GSA_Data_Normalization_for_Building_Automation_Systems.pdf
PDF 1 MB Posted
- Attached to
- replace chiller Federal contract opportunity
- Solicitation number
- 47PJ0018Q0029
About this file
GSA Data Normalization for Building Automation Systems - reference document
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RESPONSE_TO_QUESTIONS.pdf | ||
| Amendment_0003.pdf | ||
| Solicitation_Amendment_47PJ0018Q0029_0002.pdf | ||
| PembinaChiller-amendment_0001.pdf | ||
| Object_Naming_Submittal_TEMPLATE-v1.xlsx | XLSX spreadsheet | |
| GSA_R8_Open_Protocol_Implementation_Guide_-_BACnet_-_v1_0_0_FINAL.pdf | ||
| solicitation29-Pembina_chiller.pdf | ||
| GSA_PBS_Telecommunications_Distribution_Design_Guide.pdf | ||
| Device_Schedule_TEMPLATE-v2.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Public Buildings Service Office of Facilities Management - Facility Technologies
GSA Data Normalization for Building Automation Systems
Required NCMMS asset parameters, how NCMMS interacts with Building Automation System (BAS) points, standardizing BAS point names and standardizing data tagging methods within the GSA.
DOCUMENT CHANGE LOG
Date Revision Comment By 11/27/2017 2.3 Compliance for 508 added. CPayne 10/06/2017 2.2 Added Variable Refrigerant Flow (VRF) to Appendix C CPayne 9/8/2017 2.1 Modified Appendix B per BIM Program review. CPayne 8/8/2017 2.0 Edited based on final draft review and BAS manufacturer review. Release version 2.0 created CPayne
7/25/2017 1.3 Edited based on regional Smart Building POC comments and suggestions (all regions.) Final Draft.
CPayne
7/03/2017 1.2 Post QC review modifications completed and NCMMS team review modifications completed.
CPayne
6/16/2017 1.1 Document restructuring after initial review.
New draft created with comments reset for QC review.
CPayne
6/2/2017 1.0 Draft document created for review. CPayne
TABLE OF CONTENTS
Section 1 - Introduction
Section 2 - Intended Audience & Applicability
Section 3 - Definitions
Section 4 - National BAS Object Naming Standard
Section 5 - BAS Server Level Point Requirements
Section 6 - Tagging
Section 7 - NCMMS Asset Matching
Appendices
Appendix A - Points Required at the BAS Server Level
Appendix B - NCMMS Asset “Type” Option List
Appendix C - National BAS Object Naming & Tagging Standard
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 2
SECTION 1 - INTRODUCTION
The GSA has created national programs and implemented enterprise technology to better utilize the technology and time required to manage the thousands of GSA facilities. As part of leveraging this technology, the GSA intends to standardize data for building systems by implementing a standard for BAS equipment/point naming conventions and point tagging. As regional buildings are connected at the national level for systems such as NCMMS-Maximo and GSAlink, normalizing provides a smoother and faster path to integration when programmers know what to expect when connecting to various Building Automation Systems.
This document is designed to establish standardized requirements related to BAS point naming, implement Haystack tagging requirements, and clarify the necessary fields in the National CMMS Maximo system for matching assets to Building Automation System (BAS) equipment, across the GSA portfolio.
In the following sections, this document will guide you through the requirements for BAS point naming, outline the requirement for data tagging by standardizing on the Project Haystack open source data initiative and cover the proper procedure when configuring NCMMS Asset naming.
SECTION 2 - INTENDED AUDIENCE & APPLICABILITY
1. GSA AND O&M PERSONNEL shall use this document to correctly configure the National
CMMS assets (Section 7) so that all BAS related assets match the equipment as named in the BAS. This document can also be utilized to better understand the BAS naming convention and the Haystack tagging requirements.
2. BMC SYSTEM CONTRACTORS shall utilize this document to configure all building systems with the perspective of the GSA’s overall portfolio. All new installation and *renovated systems shall be configured with the naming and tagging conventions as described within this document to provide consistency throughout all of the GSA. All BMC system-related documentation and submittal packages shall reflect these naming and tagging conventions. A point summary table shall be created by the BAS contractor and kept current throughout the duration of the project as the master list of all I/O points. A minimum BAS server-level point list is provided within this document to accurately engineer, specify, and quote BAS projects. Project closeout documents shall include an up-to-date and accurate “Point Summary Table”, along with relevant commissioning documentation related to point tagging checkout. For each project, the contractor shall submit the documentation for approval prior to final acceptance of the system. The point summary table shall be used as a reference and guide throughout the commissioning process.
*Renovated systems applies to major upgrades which replace existing programming along with equipment and system renovations. The standard as described within this document does not require partial renovations to modify existing programming and point names that don’t fall under the scope of work or may negatively impact other existing programming.
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 3
SECTION 3 - DEFINITIONS
1. Point – Points are typically a software level variable representing a digital or analog sensor or actuator type object or entity (sometimes called hard points). Points can also represent a configuration or programmed value such as a setpoint or schedule log (sometimes called soft points). Typically, the attributes of a point constitute a point object.
2. Tag – A tag is a name/value pair applied to an object or entity within the Building Automation System and is further defined by referencing Project Haystack. A tag defines a fact or attribute about an object or entity and can also be known as “metadata.”
3. NCMMS – The GSA’s National Computerized Maintenance Management System. The National CMMS is a central repository (database) for all maintainable GSA assets that runs on the Maximo software platform. The NCMMS provides a mandatory, agency-wide means and method for processing and reporting all maintenance work and repairs done for PBS regardless of region or contractor.
4. NCMMS Asset – NCMMS assets are used to store asset numbers and corresponding information, such as parent, location, vendor, status, description, and maintenance costs for each asset in the Maximo system. You can build the asset hierarchy as an arrangement of buildings, departments, assets, and subassemblies.
http://project-haystack.org/
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 4
SECTION 4 - NATIONAL BAS OBJECT NAMING STANDARD
As stated in the introduction, implementing a standard for BAS equipment and point naming provides added value to the GSA. As regional buildings are connected at the national level for systems such as NCMMS-GSAlink and SkySpark, normalizing offers a smoother and faster path to integration, as programmers know what to expect when connecting to various BAS.
As times and technology have progressed, there are now different methods utilized to normalize data. One method is to standardize BAS object and point naming conventions. The second method covered in this document will be described in “Section 6 –Tagging”. There is a great deal of value in normalizing regional/building server BAS names, building names, global controller names, floor IDs, equipment abbreviations and point names. Having a unified hierarchy across the GSA portfolio will make national level implementations less complex and less costly overall.
