This document is a specification for the drydock repairs and maintenance on the USCGC FREDERICK HATCH (WPC 154) cutter scheduled for fiscal year 2025. The key details are:

The specification outlines various work items that the contractor must perform, including inspecting and preserving the hull plating, tanks and voids, sewage and grey water system, stern tube interiors, rudder assemblies, stabilizing fins, propulsion shafting system, and other mechanical systems. The government may provide new or refurbished equipment for certain components. The work must be performed in accordance with various Coast Guard drawings, technical publications, and standard specifications. Critical inspection points are identified, and certain preservation and welding requirements are specified. The estimated period of performance is from March 25, 2025 to July 22, 2025, and the work will be executed at the contractor's facility.

View the file

Other files for this federal contract opportunity

Other files attached to DRYDOCK: USCGC FREDERICK HATCH DD FY25, newest first.
File Type Posted
Attachment1 Schedule of Services_Rev HATCH DD.xlsx XLSX spreadsheet
Attachment 3 - Operational Foreseeable Cost.xlsx XLSX spreadsheet
70Z08025QPBPL00020004_US signed.pdf PDF
QUESTIONS_ANSWERS.pdf PDF
70Z08025QPBPL00020003.pdf PDF
70Z08025QPBPL00020002_US HATCH signed.pdf PDF
70Z08025QPBPL00020001_US HATCH Amendment signed.pdf PDF
Attachment 1 Schedule of Services_Rev.xlsx XLSX spreadsheet
Schedule of Services - CGC FREDERICK HATCH DD.xlsx XLSX spreadsheet
70Z08025QPBPL0002_0_US COMBINED SYNOPSIS SOLICITATION FREDERICK HATCH DD REPAIRS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC FREDERICK HATCH (WPC 1143)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2025

Developed By: Brandon M Triepke

(Rev-0 21 August 2024)

USCGC FREDERICK HATCH (WPC-154) DRYDOCK AVAILABILITY FY2025

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items ........................................................................................... xii Principal Characteristics ............................................................................................................................ xiii General Requirements WORK ITEM 1: Hull Plating, Inspect WORK ITEM 2: Tanks and Voids, Inspect and Preserve WORK ITEM 3: Sewage and Grey Water System, Clean and Inspect WORK ITEM 4: Stern Tube Interiors, Preserve WORK ITEM 5: Rudder Assemblies, Inspect and Repair WORK ITEM 6: Stabilizing Fins, Inspect and Repair WORK ITEM 7: Propulsion Shafting System, Inspect and Repair WORK ITEM 8: Bow Thruster Propeller and Tunnel, Inspect and Repair WORK ITEM 9: HVAC Duct System, Clean WORK ITEM 10: Machinery Ventilation System, Clean WORK ITEM 11: ASW/Firemain System Components, Renew/Overhaul WORK ITEM 12: Impressed Current Cathodic Protection (ICCP) and Anti-Fouling System, Inspect and

Maintain WORK ITEM 13: Stern Launch Door, Inspect and Preserve WORK ITEM 14: Electrical Power Distribution System, Thermographic Inspection (450 VAC And

Below) WORK ITEM 15: Drydocking WORK ITEM 16: Temporary Services, Provide - Cutter WORK ITEM 17: U/W Body, Preserve WORK ITEM 18: Freeboard, Preserve WORK ITEM 19: Weatherdecks, Preserve WORK ITEM 20: Superstructure, Preserve WORK ITEM 21: Mast, Preserve WORK ITEM 22: Louver Assembly, Overhaul WORK ITEM 23: Watertight Closures, Assess WORK ITEM 24: Sea Trial Performance, Support, Provide WORK ITEM 25: Reduction Gear, Housing Cover, Renew iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 079-900, Rev D, Stability and Loading Data Booklet

Coast Guard Drawing 154 WPC 079-902, Rev -, Curves of Form Hydrostatic Analysis

Coast Guard Drawing 154 WPC 085-301, Rev B, Hull Lines and Offsets

Coast Guard Drawing 154 WPC 127-302, Rev C, Potable Water & Sewage Tank Fabrication Details

