Attach 7 - Intrusion Detection System Vendor Checklist.doc
DOC document 81 KB Posted
- Attached to
- DHS ICE Seattle POET Alteration Federal contract opportunity
- Solicitation number
- 47PL0224Q0012
About this file
This document provides details for a solicitation seeking security system installation and maintenance services. The General Services Administration is soliciting proposals on behalf of U.S. Immigration and Customs Enforcement to procure, install, configure, program, test, document and maintain an electronic security system at the ICE Seattle Processing, Operations, Enforcement, and Training facility. Services will include a physical access control system, intrusion detection system, video surveillance system, and video intercom system. The solicitation will use lowest price technically acceptable source selection procedures. Offerors must register with the System for Award Management to access the solicitation and any amendments released through that site. Proposals are due by the date specified in the solicitation. The award will be a firm fixed price contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach 9 - EPACS Portchart Template.xlsx | XLSX spreadsheet | |
| Attach 8 - CCTV Checklist.doc | DOC document | |
| Attach 5 - Contractor Questions.xlsx | XLSX spreadsheet | |
| Attach 6 - MegaCenter Alarm Requirements MAR.docx | DOCX document | |
| Attach 4 - GSA PBS Order 3490.3.pdf | ||
| Attach 3 - SCA Wage Determination 2015-5535 Rev 21 26DEC23.pdf | ||
| 47PL0224Q0012 DHS ICE Seattle POET Alteration.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFED/FOR OFFICIAL USE ONLY (FOUO)
Intrusion Detection System Vendor Checklist
Security Vendor/installer name Survey/ Check List Inspection Date:
Contract number (if known):
Address of Site: (include floor and room number)
Site (Tenant) Representative:
OPR SMU Security System Project Manager:
GENERAL/DOCUMENTATION REQUIREMENTS
1. Has the IDS alarm system been installed to Underwriters Laboratory 2050 specifications (if specified in/ by SOW) FORMCHECKBOX
YES FORMCHECKBOX
NO
2. System design fully protects all areas identified by the SOW (if no use comments below) FORMCHECKBOX
YES FORMCHECKBOX
NO
3. Do the products used meet the system features that the customer requested by the SOW FORMCHECKBOX
YES FORMCHECKBOX
NO
4. Are drawings showing specific locations of all IDS devices placed in “as-built” notebook as required by SOW Part B FORMCHECKBOX
YES FORMCHECKBOX
NO
5. Has the accuracy/naming/location of all points and devices been verified by the installer FORMCHECKBOX
YES FORMCHECKBOX
NO
6. Is the inventory list of all installed and spare devices been placed in “as-built” book as required by SOW Part B FORMCHECKBOX
YES FORMCHECKBOX
NO
7. Has all other documentation for all security equipment installed been provided to ICE FORMCHECKBOX
YES FORMCHECKBOX
NO
8. Has training for the IDS system been identified and provided to tenant points of contact FORMCHECKBOX
YES FORMCHECKBOX
NO
mEGACENTER REQUIREMENTS
9. Does the COMMS encryption scheme meet the Mega Center requirements FORMCHECKBOX
YES FORMCHECKBOX
NO
10. Has the Mega Center Alarm Requirement (MAR) document been completed and a copy placed in “as-built” book FORMCHECKBOX
YES FORMCHECKBOX
NO
11. Has full system testing and function verifications been fully successfully performed with the Mega Center and any outstanding issues resolved FORMCHECKBOX
YES FORMCHECKBOX
NO
12. Has system communications been confirmed with the Mega Center with both IP and analog phone line FORMCHECKBOX
YES FORMCHECKBOX
NO
13. Does the Mega Center receive the point/device alarm and restore signal FORMCHECKBOX
YES FORMCHECKBOX
NO
14. Does the Mega Center receive Loss of AC, Low battery, and Loss of COMMS signals FORMCHECKBOX
INTRUSION DETECTION SYSTEM (IDS) AUXILIARY POWER
15. Is the IDS equipped with a commercial power supply indicator Light FORMCHECKBOX
YES FORMCHECKBOX
NO
16. Does the IDS equipment audibly indicate with a commercial power failure FORMCHECKBOX
YES FORMCHECKBOX
NO
17. Is the emergency power source designed to cut in and operate automatically FORMCHECKBOX
YES FORMCHECKBOX
NO
18. Have all power supplies, backup power supplies, and batteries been tested for correct voltage FORMCHECKBOX
YES FORMCHECKBOX
NO
19. Have all power supplies, backup power supplies and batteries been checked to ensure they work when isolated from commercial power FORMCHECKBOX
INTRUSION DETECTION SYSTEM (IDS)
20. Do Keypads have anti-tamper capability enabled which creates a specific auto alarm FORMCHECKBOX
YES FORMCHECKBOX
NO
21. Do detection devices have functional anti-tamper switches which creates a specific auto alarm FORMCHECKBOX
YES FORMCHECKBOX
NO
22. Do security panel enclosures have functional anti-tamper switches which creates a specific auto alarm
FORMCHECKBOX
YES FORMCHECKBOX
NO
23. Are all points and devices identified in the IDS panel programming FORMCHECKBOX
YES FORMCHECKBOX
NO
24. Installed Devices
_____# of Keypads
_____# of Zone Expanders
_____# of contacted exterior walk through doors
_____# of contacted interior doors
_____# of contacted overhead doors
_____# of interior motion detectors
_____# of glass break/shock sensors
_____# of duress devices _____# of power supplies _____# and type of other device
25. Can the IDS system provide a historical record of alarms via an automatic logging system FORMCHECKBOX
YES FORMCHECKBOX
NO
26. Are zones and points established at each keypad FORMCHECKBOX
YES FORMCHECKBOX
NO
27. Does the IDS include Normal/Disarm, Secure/Arm and maintenance modes of operation FORMCHECKBOX
YES FORMCHECKBOX
NO
28. If equipped, has the automatic alarm bypass mode been disabled FORMCHECKBOX
YES FORMCHECKBOX
NO
29. Is access to the IDS via host computer or keypads password protected FORMCHECKBOX
YES FORMCHECKBOX
NO
30. Are any motion sensors installed above drop ceilings FORMCHECKBOX
YES FORMCHECKBOX
NO
31. Are all IDS components located outside protected from the weather and tampering FORMCHECKBOX
YES FORMCHECKBOX
NO
32. Are all perimeter doors protected by a Balanced Magnetic switch (BMS) that meet UL 634 standards FORMCHECKBOX
YES FORMCHECKBOX
NO
33. If Duress switches are installed are the alarms tied to the IDS FORMCHECKBOX None FORMCHECKBOX
YES FORMCHECKBOX
NO
34. Have all doors including automatic door closers been checked to ensure IDS operation FORMCHECKBOX
YES FORMCHECKBOX
NO
35. Egress bars checked to ensure audible alarm activates when open FORMCHECKBOX
YES FORMCHECKBOX
NO
36. Have egress bars with built in delay been checked for correct operation FORMCHECKBOX