This GSA Smart Building Technology Device & Object Naming Standard is intended to standardize the names and tagging of BAS, Lighting, Metering, and other devices and control objects. Note: It is understood that certain BAS manufacturers will have different requirements and limitations regarding acceptable character types and overall character length limitations. It is also understood that certain manufacturers allow for more generalized “tree” structuring of objects which means aspects like equipment name and building do not necessarily have to be included in the point name due to parent/child folder structuring.
The provided documentation and diagrams in Appendix-C are intended to give the project engineer and technician the ability to find the appropriate names and tags for each object based on GSA requirements. The diagrams show generic HVAC, lighting, metering, and other equipment containing control points and objects, some of which may or may not be present in a particular application.
All device tagging and object naming shall be submitted to the GSA Regional Office of Facility Management (OFM) or the Facilities Management Division (FMD) for review and approval prior to implementation – any system objects implemented prior to OFM/FMD approval shall be corrected by the vendor at no additional cost to GSA.
Any control object, tag or point that is not represented in this document must be submitted to the OFM/FMD via RFI. A response will be generated identifying the name that should be used for the application. If the supplied name is not currently represented in the standard document, it may be added.
Note: It is understood that the object names for some products cannot be modified (i.e. “canned application” or “pre-configured” controllers.) These devices/object names shall be submitted with an indication that the controller cannot be customized.
1. Process
This Object Naming Standard shall be implemented according to the following process:
a. Engineer automation system to understand what objects are required.
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 5
b. Using the National BAS Object Naming & Tagging Standard document (APPENDIX-C), identify and document the standardized names and tags for the control objects and devices.
c. Submit the proposed names to the OFM/FMD.
d. Receive comments back, correct errors, and resubmit. Repeat process until all issues are resolved.
e. Object naming is approved by OFM/FMD.
f. Implement names and tags into the BAS database and programming.
Failure to follow and complete these steps in order may result in substantial re-work by and at the expense of the BAS contractor.
2. Scope
This Object Naming Standard covers all BACnet-discoverable devices and objects which includes:
a. AI, AO, AV, BI, BO, BV, MO, & MV point types
b. Calendar objects (Cldr)
c. Schedule objects (Sched)
d. Trend Log objects (Td)
e. Event Enrollment objects (Evt)
f. Notification Class objects (Not)
g. File objects (File)
h. Command objects (Cmd)
i. Devices
This Standard also covers all points, registers, etc. (objects) that are mapped using a driver, integration device, or system (such as Niagara Framework), and any additional objects created in the integration device or system. For example, registers mapped from a third-party Modbus device to a BAS controller or integration device using a driver must be named using this Standard.
3. Understanding the Standard
To properly implement this Object Naming Standard, it is important to understand the intended goal, the desired outcome, the design philosophy of the naming system and the methodology used to meet those goals.
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 6
GOAL:
Ensure that the way the BAS devices and objects are named, enables any user of the system or system data to instantly identify the device or object and understand the function of system objects, whether they are sensors, actuators, schedules, trend logs, etc. A user can be a human operator, but it can also be a computer that stores or processes information from the system.
PHILOSOPHY:
To allow a human to instantly identify a device or object simply by reading the name. At minimum, the name must indicate which building, what equipment/system to which it is associated, the type of object, and the object’s primary function. The parts of the name must be human-readable using standardized abbreviations. These standardizations allow an operator or analyst to read, search, sort, group, and filter objects with ease.
A computer interpreter of any type would be able to use the building and equipment/system indications to group objects. To make the function of an object clear to a machine, the object type/function portion of the name is composed of standardized “camel-cased” abbreviations that a computer can break apart and use to automatically apply metadata tags. These tags allow applications, such as analytics engines or CMMS, to interpret information directly from the BAS or from a trend archive and create actionable responses and outputs.
METHODOLOGY:
To create names that are both human-readable and machine-readable, the structure and abbreviations of the names are standardized. Each name has three parts separated by underscores: Building Number, Equipment Designator, and Object Name. (See the “Object Name Anatomy” section below for technical details on structure standardization.)
Building Numbers are provided by GSA in accordance with a pre-existing numbering system. The “Equipment Designator” is a free-form field; the mechanical drawings equipment schedule can be used as a guide. The “Object Name” is a camel-cased, standardized name for the object.
4. Object Unit Descriptions
Object units are suggested in parentheses, such as: (°F)
For analog points, the engineering units are provided. Engineering units are standardized, and the OFM/FMD should be consulted where the standard units are inappropriate for the measurement or application.
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 7
Generally, analog outputs are expressed in percent (%, or pct). For valves and dampers, %open/%closed is used. 0% open would indicate that the control object is closed. 100% open would indicate that the control object is open. For mixing dampers, diverting valves, face/bypass dampers, etc., see unit indications where objects are found in diagrams in this document.
Binary outputs are generally expressed with (Off/On). Other binary units are provided depending on the application. The order of the state text labels is determined by the default position of the device. For example, a damper that is normally closed would use the units (Closed/Open), whereas a damper that is normally open would use (Open/Closed).
5. Object Name Anatomy
Underscore Delimiter
Building_Equipment_Object
IMPORTANT
NEVER EXCEED 45 CHARCTERS
Building Number
Equipment/ Location Designation
Standard Object Name
Up to 6 characters as-needed
16-31 characters as-needed
Number of characters available depends on BAS product limitations. At the beginning of a project, the BAS limitation should be considered to ensure that names can be accommodated within the characters available. Some adjustments may be required.
Always 6 characters, always designated by
GSA
No formal standard – best practice is to use the equipment designations used in the building’s mechanical drawings
Always use standardized names found in this document.
SS####_EEEEEE_PPPPPPPPPPPPPPPPPPPPPPPPPPPPPPP
CO0624_A01_SATmpSp
CO0624 is DFC Building 810
Air Handling Unit 1
Supply Air Temperature Set Point
Example
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 8
6. Typical Conventions (Suffixes with Examples)
Ena Usually applied to BV objects. An “Ena” point indicates that conditions have been met to allow a device to be commanded, but is not the actual command.
• CHWSysEna
• HHWSysEna
• BlrEna
• EconEna
Cmd Usually applied to BO and AO objects, and sometimes BV and AV objects also. A “Cmd” point commands something – starts a motor, modulates a valve, etc.
• SFCmd
• ChlrCmd
• MADmprCmd
• BlrCmd
• CCVlvCmd
• CTDivVlvCmd
Sts Usually applied to BI objects. Corresponds to the “Cmd” point. This is the actual status of the commanded equipment.
• SFSts
• ChlrSts
• SFVFDSts
• CHWPmpSts
Pos Applied to AI objects, “Pos” is feedback from a device such as a valve or a VFD.
Corresponds to command (Cmd) in the case of a valve or damper, or speed (Spd) in the case of a VFD.