Coast Guard Drawing 154 WPC 168-201, Rev F, Louvers and Covers A&D

Coast Guard Drawing 154 WPC 171-601, Rev D, Mast Prefab

Coast Guard Drawing 154 WPC 204-301, Rev F, Equipment Removal Plan

Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram

Coast Guard Drawing 154 WPC 528-301, Rev B, Grey Water System Diagram

Coast Guard Drawing 154 WPC 529-301, Rev -, Bilge System Diagram

Coast Guard Drawing 154 WPC 556-302, Rev D, Fin Stabilizer Hydraulic System Diagram

Coast Guard Drawing 154 WPC 561-202, Rev C, Steering Arrangement & Details

Coast Guard Drawing 154 WPC 565-201, Rev -, Fin Stabilizer System A&D

Coast Guard Drawing 154 WPC 593-303, Rev A, Sewage Control System

Coast Guard Drawing 154 WPC 633-301, Rev C, Cathodic Protection System

Coast Guard Drawing 154 WPC 995-900, Rev -, FRC Docking Assembly Details & Construction

Coast Guard Drawing 154 WPC 997-002, Rev A, Alternate Docking Plan Mobile Lift Option

Coast Guard Drawing 154 WPC 997-004, Rev A, Steel Block Towers for Alternate Docking Plan

Coast Guard Drawing 154 WPC 997-302, Rev -, Docking Plan (Supersedes DWGS 154-WPC-997-1, 997-301)

Coast Guard Drawing 154B WPC 111-301, Rev A, Shell Expansion

Coast Guard Drawing 154B WPC 131-301, Rev B, Scantlings Main Deck

Coast Guard Drawing 154B WPC 161-301, Rev -, Skegs and Stern Tubes Support Structures

Coast Guard Drawing 154B WPC 167-201, Rev A, Schedule of Doors, Manholes, and Hatches

Coast Guard Drawing 154B WPC 169-201, Rev -, Structural Closure Stern Gate

Coast Guard Drawing 154B WPC 171-201, Rev B, Mast A&D

Coast Guard Drawing 154B WPC 204-301, Rev -, Equipment Removal Plan

Coast Guard Drawing 154B WPC 243-201, Rev A, Main Propulsion Shafting A&D

Coast Guard Drawing 154B WPC 245-301, Rev -, Propeller Plans and Data Six Blade Propeller v (Rev-0)

Coast Guard Drawing 154B WPC 251-301, Rev -, Combustion Air Diagram

Coast Guard Drawing 154B WPC 256-301, Rev A, Main and Auxiliary Cooling System Diagram

Coast Guard Drawing 154B WPC 320-301, Rev -, 450V System Deck Plan

Coast Guard Drawing 154B WPC 330-301, Rev B, 120V System Deck Plan

Coast Guard Drawing 154B WPC 405-201, Rev -, Antenna A&D

Coast Guard Drawing 154B WPC 405-202, Rev -, Antenna Arrangement and Installation

Coast Guard Drawing 154B WPC 406-301, Rev D, Schedule of Bonding and Grounding

Coast Guard Drawing 154B WPC 422-301, Rev -, Electrical Navigational Aids

Coast Guard Drawing 154B WPC 506-201, Rev C, Fills, Vents, Sounds, Overflows Arrangement

Coast Guard Drawing 154B WPC 512-201, Rev C, HVAC Arrangement

Coast Guard Drawing 154B WPC 512-301, Rev A, HVAC System Diagram

Coast Guard Drawing 154B WPC 512-305, Rev -, HVAC Equipment List

Coast Guard Drawing 154B WPC 513-201, Rev B, Machinery Ventilation Arrangement

Coast Guard Drawing 154B WPC 513-301, Rev A, Machinery Ventilation Diagram

Coast Guard Drawing 154B WPC 556-202, Rev -, Fin Stabilizer Hydraulic System A&D

Coast Guard Drawing 154B WPC 562-201, Rev -, Rudder Details

Coast Guard Drawing 154B WPC 562-202, Rev -, Rudder Arrangement & Details

Coast Guard Drawing 154B WPC 565-301, Rev -, Fin Stabilizer Control System

Coast Guard Drawing 154B WPC 565-302, Rev -, Fin Stabilizer Control System COED

Coast Guard Drawing 154B WPC 568-201, Rev B, Bow Thruster System A&D

Coast Guard Drawing 154B WPC 593-201, Rev B, Sewage System Arrangement

Coast Guard Drawing 154B WPC 593-301, Rev A, Sewage System Diagram

Coast Guard Drawing 154B WPC 601-302, Rev -, General Arrangement

Coast Guard Drawing 154B WPC 602-305, Rev B, Visual Identification and Draft Marks Plan

