to limit or restrict competition. Supplier must specify the brand and model number of the product offered in his bid. Bids not specifying brand and model number shall be considered as offering the exact product specified in the solicitation.

9. New Products/Warranty/Patents All products bid for purchase must be new, never previously used, of the manufacturer’s current model and/or packaging, and of best quality as measured by acceptable trade standards. No remanufactured, demonstrator, used or irregular products will be considered for purchase unless otherwise specified.

The manufacturer’s standard published warranty and provisions shall apply, unless more stringent warranties are otherwise required by LSU and specified in the solicitation. In such cases, the supplier and/or manufacturer shall honor the specified warranty requirements, and bid prices shall include any premium costs of such coverage.

Supplier guarantees that the products proposed and furnished will not infringe upon any valid patent or trademark; and shall, at its own expense, defend any and all actions or suits charging such infringement, and shall save LSU harmless.

10. Descriptive Information Suppliers proposing an equivalent brand or model are to submit with the bid descriptive information (such as literature, technical data, illustrations, etc) sufficient for LSU to evaluate quality, suitability, and compliance with the specifications. Failure to submit descriptive information may cause bid to be rejected. Any changes made by supplier to a manufacturer's published specifications shall be verifiable by the manufacturer. If items bid do not fully comply with specifications, supplier must state in what respect items deviate. Supplier’s failure to note exceptions in its bid will not relieve the supplier from supplying the actual products requested.

11. Bids/Prices/F.O.B. Point

• The bid price for each item is to be quoted on a “net” basis and F.O.B. LSU Destination, i.e. title passing upon receipt and inclusive of all delivery charges, any item discounts, etc.

• Bids other than F.O.B. LSU Destination may be rejected.

• Bids indicating estimated freight charges may be rejected.

• Bids requiring deposits, payment in advance, or C.O.D. terms may be rejected.

• Suppliers who do not quote “net” item prices and who separately quote an overall “lump sum” freight cost or discount for all items shall be considered as submitting an “all-or-none” bid for evaluation and award purposes; and risk rejection if award is made on an item or grouped basis.

• Prices shall be firm for acceptance for a minimum of 30 days, unless otherwise specified. Bids conditioned with shorter acceptance periods may be rejected.

• Prices are to be quoted in the unit/packaging specified (e.g. each, 12/box, etc), or may be rejected.

• In the event of extension errors, the unit price bid shall prevail.

12. Taxes Supplier is responsible for including all applicable taxes in the bid price. LSU is exempt from all Louisiana state and local sales and use taxes. By accepting an award, resident and non-resident firms acknowledge their responsibility for the payment of all taxes duly accessed by the State of Louisiana and its political subdivisions for which they are liable, including but not limited to:

franchise taxes, privilege taxes, sales taxes, use taxes, ad valorem taxes, etc.

13. Terms and Conditions This solicitation contains all terms and conditions with respect to the purchase of the goods and/or services specified herein.

Submittal of any contrary terms and conditions may cause your bid to be rejected. By signing and submitting a bid, supplier agrees that contrary terms and conditions which may be included in its bid are nullified.

14. Supplier Forms/LSU Signature Authority The terms and conditions of the LSU solicitation and purchase order/contract shall solely govern the purchase agreement, and shall not be amended by any supplier contract, form, etc.

The University’s chief procurement officer, or authorized designee, is delegated sole authority to execute/sign any supplier contracts, forms, etc, on behalf of LSU. Departments are expressly prohibited from signing any supplier forms. Any such supplier contracts/forms bearing unauthorized signatures shall be null and void, shall have no legal force, and shall not be recognized by LSU in any dispute arising therefrom. Suppliers who present any such forms to department users for signature without regard to this strict LSU policy may face contract cancellation, suspension, and/or debarment.

15. Awards Award will be made to the lowest responsible and responsive supplier. LSU reserves the right: (1) to award items separately, grouped, or on an all-or-none basis, as deemed in its best interest; (2) to reject any or all bids and/or items; and (3) to waive any informalities.

All solicitation specifications, terms and conditions shall be made part of any subsequent award as if fully reproduced and included therein, unless specifically amended in the formal contract.

Rev. 2/25

STANDARD TERMS & CONDITIONS INVITATION TO BID Page 5

16. Acceptance of Bid Only the issuance of an official LSU purchase order/contract, a Notification of Award letter, or a Notification of Intent to Award letter shall constitute the University’s acceptance of a bid. LSU shall not be responsible in any way to a supplier for goods delivered or services rendered without an official purchase order/contract or award letter. Bid tabulations may be requested after acceptance of bid.

17. Applicable Law All contracts shall be construed in accordance with and governed by the laws of the State of Louisiana.

18. Awarded Products/Unauthorized Substitutions Only those awarded brands and numbers stated in the LSU contract are approved for delivery, acceptance, and payment purposes. Any substitutions require prior approval of the Procurement Office. Unauthorized product substitutions are subject to rejection at time of delivery, post-return at supplier's expense, and non-payment.