• CCVlvPos
• CTFPos
• MADmprPos
• SashPos
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 9
Sp Applied to AV objects, “Sp” is shorthand for Setpoint. Used to indicate the setpoint that corresponds to a control variable.
• SATmpSp
• CHWSTmpSp
• SAStPrsSp
• HWSFlwRatSp
• CHWSysOATmpEnaSp
Alm Usually applied to BI or BV objects (but not limited to). Alarm (Alm) should only be used on objects that have a corresponding event notification.
• BlrAlm
• MATmpAlm
• LowTempAlm
• DAStPrsAlm
• FireAlm
• ServiceAlm
Td Applied to the end of an object name to indicate that it is the trend object associated with the control point object.
• SATmpTd
• SFStsTd
• CCVlvCmdTd
• MATmpSpTd
Sched Applied to schedule objects.
• AHU01_Sched
• IceSys_Sched
• CHW_Sched
• EF01_Sched
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 10
SECTION 5 - BAS SERVER LEVEL POINT REQUIREMENTS
To effectively and efficiently integrate GSA buildings at a national level (GSAlink), there is a requirement to have certain data points available over the network from the BAS supervisor/server. These data points or histories should be made available via an open protocol as described below.
The GSA has a standard requirement that states, all high-level network-based control applications like scheduling, overrides, etc. shall exist at the global network controller level within the building. In the event of a network outage, the O&M still retains the ability to directly connect to the controllers and make necessary modifications while the server is unavailable (disaster recovery procedure). Though the control level aspects of the programming shall reside in the global network controllers, the long-term trends will be maintained at the server level and the I/O points shall be mapped to the server for display on the Graphical User Interface (GUI) and made available via an open protocol for national level integrations.
This can be accomplished in many ways and will differ depending on the BAS manufacturer utilized for the project. The goal is to have relevant, national-level historical trend data accessible utilizing a 1:1 connection from the national server (i.e. GSAlink, SkySpark, etc.) to the BAS server. For example:
1. NiagaraAX and Niagara4 (i.e. Vykon, Honeywell, Johnson FX, etc.) based systems shall have the required data points for operations and maintenance imported to the Niagara Supervisor so these points/historical trends can be accessed by national-level systems with a 1:1 connection to the server.
2. All other Building Automation Systems shall conform to a similar practice of providing open source access to point or historical data at the BAS-server level by either enabling the BACnet Server feature of the software application (if available) or exporting historical point data to a GSA-provided SQL Database.
Utilize the table found in “Appendix A - Points Required at the BAS Server Level” to determine and configure the necessary server-level historical trend data. Note: If the entire point or historical database is made available as described above by exporting over BACnet or exporting to an SQL database, there is no need to use the table to select points since all points will be accessible to the national-level system/s.
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 11
SECTION 6 - TAGGING
Discussed within this section and further detailed in Appendix-C, are the requirements for “tagging” BAS objects with the correct metadata when configuring systems for the GSA.
Equipment and point naming was covered previously within this document, but as mentioned, the key to normalizing BAS data and providing the greatest impact is to properly tag objects with “facts” or “attributes” that give the data better meaning, thus providing more ways to analyze, prioritize and act upon the collected data.
The standard tagging model for the GSA will be modeled after Project Haystack. The tagging requirements described in Appendix-C are modeled after the Haystack documentation which can be found here.
Note: If the Building Automation System has the capability to implement tagging, the standards detailed in “Appendix C – National BAS Object Naming & Tagging Standard” shall be used for all new construction and renovation projects within the GSA.
Why Haystack?
As tagging is adopted and implemented by more BAS manufacturers, there is no guarantee that all manufacturers will adopt the Haystack tagging method as their base tagging model. Even so, Haystack has developed a very robust list of available tags along with the ability to create custom libraries and those tags should be available or creatable using any manufacturer tagging process in the future.
For example, the BACnet committee is currently working on a tagging scheme that supports multiple namespaces such as Haystack and any other tagging schemes that may come along in the future. Similarly, ASHRAE is also pursuing a published list of tags for Standard 223 in conjunction with the BACnet committee’s efforts. Both efforts are in the early stages of design but both seek alignment with Haystack wherever possible.
What is Haystack?
Project Haystack is an open source initiative to streamline working with data from the Internet of Things. We standardize semantic data models and web services with the goal of making it easier to unlock value from the vast quantity of data generated by the smart devices that permeate our homes, buildings, factories, and cities. Applications include automation, control, energy, HVAC, lighting, and other environmental systems.
Why Do We Need Tagging?
Macro trends in technology are making it increasingly cost effective to instrument and collect data about the operations and energy usage of buildings. We are now awash in data and the http://project-haystack.org/doc/Intro
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 12 new problem is how to make sense of it. Today most operational data has poor semantic modeling and requires a manual, labor-intensive process to "map" the data before value creation can begin. Pragmatic use of naming conventions and taxonomies can make it more cost effective to analyze, visualize, and derive value from our operational data.
Vendor Specific Haystack/tagging Information
• Niagara AX/N4 (applies to any Niagara-based OEM controller).
o Niagara AX and N4 can easily support Haystack tagging.
o The tag dictionary from the “NHAYSTACK” module shall be used as the primary resource for all tagging. The module can be downloaded here.
o When a tag or relationship type is required that does not currently exist in the
NHAYSTACK library, a new tag dictionary shall be created by the contractor and named using the unique GSA building ID (i.e. NY0282).
• Honeywell EBI o Today, EBI does not have a tagging database to associate tags to objects in the database. This is currently being reviewed for inclusion in future updates of EBI.
• Schneider Electric o Schneider IA Series (AX and N4) adhere to the same Haystack tagging methods described above in the Niagara AX/N4 section.
o SmartStruxure support and standards to be determined.
• Siemens o The current Siemens Insight and Desigo CC versions do not include any standards or guidelines for the usage of Haystack but these standards are currently in development for future releases of the software.
o Siemens does support Haystack tagging through compatibility with the Niagara Framework.
• Alerton o Alerton is currently in the process of adding tagging capability in Compass. Once tagging support is added, Haystack will be supported by the Alerton Standard Applications.
o Alerton dealers will also be allowed to configure custom applications related to tagging.
• Automated Logic o Currently, Automated Logic does not support tagging, but development plans include support for the BACnet Standard tagging scheme with semantic tagging that was recently adopted by the BACnet committee in 2017 (SSPC 135) and referenced above in the “Why Haystack” section.
http://project-haystack.org/download
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 13
SECTION 7 - NCMMS ASSET MATCHING
The National CMMS naming convention is not configured in a fashion that completely aligns with typical BAS naming conventions. The way NCMMS defines an Air Handling Unit (AHU), for example, is not by AHU name (i.e. “AHU-01-LBY”), but rather by AHU “Type” (size in tonnage).