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 8000, SWBS 256, Apr 2015, Main Engine Seawater Strainer, 10 Inch Duplex Basket Strainer

Coast Guard Technical Publication (TP) 8001B, SWBS 633, Sep 2018, Cathodic Protection System – Model CA44227

Coast Guard Technical Publication (TP) 8010B, SWBS 565, May 2019, Fin Stabilizer System – Model QC-1500 with MPU20 Hydraulic System

Coast Guard Technical Publication (TP) 8081A, SWBS 243, Apr 2018, Stern Tube Seal with Emergency Packing Gland

Coast Guard Technical Publication (TP) 8096B, SWBS 252, Aug 2018, Bowthruster – Model 60 LK with Operator Panel and Motor Drive – Installation, Service, and Operation Manual

Coast Guard Technical Publication (TP) 8123, SEP 2019, Preliminary - Heating, Ventilation, and Air Conditioning System - Frc-514-P1

Coast Guard Technical Publication (TP) 8153A, SWBS 562, Apr 2019, Rudderstock Seal Assembly, Type EL + IS, Model H 78525-01

Coast Guard Technical Publication (TP) 8911B, SWBS 086, Apr 2020, Technical Repair Standard for Use on FRC - Fin Stabilizer System Model QC-1500 vi (Rev-0)

Coast Guard Technical Publication (TP) 8913A, SWBS 086, Mar 2020, Technical Repair Standard for Propellers

Coast Guard Technical Publication (TP) 8916, SWBS 086, 28 JUL 2020, TECHNICAL REPAIR

STANDARD FOR USE ON FRC - FLOW ADAPTIVE RUDDER AND EL + IS RUDDERSTOCK

SEAL MODEL - H 78525-01 (HULLS 1118, 1139 AND ON) 154' WPC (A) AND (B) CLASS

CUTTERS

Coast Guard Technical Publications (TP) 6632, SWBS 6633, Jul 2015, Reduction Gear – Model ZF 280-1

Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC Electrical Motors

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses

TP 8026-241-A, Preliminary - ZF Marine Transmission Model: ZF 23560 C/D Series Part Number:

3090.002.029 Operations and Maintenance Manual

OTHER REFERENCES

American Bureau of Shipbuilding (ABS) Rules for Survey After Construction, Part 7

American Society for Nondestructive Testing, SNT-TC-1A: Personnel Qualification and Certification in Nondestructive Testing, 2016

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates vii (Rev-0)

Coast Guard Maintenance Procedure Card (MPC) B10017.D, CONVERSION B/T ANODE BOLT (1 Time, 01-32)

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

Commercial Item Descriptions (CID) A-A-59316, Nov 2003; Abrasive Materials for Blasting

DOD-STD-2003, Dec 1990, Electric Plant Installations, Standard Methods for Surface Ships and Submarines (Cable), Figures 1B5, 3B19, 3B20, 3B21

Federal Standard (FED-STD) 595, 2008, Colors Used In Government Procurement

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL-C-16173, Jan 1993, Corrosive Preventative Compound, Solvent Cutback, Cold Application

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use

MIL-PRF-24667, Jun 2005, Coating system, Non-Skid, for Roll or Spray Application

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

QPL-24667, May 2006, Qualified Product List of Products Qualified under Performance Specification MIL-PRF-24667, Coating system, Non-Skid, for Roll or Spray Application

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE No.2 2004, Near White Blast Cleaning) viii (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

3 N **Sewage Tank Zinc

Anode

NIIN: 014474686 2 142.19

5 Y **Port Rudder NSN: 2040-01-690-5509 1 ea. 30,000 5 Y **Stbd Rudder NSN: 2040-01-690-5507 1 ea. 30,000 5 N Stock Seal Overhaul

Kit (Full-Service Kit from TP-8153, pg 7-2, Table

7-1)

NSN: 2040-01-597-6204

PN: H78525-01

2 kt 13,867.71

5 N Locknut PC5 154WPC 562-002

NSN: 5310-33-201-6431 PN:

KM32

4 ea. 100.00

5 N Lock Washer PC6

154WPC 562-002

NSN: 5310-33-201-5247 PN:

MB 32

2 ea. 150.00

5 N Upper Roller Bearing

PC7 154WPC 562-002

NSN: 3110-01-597-3537 PN:

23032 CC/C2W33

2 ea. 502.11

5 N Oil Seal PC8 154WPC 562-002

NSN: 5330-01-618-5091 PN:

CR70028 CRWH1R

2 ea. 60.00

5 N Lower Bearing PC9

154WPC 562-002

NSN: 3120-01-631-4104 2 ea. 1,162.00

6 Y **Fin Blade NSN: 2040-01-598-8181 PN:

601-15-020S02-00-00-A

2 ea. 22,254.38

6 N **Hydraulic Cylinder NSN: 9999-01-682-3497 PN:

304-07-070040-00-01-ABS_C

4 ea. 5,723.55

6 Y **Shaft, Shouldered NSN: 3040-01-659-0358 PN:

601-15-S00001-00-05_F

2 ea. 12,076.58

7 Y **Propeller Shaft NSN: 2010-01-605-7516 2 ea. 103,000 7 Y **LH Propeller NSN: 2010-01-628-0276 PN:

531915 1 ea. 190,000

7 Y **RH Propeller NSN: 2010-01-627-9761 531914

1 ea. 190,000

7 N **Stave Kit (each kit contains 8 reg. Romor staves, 2 rubber locking staves, 2 Romor staves w/keeper slot)

NSN: 3120-01-605-7400 P/N:

80920203000003

4 kt 2430

7 N **FWD Bearing Split External Retaining Ring

Kit (each kit contains 1ea retaining ring, 10ea socket head cap screws)

NSN: 3120-01-605-7345 P/N:

80920203000004

2 kt 1970

7 N **AFT Bearing Split External Retaining Ring

Kit (each kit contains

NSN: 3120-01-605-7510 P/N:

80920203000005

2 kt 2575 ix (Rev-0)

1ea retaining ring, 10ea socket head cap screws)

7 N **Kit, Installation Part- Replacement (see note

4.1 for kit contents)

NSN: 2010-01-629-4693 P/N:

950700

2 kt 1900

7 Y *Kit, Propeller – Removal/Installation Tools and Equipment (see note 4.2 for kit contents)

NSN: 2010-01-632-2198/ P/N:

999120

1 kt 22,970

7 N Shaft Seal Overhaul Kit (see table 7-4 of TP- 8081, pg 7-8, Service

Kit B)

NSN:5330-01-618-5248 P/N:

H76214-6

2 kt 5650.93

7 N **Shaft Seal Overhaul Kit (see table 7-5 of TP-

8081, pg 7-9, Service Kit C)

NSN: 5330-01-618-5276 P/N:

H76214-8

2 kt 4896

7 N Anodes, Zinc (stern tube)

NIIN: 01-644-5483 P/N:

Z0020202H3

28 ea. 50

7 N CAD Model of LH & RH propellers for use in propeller scans and analysis

N/A 1 ea. 1

8 N **Set of bevel gears 19:28, Mfr: Schottel

NSN: 3020-01-618-1133 PN:

1088301

1st. 10,378.13

8 Y **Propeller, Mfr:

Schottel

NSN: PN: 1161329 1ea. 20,000.00

12 N **Anode, Corrosion, Elliptical

NSN: 5340-99-400-2561 PN:

PPEC1202-MM50

2 ea. 1,900.00

12 N **Silver/Silver Chloride Reference Electrode

Cell

NSN: 6630-99-553-5405 PN:

PPR100019

2 ea. 1,625.00

12 N Copper Anode, Anti- Fouling

NSN: 5342-99-133-5325 PN:

PAAZRRY037FT

3 ea. 436.69

17 N **Depth Sounder Transducer

NSN: 5845-01-586-7921

P/N: SS164-20-10-F

1 ea. $1,021.28

17 Y **Speed log transducer NSN: 6605-99-839-3629 1 ea. $9,458.38 17 N Parts Kit, Gate Valve

(Doppler Speed Log)

NSN: 4820-99-374-5925 P/N:

81702-0410-00 1 ea. $1,000.00

17 N Zinc Anodes NIN: 01-647-6179 P/N:

DS620

4 ea. $50.00

25 N ***COVER 3090303045 1 ea. 3,377.00 25 N ***TUBE 3090306027 1 ea. 80.50

25 N ***HEX BOLT

M10X55 BOX

0636100417 1 ea. 138.00

25 N ***BUSHING PLUG 3090303019 1 ea. 123.00

25 N ***PISTON RING

100X2.5 SH

0634402163 01 1 ea. 202.40 x (Rev-0)