19. Testing/Rejected Goods Supplier warrants that the products furnished will be in full conformity with the specification, drawing or sample, and agrees that this warranty shall survive delivery, acceptance, and use. Any defect in any product may cause its rejection. LSU reserves the right to test products for conformance to specifications both prior to and after any award. Supplier shall bear the cost of testing if product is found to be non-compliant. All rejected goods will be held at supplier's risk and expense, and subject to supplier's prompt disposition. Unless otherwise arranged, rejected goods will be returned to the supplier freight collect.

20. Delivery Supplier is responsible for making timely delivery in accordance with its quoted delivery terms. Supplier shall promptly notify the LSU Department and/or Procurement Office of any unforeseen delays beyond its control. In such cases, LSU reserves the right to cancel the order and to make alternative arrangements to meet its needs.

21. Default of Supplier Failure to deliver within the time specified in the bid/award will constitute a default and may be cause for contract cancellation.

Where the University has determined the supplier to be in default, LSU reserves the right to purchase any or all goods or services covered by the contract on the open market and to surcharge the supplier with costs in excess of the contract price.

Until such assessed surcharges have been paid, no subsequent bids from the defaulting supplier will be considered for award.

22. Supplier Invoices Invoices shall reference the LSU purchase order number, supplier's packing list/delivery ticket number, shipping/delivery date, etc. Invoices are to be itemized and billed in accordance with the order, and submitted on the supplier's own invoice form.

Invoices submitted by the supplier's third party supplier are not acceptable.

23. Delinquent Payment Penalties Delinquent payment penalties are mandated and governed by Louisiana R.S. 39:1695. Supplier penalties to the contrary shall be null and void, shall have no legal force, and shall not be recognized by LSU in any dispute arising therefrom.

24. Assignment of Contract/Contract Proceeds Supplier shall not assign, sublet or transfer its contractual responsibilities, or payment proceeds thereof, to another party without the prior written consent and approval of the Procurement Office. Unauthorized assignments of contract or assignments of contract proceeds shall be null and void, shall have no legal force, and shall not be recognized by LSU in any dispute arising therefrom.

25. Right to Piggyback Where this solicitation may name one department as the primary contract user, LSU reserves the right to authorize additional departments/campuses to use the contract as their needs arise; and Vendor shall honor all such purchase orders.

26. Contract Cancellation LSU has the right to cancel any contract for cause, in accordance with procurement rules and regulations, including but not limited to: (1) failure to deliver within the time specified in the contract; (2) failure of the product or service to meet specifications, conform to sample quality or to be delivered in good condition; (3) misrepresentation by the supplier; (4) fraud, collusion, conspiracy or other unlawful means of obtaining any contract with the University; (5) conflict of contract provisions with constitutional or statutory provisions of state or federal law; (6) any other breach of contract. LSU has the right to cancel any contract for convenience at any time by giving thirty (30) days written notice to the supplier. In such cases, the supplier shall be entitled to payment for compliant deliverables in progress.

27. Prohibited Contractual Arrangements Per Louisiana R.S. 42:1113.A, no public servant, or member of such a public servant’s immediate family, or legal entity in which he has a controlling interest shall bid on or enter into any contract, subcontract, or other transaction that is under the supervision or jurisdiction of the agency of such public servant. See statute for complete law, exclusions, and provisions.

Rev. 2/25

STANDARD TERMS & CONDITIONS INVITATION TO BID Page 6

28. Equal Employment Opportunity Compliance By submitting and signing this bid, supplier agrees to abide by the requirements of the following as applicable: Title VI and VII of the Civil Rights Act of 1964, as amended by the Equal Opportunity Act of 1972; federal Executive Order 11246; federal Rehabilitation Act of 1973, as amended; the Vietnam Era Veteran’s Readjustment Assistance Act of 1974; Title IX of the Education Amendments of 1972; the Age Act of 1975; the Americans with Disabilities Act of 1990. Supplier agrees not to discriminate in its employment practices, and will render services under any contract entered into as a result of this solicitation without regard to race, color, religion, sex, age, national origin, veteran status, political affiliation, handicap, disability, or other non-merit factor. Any act of discrimination committed by supplier, or failure to comply with these statutory obligations when applicable, shall be grounds for termination of any contract entered into as a result of this solicitation.

29. Mutual Indemnification Each party hereto agrees to indemnify, defend, and hold the other, its officers, directors, agents and employees harmless from and against any and all losses, liabilities, and claims, including reasonable attorney’s fees arising out of or resulting from the willful act, fault, omission, or negligence of the indemnifying party or of its employees, contractors, or agents in performing its obligations under this agreement, provided however, that neither party hereto shall be liable to the other for any consequential damages arising out of its willful act, fault, omission, or negligence.

30. Certification of No Suspension or Debarment By signing and submitting this bid, supplier certifies that its company, any subcontractors, or principals thereof, are not suspended or debarred under federal or state laws or regulations. A list of parties who have been suspended or debarred by federal agencies is maintained by the General Services Administration and can be viewed on the internet at www.sam.gov.