A separate field is utilized to associate the NCMMS Asset with the BAS equipment name.
Appendix C lists and defines all the available Asset options within NCMMS. To properly configure an NCMMS Asset, one would need to know some specific details about the equipment like, but not limited to:
• Equipment name as described in the Building Automation System
• AHU size (Tonnage)
• Chiller type (Absorption, Centrifugal, Screw, etc.)
• Chiller size (Tonnage)
• Boiler type (Gas, Oil, Electric, etc.)
• Boiler size (MBH)
• Use the table in Appendix C to determine the necessary assets for a given project
Among the many parameters within NCMMS that are required for proper asset management, there are two (2) parameters that require proper configuration to ensure asset matching and correct labeling within the system when associating NCMMS records with BAS labels.
• The first is the “Type” record. As discussed above and displayed in Appendix-B, the “Type” field is used to describe the type of equipment and sizing parameters. This field is not used to display the equipment name as shown in the BAS. The user cannot enter any value into this field, but must use the pre-defined values shown in the equipment list.
This list can be viewed by clicking the Search button (magnifying glass) next to the field.
• The second is the “Asset Tag” record. This field is utilized for the equipment description as shown in the BAS. For example, a site may have several “AHU-01” Types (because the building has several AHUs sized 3 to 24 tons), but it will only have one “AHU-01- LBY” Asset Tag for the associated asset. This field is a large format alpha-numeric data field which means it allows both letters and numbers and will allow plenty of characters for proper description. The BAS equipment description as shown on the graphic pages should be entered in this field. Section 4 and Appendix-C describes the required naming convention and abbreviations for GSA equipment and point names.
A list of available “Type” records and the corresponding equipment description can be found in Appendix B - NCMMS Asset “Type” Option List. NCMMS manages more than just BAS assets, so there are many “Types” that will not be utilized when matching assets to BAS equipment.
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 14
APPENDICES
APPENDIX A - POINTS REQUIRED AT THE BAS SERVER LEVEL
The purpose of the required BAS Server Level Points is not to require additional equipment or sensors, but rather indicate the points that should be considered as value added monitoring points and be included in the Building Control System design. These points should be made accessible to third party systems over Open Protocol data sources (i.e. BACnet, SQL, etc.).
It should be stressed that the purpose of this point list is to influence system design and not to restrict the use or availability of control or monitoring points that exist in a system. As with all big data applications, the more data made available the greater value add to the analyses being performed. This list should be utilized to verify that the largest pool of data is available for fault detection and diagnostics.
The point list table below shows the points currently utilized in the GSAlink rules (highlighted) as well as an additional set of control points that have proven to bring value in fault detection and diagnostics.
# Equipment Description Point Type
Required If
Available Preferred
AHU
1 AHU Cold Deck Supply Temp Physical Yes Yes
2 AHU Cold Deck Fan Status Physical Yes Yes
3 AHU Hot Deck Supply Temp Physical Yes Yes
4 AHU Hot Deck Fan Status Physical Yes Yes
5 Building Air Pressure Physical Yes
6 Building Air Pressure Setpoint Virtual Yes
7 Bypass Damper Status Physical Yes Yes
8 Chilled Water Pump Physical Yes Yes
9 Chiller Plant Mode Virtual Yes Yes
10 Cooling Lockout OA Temp Virtual Yes
11 Cooling Max Airflow Virtual Yes
12 Cooling Min Airflow Virtual Yes
13 Cooling Mode Virtual Yes Yes
14 Cooling Valve Position Physical Yes
15 Cooling Valve Status Physical Yes Yes
16 Dehumidification Mode Virtual Yes Yes
17 Dehumidification Setpoint Virtual Yes
18 Dewpoint Setpoint Virtual Yes
19 Supply Fan Status Physical Yes Yes
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 15
20 Supply Temp Physical Yes Yes
21 Supply Temp Setpoint Virtual Yes Yes
22 Duct Static Pressure Physical Yes
23 Duct Static Pressure Setpoint Virtual Yes
24 Economizer Enabled Command Virtual Yes
25 Economizer Enthalpy Disable Setpoint Virtual Yes
26 Economizer Mode Virtual Yes Yes
27 Economizer Temp Disable Setpoint Virtual Yes
28 Economizer Temp Enable Setpoint Virtual Yes
29 Exhaust Air Damper Position Physical Yes
30 Free Cooling Temp Setpoint Virtual Yes
31 Global OA Temp Physical Yes
32 Heat Exchanger Valves Physical Yes Yes
33 Heating Lockout OA Temp Virtual Yes
34 Heating Max Airflow Virtual Yes
35 Heating Mode Virtual Yes Yes
36 Heating Valve Status Physical Yes Yes
37 Hot Water Pump Command Physical Yes Yes
38 Hot Water Pump Status Virtual Yes Yes
39 Min Outside Air Damper Setpoint Virtual Yes
40 Min Outside Air Ratio Virtual Yes
41 Mixed Air Temp Physical Yes Yes
42 Mixed Air Temp Setpoint Virtual Yes
43 Outside Air Airflow Sensor Physical Yes Yes