25 N ***O-RING 0634303314 01 2 ea. 6.40 25 N ***PIN, ZF 4650 0731201586 01 1 ea. 40.80 25 N ***WASHER 0630100294 01 1 ea. 1.60

25 N ***PISTON RING

32X2 SH

0634402051 01 1 ea. 70.40

25 N ***RING OR 0.50X4

FM75

0634313622 01 1 ea. 16.00

25 N ***BOLT, HEXAGON 0636100796 01 2 ea. 3.20 25 N ***WASHER 0630100295 01 2 ea. 1.60 25 N ***O-RING, ZF 4650 0634303485 01 1 ea. 5.60 25 N ***THREADED BUSH 3090303020 01 1 ea. 239.20 25 N ***O-RING, ZF 4650 0634303485 01 1 ea. 5.60 25 N ***OIL PUMP 3082206015 01 1 ea. 6,172.80 25 N ***GASKET 3082306141 01 2 ea. 26.40 25 N ***KEY 0631501069 01 1 ea. 5.60

25 N ***RING A20X1 2

DIN471

0630501016 01 1 ea. 3.20

25 N ***M 10 X 65 STUD 0636100250 01 2 ea. 4.80 25 N ***NUT, HEXAGON 0637006281 01 2 ea. 3.20 25 N ***SPACER 3082306038 01 2 ea. 87.20

25 N ***SCREW UNION

M26X1.5 0737835235 01 1 ea. 112.00

25 N ***WASHER

SEALING 3/4 BSP

0630050047 01 10 ea. 156.00

25 N ***SCREW UNION

M26X1.5

0737835237 01 1 ea. 196.00

25 N ***SOCKET 0637101477 01 1 ea. 44.80

25 N ***CU SEALING

RING A22X27 D

0634801074 01 1 ea. 2.40

25 N ***HOSE PIPE 0632100352 01 1 ea. 250.40 25 N ***UNION SCREW 0637100510 01 2 ea. 35.20

25 N ***WASHER

SEALING

0630050045 01 7 ea. 34.40

25 N ***SCREW UNION

M26X1.5

0737835234 01 1 ea. 109.60

25 N ***PIPE 3090207020 01 1 ea. 669.60

25 N ***SCREW UNION

M26X1.5 0737835236 01 1 ea. 289.60

25 N ***BALL 0635460083 01 2 ea. 14.40 25 N ***CLAMP M22X25 0632311338 01 3 ea. 28.00 25 N ***SHACKLE 3085310011 01 1 ea. 22.40 25 N ***BOLT, HEXAGON 0636100796 01 1 ea. 3.20 25 N ***WASHER 0630100276 01 2 ea. 2.40 25 N ***NUT STUD M8 R 0637006172 01 1 ea. 3.20

25 N ***PIPE KPL., ZF

23560 3090207022 01 1 ea. 468.80

25 N ***UNION SCREW 0737835250 01 1 ea. 93.60 25 N ***CABLE MARINE 6029018060 01 1 ea. 3,804.00 xi (Rev-0)

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item

Title

1 Hull Plating, Inspect

2 Tanks and Voids, Inspect and Preserve

3 Sewage and Grey Water System, Clean and Inspect

4 Stern Tube Interiors, Preserve

5 Rudder Assemblies, Inspect and Repair

6 Stabilizing Fins, Inspect and Repair

7 Propulsion Shafting System, Inspect and Repair

8 Bow Thruster Propeller and Tunnel, Inspect and Repair

11 ASW/Firemain System Components, Renew/Overhaul

Impressed Current Cathodic Protection (ICCP) and Anti-Fouling System, Inspect and Maintain

13 Stern Launch Door, Inspect and Preserve

17 U/W Body, Preserve

18 Freeboard, Preserve

19 Weatherdecks, Preserve

20 Superstructure, Preserve

21 Mast, Preserve

24 Sea Trial Performance, Support, Provide xiii (Rev-0)

PRINCIPAL CHARACTERISTICS

154' WPC (SENTINEL CLASS)