31. Right to Audit The University shall be entitled to audit the books and records of a supplier or any subcontractor under any negotiated contract or subcontract to the extent that such books and records relate to the performance of such contract or subcontract. Such books and records shall be maintained by the supplier for a period of five (5) years from the date of final payment under the prime contract and by the subcontractor for a period of five (5) years from the date of final payment under the subcontract, pursuant to

LAC 34:XIII.1603.

32. Data Privacy By signing and submitting this bid, I hereby authorize that all information provided in this solicitation, including any and all personal or company data may be shared with LSU departments, suppliers and other governmental agencies to facilitate procurement transactions. This data will be retained according to LSU’s retention schedule. To learn more about privacy at LSU, please see the LSU Privacy Statement.

Rev. 2/25 https://www.sam.gov https://www.sam.gov http://www.lsu.edu/privacy/ http://www.lsu.edu/privacy/

PRICE SHEET INVITATION TO BID Page 7

ITEM

NO.

ITEM DESCRIPTION QUANTITY UOM UNIT PRICE EXTENDED

AMOUNT

UNLESS SPECIFIED ELSEWHERE, SHIP ALL ITEMS TO:

LSU

3255 Patrick F. Taylor Hall Baton Rouge, LA 70803

1 All or None

Particle Image Velocimetry (PIV) System per attached specifications.

Specify Manufacturer / Brand Bid:

Specify Model / Number Bid:

1 Each $____________ $_____________

Technical Specifications for a Particle Image Velocimetry (PIV) System

Purpose: The purpose of this solicitation is to obtain competitive bids to obtain a Particle Image Velocimetry (PIV) system for the Open-jet wind lab at Louisiana State University.

This document defines the technical and performance specifications for the procurement of a Particle Image Velocimetry (PIV) system for advanced experimental wind engineering research.

The system shall be a complete, integrated solution capable of delivering high-quality, quantitative velocity measurements and flow visualizations under large-scale and open-environment wind testing conditions.

The complete PIV system shall include the following requirements:

1. System Overview

The PIV system shall be a complete, modular and upgradable system capable of performing two-dimensional, two-component (2D/2C) velocity measurements.

2. Application-Specific Requirements

The system will be used in a non-conventional open-jet wind lab facility characterized by:

− Open-jet test section exposed to ambient daylight conditions.

− High flow velocities (minimum 40 m/s, turbulence intensity up to 35%).

The system must therefore be capable of reliable operation under ambient light exposure, while maintaining high measurement fidelity in high-speed turbulent flows.

3. Measurement Requirements

The PIV system shall be capable of providing accurate and repeatable measurements of the following flow quantities:

− Instantaneous and time-averaged velocity fields (two components: u(t), and v(t)).

− Turbulence statistics, including:

o Turbulence Intensity.

o Reynolds stresses.

4. Measurement Domain and Spatial Resolution Requirements

− Minimum Field of View (FOV): 1.0 m × 1.0 m − Maximum Vector spacing : 2 mm for the above FOV.

5. Temporal Resolution Requirements

− Minimum sampling rate required: 625 Hz.

− A minimum duration of 15 minutes under 625Hz sampling rate, for the domain and spatial resolution mentioned above. The system must have suitable hardware capabilities to acquire and transmit data at a reasonable speed without latency problems (less than 10 s after the experiment is complete).

− A minimum signal-to-noise ratio of 100 under outdoor or semi-outdoor conditions.

6. Software Requirements

− Data acquisition software included.

− Export compatibility of raw data in formats readable by MATLAB (or equivalent), Python

(or equivalent), and Tecplot (or equivalent), for the creation of high quality 2D average, minimum, maximum, and root mean square (RMS) velocity contours from measured data, over the mentioned domain (1.0 m × 1.0 m).

7. Seeding and Optics

− Suitable seeding system for air flows, consistent with all above requirements.

− Uniform particle distribution capability, consistent with all above requirements.

− Optical mounts and alignment system for large-scale setup, for a fully operational system.

8. Environmental and Safety Requirements

− Compliance with laser safety standards (ANSI Z136.1 and IEC 60825-1).

− Appropriate shielding and safety enclosures.

− Suitable for laboratory and open-environment operations.

9. Documentation and Support

− Complete technical documentation and manuals.

− Supplier must provide onsite installation of equipment and on-site training. Onsite training will be conducted at the Open-jet wind lab at Louisiana State University, for one (1) trainee not to exceed two (2) days.

− Minimum one-year warranty.

Amy Bourgeois Highlight

ADPDE53.tmp
Technical Specifications for a Particle Image Velocimetry (PIV) System
1. System Overview
2. Application-Specific Requirements
3. Measurement Requirements
4. Measurement Domain and Spatial Resolution Requirements
5. Temporal Resolution Requirements
6. Software Requirements
7. Seeding and Optics
8. Environmental and Safety Requirements
9. Documentation and Support