44 Outside Air Damper Status Physical Yes Yes
45 Outside Air Airflow Setpoint Virtual Yes Yes
46 Outside Air Temp Physical Yes Yes
47 Occupancy Mode Virtual Yes Yes
48 Outside Air Damper Position/ Feedback Physical Yes
49 Outside Air Enthalpy Virtual Yes
50 Outside Air Damper Position Physical Yes
51 Return Air Damper Position Physical Yes
52 Return Air Fan Status Physical Yes
53 Return Air Temp Physical Yes Yes
54 Static Pressure Sensor Physical Yes Yes
55 Two Positon Outside Air Damper Command Physical Yes
56 Two Position Outside Air Damper Status Physical Yes
57 Zone Air Dewpoint Temp Virtual Yes
58 Zone Air RH Physical Yes
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 16
59 Zone Air Temp Physical Yes
60 Zone Air Temp Setpoint Virtual Yes
61 Zone Damper Position Physical Yes Yes
62 Zone Damper Temp Physical Yes Yes
63 Zone Supply Temp Physical Yes Yes
Chiller 64 Chilled Water Delta-T Virtual Yes
65 Chilled Water Return Temp Physical Yes Yes
66 Chilled Water Supply Temp Physical Yes Yes
67 Chiller Enabled Virtual Yes
68 Chiller Operation Mode Virtual Yes
69 Chiller Status Physical Yes Yes
70 Chilled Water Diff Press Setpoint Virtual Yes Yes
71 Chilled Water Differential Pressure Physical Yes Yes
72 Chilled Water Pump Status Physical Yes Yes
73 Chilled Water Supply Setpoint Virtual Yes Yes
74 Compressor Refrigerant Supply Pressure Physical Yes
75 Compressor Refrigerant Supply Temp Physical Yes
76 Compressor Run Load Physical Yes
77 Compressor Start Virtual Yes
78 Compressor Voltage Physical Yes
79 Condenser Pump Command Virtual Yes
80 Condenser Refrigerant Pressure Physical Yes
81 Condenser Refrigerant Temp Physical Yes
82 Condenser Water Approach Temp Physical Yes
83 Condenser Water Delta-T Virtual Yes
84 Condenser Water Return Temp Physical Yes
85 Condenser Water Supply Temp Physical Yes
86 Cooling Mode Virtual Yes Yes
87 Current Draw Physical Yes
88 Evaporator Approach Temp Virtual Yes
89 Evaporator Refrigerant Pressure Physical Yes
90 Evaporator Refrigerant Temp Physical Yes
91 Evaporator Water Return Temp Physical Yes
92 Evaporator Water Supply Temp Physical Yes
93 Expansion Valve Position Physical Yes
94 Heat Sink Temp Physical Yes
95 Lagging Chiller Enabled Virtual Yes
96 Lagging Chiller Enabled Setpoint Virtual Yes
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 17
97 Lead Chiller Enabled Virtual Yes
98 Lead Chiller Enabled Setpoint Virtual Yes
99 Lead Chiller Selection Virtual Yes
100 Occupancy Mode Virtual Yes Yes
101 Primary Pump Command Physical Yes
102 Secondary Pump Command Physical Yes
Cooling Tower 103 System Bypass Valve Physical Yes
104 Condenser Water Supply Temp Setpoint Virtual Yes
105 Condenser Water Return Temp Setpoint Virtual Yes
106 Condenser Water Supply Diff Press Setpoint Virtual Yes
107 Condenser Water Return Diff Press Setpoint Virtual Yes
108 Chiller Plant Enabled Virtual Yes
109 Condenser Pump Command Physical Yes
110 Condenser Pump Status Physical Yes Yes
111 Cooling Tower Fan Enabled Virtual Yes
112 Cooling Tower Fan Feedback Physical Yes
113 Cooling Tower Return Temp Physical Yes Yes
114 Cooling Tower Sump Temp Physical Yes
115 Cooling Tower Supply Setpoint Virtual Yes Yes
116 Cooling Tower Supply Temp Physical Yes Yes
117 Cooling Tower Water Level Physical Yes
118 Induction Loop Return Temp Physical Yes
119 Induction Loop Supply Temp Physical Yes
Terminal Units 120 Average Space Temp Virtual Yes
121 Chilled Water Temp Physical Yes
122 Circulating Fan Command Physical Yes
123 Cooling Lockout Outside Air Temp Virtual Yes
124 Cooling Max Airflow Virtual Yes
125 Cooling Min Airflow Virtual Yes
126 Cooling Mode Virtual Yes Yes
127 Cooling Temp Setpoint Virtual Yes Yes
128 Cooling Valve Position Physical Yes
129 Dewpoint Setpoint Virtual Yes
130 Supply Fan Status Physical Yes Yes
131 Fan Coil Enabled Virtual Yes
132 Fan Speed Physical Yes
133 Heating Lockout OA Temp Virtual Yes
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 18
134 Heating Max Airflow Virtual Yes
135 Heating Mode Virtual Yes Yes
136 Heating Stage Command(s) Virtual Yes
137 Heating Temp Setpoint Virtual Yes Yes
138 Electric Heating Coil Command Physical Yes
139 Hot Water Valve Position Physical Yes
140 Minimum Air Temp Virtual Yes
141 Occupancy Mode Virtual Yes Yes
142 Return Air Temp Physical Yes
143 Room Temp Physical Yes
144 Room Temp Setpoint Virtual Yes
145 Supply Air Damper Position Physical Yes
146 Supply Airflow Limit Virtual Yes
147 Supply Air Temp Physical Yes
148 Supply Airflow Physical Yes
149 Supply Airflow Setpoint Virtual Yes
150 Ventilation Demand Virtual Yes
151 Zone Occupancy Status Virtual Yes
152 Zone Temp Physical Yes Yes
153 Zone Temp Setpoint Virtual Yes Yes
Boilers / Heat Exchangers 154 Boiler Supply Temp Physical Yes Yes
155 Boiler Runtime Virtual Yes
156 Boiler Start/Stop Command Virtual Yes
157 Boiler Status Physical Yes Yes
158 Boiler Entering Temperature Physical Yes
159 Boiler Valve Command Physical Yes
160 Boiler Valve Status Physical Yes
161 HW Diff Press Setpoint Virtual Yes Yes
162 HW Pressure Differential Physical Yes Yes
163 HW Pump Status Physical Yes Yes
164 HX Return Temp Physical Yes
165 HX Supply Temp Physical Yes Yes
166 HX Mode Virtual Yes Yes
167 HX Pump Status Physical Yes Yes
168 HX Temp Setpoint Virtual Yes Yes