PHYSICAL

Anchor ROCNA, anchor, 150 KG/ 331 LB, Stainless Steel Bulkheads (7), Watertight Bulkheads located below the Main Deck Displacement, delivery, light ship 302 Metric Tons Draft, full load 2.58 Meters (8.46 Feet) End of service life displacement 353 Metric Tons Framing Longitudinal Full load displacement 353 Metric Tons Height of highest projection 17.22 Meters (56.5 Feet) Length overall (loa) 46.80 Meters (153.5 Feet) Maximum beam 7.75 Meters (25.43 Feet) Minimum operating displacement 314 Metric Tons Waterline length (lwl) 44.35 Meters (145.5 Feet)

HULL

Hull/main weatherdeck material AH-36 Steel Superstructure 5456-H1111 Aluminum

MACHINERY

Bow thruster Schottel STT 60 LK Diameter of propeller 1900 mm Emergency service generator (edg) Cummins 6BTA5.9-DM Diesel with Stanford 93KW Generator Fin stabilizer (2), Quantum QC1500 Main propulsion (2), MTU 20V4000 M93L, Sequential Turbo-Charged Diesels Number of blades 6 Number of propellers (2) Michigan Wheel Marine Propeller pitch capability Fixed Propulsion shafts (2), Electralloy Nitronic 50HS (9430mm) Shafts Reduction gears (2), ZF 23560C/D Series Rudders (2), 316L Stainless Steel Shaft rotations per minute 478 Shaft(s) bearing, aft (2), Duramax Bearings Shaft(s) bearing, intermediate (2), Duramax Bearings Shaft(s) diameter 8 Inches Shaft(s) Seal (2), Wartsila Mechanical Seals Ship service generators (2), Cummins QSM11-DM Diesels with Stanford 317KW Generator

TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)

Fresh water tank, port (3-38-2-w) 708 gal Fresh water tank, stbd (3-38-1-w) 756 gal Fuel oil edg day tank (1-10-1-f) 134 gal Fuel oil gen. ovrflw tnk, ctr. (3-40-0-f) 1,159 gal Fuel oil overflow tank, center (3-10-0-f)

616 gal

Fuel oil service tank, #1 port (3-17-2-f) 1,750 gal Fuel oil service tank, #1 stbd (3-17-1-f) 1,750 gal Fuel oil service tank, #2 port (3-40-2-f) 890 gal Fuel oil service tank, #2 stbd (3-40-1-f) 890 gal Fuel oil storage tank, #1 center (3-11-0- 5,040 gal xiv (Rev-0)

f) Fuel oil storage tank, #2 center (3-23-0-f)

5,350 gal

TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)

Grey water tank, (3-17-0-w) 2,668 gal.

Lube oil storage tank, (2-35-2-f) 146 gal.

Oily water tank, (3-34-1-w) 336 gal.

Sewage collection tank, (3-6-0-w) 429 gal.

Waste oil tank, (3-34-2-f) 336 gal.

1 (Rev-0)

00000_0623_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

2 (Rev-0)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.

3.1.1.3 SFLC-PBPL Availabilities (87 WPB, 110 WPB, & 154 WPC). The Contractor must conform to SFLC Std Spec 5550 with the following amendments and supplements:

For contracts executed at a Contractor’s facility, submit (pre-award) the facility’s Fire Safety Plan document described in 29 CFR 1915.502 – “Fire Safety Plan”. For planning assume that Coast Guard personnel will not be available to fight a fire.

For all contracts at all facilities, submit the following information pre-award, taking into consideration how the maintenance/repairs specified in the work items will affect uninterrupted operation of the subject systems;

make all necessary amendments to this submission after discussions with the COR at the arrival conference and during contract execution as emerging conditions warrant:

o Describe all anticipated needs for fire detection/alarm, fire-fighting, and shipboard lighting and communication systems supplementation (see below) and a description of the proposed remedies/solutions (include pricing for maintaining capability in pre-award quote).

o Describe how any required temporary/supplemental fire detection/alarm systems will notify fire responders.

o Describe all anticipated breaches of the cutter’s Fire Protection Boundaries and the proposed temporary solutions that will minimize impact on the Fire Protection Boundary’s proper function (e.g. removal of cables/hoses/etc. at the end of work day or installation of quick disconnects, installation of temporary fire curtains, etc.).