169 HX Valve Status Physical Yes Yes
170 Pump Override Virtual Yes
171 Pump Failure Virtual Yes
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 19
172 Pump Runtime Virtual Yes
173 Pump Start/Stop Command Physical Yes
174 Secondary Hot Water Return Temp Physical Yes
175 Secondary Hot Water Supply Temp Physical Yes
176 Secondary HW Pump Physical Yes Yes
177 Zone Occupancy Status Virtual Yes
Roof Top Units 178 Cooling Lockout Outside Air Temp Virtual Yes
179 Cooling Max Airflow Virtual Yes
180 Cooling Min Airflow Virtual Yes
181 Cooling Temp Setpoint Virtual Yes
182 Cooling Stage Command Virtual Yes
183 Dewpoint Setpoint Virtual Yes
184 Economizer Mode Enabled Virtual Yes
185 Economizer Enthalpy Disable Setpoint Virtual Yes
186 Economizer Temp Disable Setpoint Virtual Yes
187 Economizer Temp Enable Setpoint Virtual Yes
188 Energy Wheel Leaving Air Temp Physical Yes
189 Exhaust Fan Command Virtual Yes
190 Free Cooling Temp Setpoint Virtual Yes
191 Heating Lockout OA Temp Virtual Yes
192 Heating Max Airflow Virtual Yes
193 Heating Setpoint Virtual Yes
194 Heating Stage Command(s) Virtual Yes
195 Min Outside Air Damper Setpoint Virtual Yes
196 Min Outside Air Ratio Virtual Yes
197 Modulating Outside Air Damper Physical Yes
198 Outside Air Dewpoint Virtual Yes
199 Outside Air Enthalpy Virtual Yes
200 Outside Air Relative Humidity Physical Yes
201 Outside Air Temp Physical Yes
202 Return Air Temp Physical Yes
203 Supply Air Fan Command Virtual Yes
204 Supply Air Temp Physical Yes
205 Two Position Outside Air Damper Physical Yes
206 Unit Humidification Setpoint Virtual Yes
207 Unit Dehumidification Setpoint Virtual Yes
208 Zone Air Dewpoint Temp Virtual Yes
209 Zone Air Relative Humidity Physical Yes
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 20
210 Zone Air Temp Physical Yes
CRAC Units 211 Cooling Coil Valve Position Physical Yes
212 Cooling Lockout OA Temp Virtual Yes
213 Cooling Max Airflow Virtual Yes
214 Cooling Min Airflow Virtual Yes
215 Dewpoint Setpoint Virtual Yes
216 Heating Lockout OA Temp Virtual Yes
217 Heating Stage Command(s) Virtual Yes
218 Humidification Enabled Virtual Yes
219 Minimum Outside Air Ratio Virtual Yes
220 Relative Humidity Setpoint Virtual Yes
221 Return Air Humidity Physical Yes
222 Return Air Temp Physical Yes
223 Return Air Temp Setpoint Virtual Yes
224 Supply Air Fan Command Virtual Yes
225 Supply Air Temp Physical Yes
226 Unit Cooling Status Virtual Yes
227 Unit Dehumidification Mode Virtual Yes
228 Unit Heating Status Virtual Yes
229 Unit Humidification Mode Virtual Yes
230 Unit Status Virtual Yes
Energy Meters 231 Energy Meter Reading Physical Yes Yes
232 Peak Energy Demand Physical Yes Yes
233 Occupancy Mode Virtual Yes
This Section Intentionally Left Blank
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 21
APPENDIX B - NCMMS ASSET “TYPE” OPTION LIST
# Type Description 1 ABL Air Blower 2 ACC Condenser, Air-Cooled 3 ACR-01 Computer Room Air-Conditioning Unit, Package: or Special Systems 4 ACR-02 Heat Pumps, Water Cooled (WSHP) 5 ACR-03 Air Conditioning Unit or Heat Pump Split System, 6 ACR-04 Air Conditioning Unit, Ceiling/Wall/Window Mounted 7 ACR-05 Air-Cooled Condenser 8 ACR-06 Evaporative Condenser 9 ACT Air Curtain 10 ACU Air Conditioner Package 11 ACW Air Conditioner, Window 12 ADO Audio System 13 ADR Air Dryer 14 AER Aerator 15 AGS-01 Tanks, Air, Refrigerant, LP Gas 16 AHU-01 Air Handling Unit, 3 ton thru 24 ton 17 AHU-02 Air Handling Unit, 25 ton thru 50 ton 18 AHU-03 Air Handling Unit, over 50 ton 19 AHU-04 Air Handling Unit, Computer Room 20 AHU-05 Packaged Air Handler, Predictive Maintenance 21 AHU-06 Air Washer or Wet Coil System 22 AHU-07 Application 23 AHU-08 AHU UV Treatment System 24 AIR-01 Air Dryer, Refrigerated or Regenerative Desiccant Type 25 AIR-02 Air Compressor 26 AIR-03 Glycol Dry Cooler, Special Purpose 27 AIR-04 After-Cooler/Separator 28 ALM Fire Detection and Alarm System 29 ALM-01 Alarm Check Valves and Accessories 30 ALM-02 Fire Supervisory Signals - Testing 31 ALM-03 Automatic Fire Detection Smoke Detectors 32 ALM-04 Automatic Fire Detection Water flow Alarms 33 ALM-05 Automatic Fire Detection, Heat Detectors 34 ALM-06 Smoke Control Systems -Operational Testing 35 ALM-07 Fire Alarm Control Panel and Remote Annunciators 36 ALM-08 Fire Alarm Control Panel -Special Systems 37 ALM-09 Central Station Transmitter 38 ALM-10 Central Station - Receiver and Re-Transmission Equipment 39 ALM-11 Fire Alarm System - Recorder 40 ALM-12 Fire Alarm System - Event Printer 41 ALM-13 Fire Alarm System -Audio Control Panel 42 ALM-14 Fire Alarm System -Remote Controller 43 ALM-15 Fire Alarm System -Remote Amplifiers 44 ALM-16 Manual Fire Alarm Stations -Coded and Uncoded 45 ALM-17 Fire Life Safety Fire Alarm 46 APL Appliance - Washer Dryer Etc.
47 ART Artwork Sculptures Etc.
48 ASP Air Separator 49 ATP Automatic Trap Primer 50 ATS Switch, Automatic Transfer 51 ATS-01 Automatic Transfer Switches 52 AWS Air Washer
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 22
53 BAR-01 Security Bollards, Barricade 54 BAS-01 Building Automation System, DDC 55 BAS-02 Building Automation System, Pneumatic 56 BAS-03 Building Automation System, Terminal End Devices 57 BAT Battery 58 BDT-01 Metal Enclosed Busways (Busduct) 59 BFP Backflow Prevention Device 60 BLR-01 Boiler 61 BLR-02 Boiler, Application 62 BLR-03 Boiler, Burner, Gas 63 BLR-04 Boiler, Burner, Oil 64 BLR-05 Boiler, Instrument Controls 65 BLR-E Boiler, Electric 66 BLR-HW1 Boiler, Hot Water, Oil/Gas/Comb, up to 120 MBH 67 BLR-HW2 Boiler, Hot Water, Oil/Gas/Comb, 120 to 500 MBH 68 BLR-HW3 Boiler, Hot Water, Oil/Gas/Comb, 500 to 1000 MBH 69 BLR-HW4 Boiler, Hot Water, Oil/Gas/Comb, over 1000 MBH 70 BLR-MOD1 Modular Boiler, 42 MBH 71 BLR-MOD2 Modular Boiler, 57 MBH 72 BLR-MOD3 Modular Boiler, 85 MBH 73 BLR-MOD4 Modular Boiler, 112 MBH 74 BLR-MOD5 Modular Boiler, 140 MBH 75 BLR-MOD6 Modular Boiler, 167 MBH 76 BLR-MOD7 Modular Boiler, 194 MBH 77 BLR-ST1 Boiler, Steam, Oil/Gas/Comb, up to 120 MBH 78 BLR-ST2 Boiler, Steam, Natural Gas, or Oil/Gas/Comb 79 BLR-ST3 Boiler, Steam, Oil/Gas/Comb, 500 to 1000 MBH 80 BLR-ST4 Boiler, Steam, Oil/Gas/Comb, over 1000 MBH 81 BNG Burner, Gas Oil 82 BSB Heater, Baseboard 83 BSB-01 Radiant Baseboards, Convectors (Steam, Hot Water, or Electric, per section) 84 BSD Electric Buss Duct 85 BTC Battery Charger 86 BUF Floor Buffer 87 BWS Bird Wire System 88 CAO Can Opener 89 CAP-01 Capacitors 90 CAP-02 Reactors-Dry-Type, Thermographic Survey 91 CAP-03 Reactors, Liquid-Filled, Oil Leakage 92 CBL-01 Cables, Low Voltage 600 Volt Maximum, Thermographic Survey 93 CBL-02 Cables, Medium Voltage 94 CBS-01 Active Chilled Beam 95 CBS-02 Passive Chilled Beam 96 CDE Clothes Dryer, Electric 97 CHF Chemical Feeder 98 CHL-A1 Chiller, Absorption unit, up to 500 tons 99 CHL-A2 Chiller, Absorption unit, 500 to 5000 tons
100 CHL-CW1 Chiller, Centrifugal, water cooled, up to 100 tons 101 CHL-CW2 Chiller, Centrifugal, water cooled, over 100 tons 102 CHL-MB1 Magnetic Bearing Chiller, Less 500 Tons 103 CHL-MB2 Magnetic Bearing Chiller, 500-1000 Tons 104 CHL-MB3 Magnetic Bearing Chiller, over 1000 Tons 105 CHL-MOD1 Modular Chiller, 20-Ton 106 CHL-MOD2 Modular Chiller, 25-Ton 107 CHL-MOD3 Modular Chiller, 30-Ton 108 CHL-MOD4 Modular Chiller, 35-Ton
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 23
109 CHL-MOD5 Modular Chiller, 40-Ton 110 CHL-MOD6 Modular Chiller, 45-Ton 111 CHL-MOD7 Modular Chiller, 50-Ton 112 CHL-RA1 Chiller, Recip, Air Cooled, up to 25 tons 113 CHL-RA2 Chiller, Recip, Air Cooled, over 25 tons 114 CHL-S1 Chiller, Screw, Water Cooled 115 CHL-S2 Chiller, Screw, Water Cooled 116 CHL-W1 Chiller, Recip, Water Cooled, up to 50 tons 117 CHL-W2 Chiller, Recip, Water Cooled, over 50 tons 118 CHM-01 Chemical Storage Tanks 119 CKB-01 Circuit Breakers, Air, Insulated-Case, Molded-Case 120 CKB-02 Circuit Breakers, Air, Low-Voltage Power 121 CKB-03 Circuit Breakers, Air, Medium Voltage 122 CKB-04 Circuit Breakers, Oil, Medium-Voltage 123 CKB-05 Circuit Breakers, Vacuum, Medium-Voltage 124 CLK Clocks 125 CLK-01 Clocks, Central System 126 CLR-01 Central Chilled Water Package Unit:
127 CLR-02 Rotary Screw & Scroll Chiller 128 CLR-03 Centrifugal Chiller 129 CLR-04 Refrigeration Machine, Absorption Unit 130 CLR-05 Chiller Control Panel 131 CLR-06 Refrigerant Monitor 132 CLR-07 Refrigerant Purge Units 133 CLR-08 Vibration Analysis, Chillers 134 CLR-09 Non-Destructive Tube Analysis (Eddy Current Analysis) 135 CLS-01 Coils Cooling, Heating, Preheat, Reheat, Etc.
136 CMD Carbon-Monoxide Detection Sensors 137 CMI Carbon Dioxide (CO2) Concentration Measuring Instrument 138 CMP Air Compressor 139 CMP-R Air Compressor, Recip 140 CND-01 Condensing Unit, Refrigeration 141 COF Coffee Maker/Urn 142 COL Coil, Heating/Cooling 143 CON Control Panel 144 CPZ Cathodic Protection Zinc 145 CRAC Computer Room A.C.1 (CRAC Unit) 146 CRN-01 Crane, Electric 147 CTR Cooling Tower 148 CUT Cutter, Food 149 CVC Video Control System 150 CWD Clothes Washer, Domestic 151 DAV Davits/Roof Anchors/Fall Protection 152 DAV-01 Davits 153 DCS-01 DC Battery System, Lead Acid 154 DCS-02 Primary Battery (Dry Cell) 155 DCS-03 Nickel Cadmium Battery 156 DCS-04 DC Battery System, Chargers 157 DCT Switch, Disconnect 158 DDC-01 BAS Server 159 DDC-02 BAS Server Client Workstation 160 DDC-03 Network, Management Level 161 DDC-04 Network, Building Level 162 DDC-05 Field Panel 163 DDC-06 Controller 164 DDC-07 Sensors, Electronic
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 24
165 DDC-08 Alarm Maintenance 166 DDC-09 BAS Wireless Electronic, Pneumatic end devices (Thermostats) 167 DEA Deaerator Tank 168 DES De-aerating System 169 DET Detector, Leak 170 DFB Defibrillator 171 DFF Fryer, Pressurized Broaster, Gas/Electric 172 DFS Diffuser-Linear and Lay in 173 DKL Dock Leveler 174 DMP-01 Motorized Dampers, Pneumatic or Electric 175 DMW-01 Dumbwaiter 176 DOR Exterior Doors 177 DOR-01 Door, Power Operated 178 DOR-02 Door; Hydraulic, Electric or Pneumatic Operated 179 DOR-03 Door, Manual, Overhead 180 DOR-04 Door, Manually Operated Entrance 181 DPP Damper, Powered 182 DPS Differential Pressure Switch 183 DRD Drink Dispenser 184 DRN Drain 185 DRN-01 Roof Drains, Downspout, and Gutter Inspection 186 DRN-02 Drains: Areaway, Driveway, Storm 187 DSE Duplex Sewage Ejector 188 DSH-01 Dishwashing Machine 189 DSH-1 Dishwasher - Elect 190 DSH-2 Dishwasher - Steam 191 DSH-3 Dish/Tray Busing Conveyor 192 DTT Transformer, Dry 