Whenever maintenance/repairs described in work items or Change Requests necessitate securing, or making inoperable, all or part of the vessel’s fire detection or fire alarm system, submit a proposal to the COR/KO describing an equivalent method(s) for temporarily maintaining all lost functionality of the system(s). Select the most economical option(s) available (i.e. for extended loss of service of the entire system the temporary fire detections/alarm system described in SFLC Std Spec 5550 may be the best option, for shorter durations temporary watch standers may be more economical, etc.). After the COR has agreed to the proposal, maintain the capability of these systems for the duration of the contract to the greatest practicable extent.

Whenever maintenance/repairs described in work items or Change Requests necessitate securing, or making inoperable, all or part of the vessel’s firefighting (e.g. fire main system, P100 and other dewatering systems, halon systems, portable fire extinguishers, etc.), lighting, and communications systems, submit a proposal to the COR/KO describing equivalent method(s) for temporarily maintaining all lost functionality of the system(s). Select the most economical option(s) available. After the COR has agreed to the proposal, maintain fire detection/alarm/fighting and lighting/communications capability for the duration of the contract to the greatest practicable extent.

3 (Rev-0)

All Fire Protection Boundaries must be left intact and functional at all times to the greatest practicable extent.

Notify the COR in writing whenever a breached Fire Protection Boundary will be left unattended outside of normal working hours (e.g. a door/hatch is made un-closable/un-securable due to repair work, an access cut is made into deck/bhd that is part of a Fire Protection Boundary, etc.). When a Fire Protection Boundary must be breached to facilitate contract work, minimize the impact using industry-standard methods (e.g. fire curtains, quick-disconnect fittings, etc.).

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must

4 (Rev-0) be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

5 (Rev-0)

Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

6 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

7 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

8 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

TIME

9 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

12 (Rev-0)

4.2 Tank and Void Assessment form.

13 (Rev-0)

14 (Rev-0)

11100_JLW_0523_154

WORK ITEM 1: Hull Plating, Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct an inspection of the hull shell plate and inaccessible voids and to perform the designated hulls scans as specified below.

TABLE 1 – ELEVATED INSPECTION SCANS

INCLUDED SCAN TYPE

YES

Conduct an automated crawler ultrasonic inspection scanning (i.e. SIDESCAN) of underwater hull plating and entire freeboard, up to the main deck edge to detect all metal corrosion and deterioration. See paragraph 3.6.1 for requirements.

NO

Conduct a 3D laser scan of the cutter’s exterior hull shell, deck and dock floor locations/deformations and provide results in 3D CAD format. See paragraph 3.6.2 for requirements

If “YES” appears in the left-column cell then the corresponding scan work is required, must be quoted on, and executed during the contract performance period. If “NO” appears in the cell then the corresponding scan work is NOT required, must NOT be quoted on, nor executed during the contract performance period.

TABLE 1A – FREEBOARD TEARDROP MODS

CSMP # DESCRIPTION

2021001 At the port and stbd teardrop areas, extend the existing stainless-steel hull insert aft using an insert of dimensions 32” x 56” x 3/16” of the in-kind stainless-steel material specified on 154 WPC 111- 301.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 085-301, Rev B, Hull Lines and Offsets

Coast Guard Drawing 154B WPC 111-301, Rev A, Shell Expansion

Coast Guard Drawing 154B WPC 161-301, Rev -, Skegs and Stern Tubes Support Structures

Coast Guard Drawing 154 WPC 997-302, Rev -, Docking Plan (Supersedes DWGS 154-WPC- 997-1, 997-301)

15 (Rev-0)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

OTHER REFERENCES

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single- Component Adhesives (An)

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

3.4 Initial inspection/test report submission.

3.1.2 Tech Rep. None.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.1.5 Refer to Coast Guard Drawings listed in Section 2 (References) for guidance.

3.2 Inspect hull shell plate. In the presence of the Coast Guard Inspector, the Contractor must visually inspect all hull freeboard and underwater body shell plate (water boundary) to identify all discrepancies (e.g. pitting, rust, significant deformation, cracks, obvious reduced shell plate thickness, etc.). If "Yes" is specified in Table 1 above for either of the elevated inspections, then perform those inspections as well.

If "No" is specified in Table 1 above, then the corresponding elevated inspection is not required.

3.3 Inspect and test inaccessible voids. In the presence of the Coast Guard Inspector, the Contractor must remove and dispose of all drain plugs for all voids and appendages listed in Table 2 below.