193 DWS-01 Domestic Hot Water Heater - Gas 194 DWS-02 Domestic Hot Water Heater - Electric 195 DWS-03 Hot Water Heater Steam Coil 196 DWS-04 Water Softener 197 DWS-05 Water Filter 198 DWV-01 Sewage Ejector (Pneumatic Tank Type Ejectors) 199 DWV-02 Sewage Ejector, Sump Type 200 DWV-03 Sump Pump 201 DWV-04 Emergency Wash 202 DWV-05 Emergency Shower 203 DWV-06 Septic Tank and Drain Field 204 EFP Flagpole, Electric 205 EHC Exhaust Hood, Commercial Kitchen 206 EHF Exhaust Hood, Fume 207 ELT Emergency Lighting 208 ELV-01 Elevators, Hydraulic 209 ELV-02 Elevators, Electric 210 ELV-03 Elevators, Electric or Hydraulic 211 ELV-1 Hydraulic Elevator 212 ELV-2 Electric Traction Elevator 213 EMG-01 Emergency Diesel Generator 214 EMG-02 Emergency Natural Gas Generator 215 EMS Energy Management System 216 END-01 End Devices 217 EPB Panelboard, Power Distribution 218 EPR-01 Emergency Generators, Gasoline, or Natural Gas Engines 219 EPR-02 Electric Emergency Generators, Diesel Engine Powered 220 EPR-03 Emergency Generators
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 25
221 EPR-04 Emergency Pumps and Ventilators 222 EPR-05 Fuel Oil Filter/Strainer 223 EPR-06 Fuel Oil Heater 224 EPR-07 Emergency Generator Steam Turbine Driven 225 EPR-08 Load Bank Testing 226 EQP-01 Child Care Equipment 227 ESC Escalator 228 ESC-01 Escalator 229 EVP Evaporative Cooler 230 EVP-01 Indirect Evaporative Cooling System 231 EVP-02 Direct Evaporative Cooling System 232 EVP-03 Humidification Systems 233 EWC Drinking Fountain, Packaged 234 EXJ Expansion Joint 235 EXS Exit Signs 236 EXT Expansion Tank 237 EYE Eyewash/Shower Unit 238 FACILITIES Facilities Assets 239 FAF Furnace, Forced Air, Natural Gas 240 FAN-01 Fan, Axial 241 FAN-02 Fan, Centrifugal 242 FAN-03 Fan, Make-up 243 FAN-04 Fan, Utility Set 244 FCP Food Cart, Process 245 FCU Fan Coil Unit 246 FCU-01 Fan Coil Unit 247 FDR-01 Fire Door - Swinging 248 FDR-02 Fire Door - Sliding & Rolling 249 FEX Fire Extinguishers 250 FEX-01 Fire Extinguishers - Inspection 251 FEX-02 Fire Extinguishers, Stored Pressure with Gauge 252 FEX-03 Fire Extinguishers - Non-rechargeable 253 FEX-04 Fire Extinguishers, Gas Cartridge, or Cylinder (No Gauge) 254 FEX-05 Water Spray Extinguishing Systems 255 FEX-06 Fire Extinguishing Systems - Inspection, Carbon Dioxide (High Pressure)
256 FHC Cabinet, Fire Hose 257 FLEET Fleet Assets 258 FLF Filter, Fuel/Oil 259 FLT Filter, Air 260 FLT-01 Filters, Throw Away 261 FLT-02 Filters, Roll, Disposable 262 FLT-03 Filters, Electrostatic 263 FLT-04 Filters, Viscous Type (Wire Mesh) 264 FLT-05 Filters, Charcoal 265 FLT-06 Filters, Special situations, or conditions.
266 FLT-1 Filter, OR 267 FLT-2 Filter, Sand 268 FLT-3 Filter, Water 269 FMT Flow Meter 270 FNG Fences and Gates 271 FOL-01 Tanks, Fuel Oil Storage 272 FPL Fireplace 273 FPL-01 Fireplace 274 FPL-02 Incinerator 275 FPM-01 Fire Pump, Electric-Drive 276 FPM-02 Fire Pump, Diesel
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 26
277 FRG Refrigerator unit/display case w/external condenser 278 FRY-01 Fryer 279 FRZ Refrigerator/Freezer, walk-in box w/external condenser 280 FSD Fire and Smoke Dampers 281 FSD-01 Fire and Smoke Dampers 282 FSP-01 Wet-Pipe Sprinkler Systems 283 FSP-02 Dry-Pipe Sprinkler Systems 284 FSP-03 Pre-action Sprinkler Systems 285 FSP-04 Clean-Agent Fire-Extinguishing Systems 286 FUR Furniture 287 GAG Gauge 288 GBG Garbage Disposal 289 GDS Fuel-Gas Detection Sensors 290 GET Grounds Equipment, Lawn Tractor, Carts 291 GFS Glycol Feed System 292 GND Bench Grinder 293 GRD-01 Grounding Systems 294 GRL Grill 295 GRL-01 Grill 296 GRR Gear Reduction Unit 297 GTP Grease Trap 298 GWS-01 Geothermal Well System, Vertical 299 GWS-02 Geothermal Well System, Horizontal 300 HCU Heating/Cooling Unit 301 HDY Hand/Hair Dryer 302 HPU High Efficiency Purge Unit 303 HSE Fire Hose/Hose Connections 304 HSE-01 Fire Hose, 1.5 inch. Racked in Buildings 305 HSE-02 Fire Department Hose Connections - Standpipe Outlets 306 HSE-03 Fire Department Pumper Connections - Standpipe or Sprinkler 307 HST Hoist 308 HST-01 Chain Hoist and Trolley 309 HST-02 Hoist, Electric 310 HST-03 Hoist, Lighting 311 HTP-1 Heat Pump, Air Cooled 312 HTP-2 Heat Pump, Water Cooled 313 HUM Humidifier, Evaporative Pan w/ Heating Coil 314 HVU Heating & Ventilating Units 315 HWC Hot Water Converter 316 HWS-01 Hot Water Converter Steam 317 HWS-02 Solar Heating System 318 HXR-01 Heat Exchanger, Flat Plate 319 HXR-02 Heat Exchanger, Tube (Shell and Tube) 320 HYD Fire Hydrant 321 HYD-01 Fire Hydrant Flow Test-Dry Barrel and Wet Barrel 322 ICD Ice Cream Dispenser 323 ICE Ice Machine 324 ICE-02 Ice Maker 325 ICM-01 Ice Cream maker and Shake Maker 326 IEX Intercom Exchange Unit 327 INC Incinerator 328 IRG Irrigation System 329 IT IT Assets 330 ITR-01 Instrument Transformers 331 KCS Keycard System/Access Control 332 KTL Kettle, Steam
GSA Data Normalization for Building Automation Systems_v2.3.docx Page 27
333 KTL-01 Kettle 334 LCP Lighting Control Panel 335 LFT Lift, Scissor/Fork 336 LFT-01 Lift, Electric, Stage Screen 337 LFT-02 Material Handling Equipment, Electric Lift Trucks 338 LFT-03 Loading Ramp, Adjustable 339 LFT-04 Lift, Automobile 340 LFV Lift, Vehicle 341 LGD Lighting, Dimmer Control 342…