This solicitation notice is for a contract to modernize passenger and freight elevators at the Charles E. Chamberlain Federal Building in Lansing, Michigan. The General Services Administration seeks to replace elevator equipment and controls, install new elevator cabs and finishes, and perform other upgrades to improve performance, accessibility, and safety. The project budget is between $1,000,000 to $5,000,000 and work must be completed within 245 calendar days of the notice to proceed. The solicitation is set aside for small businesses only and proposals will be evaluated on both price and non-price factors with technical factors being more important than price. Interested small businesses should submit proposals by April 20, 2020 electronically to the contracting officer. The NAICS code for this opportunity is 238290 with a $16.5 million size standard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Clarification Questions and Answers.pdf | ||
| Amendment 0004 Elevator Modernization Lansing MI.pdf | ||
| Virtual Site Visit.mov | MOV file | |
| Amendment 0003 Elevator Modernization Lansing MI.pdf | ||
| Virtual Site Visit 2.mov | MOV file | |
| Pre-Proposal Conference Attendance Sheet.pdf | ||
| Amendment 0002 Elevator Modernization Lansing MI .pdf | ||
| Amendment 0001 Elevator Modernization Lansing MI.pdf | ||
| Amendment 0001 Elevator Modernization Lansing MI.pdf | ||
| Cost Breakdown.xlsx | XLSX spreadsheet | |
| Lansing Elev 4 100 drawings - Option Work.pdf | ||
| Lansing Elev 3 100 drawings - Base Contract.pdf | ||
| RFP Passenger and Freight Elevator Modernization.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agenda
SOLICITATION #47PF0020R0025
Pre-Proposal Conference Passenger and Freight Elevator Modernization
Charles E Chamberlain U.S. Courthouse April 8, 2020
Government Team:
Contracting Officer: Della Ljungkull, della.ljungkull@gsa.gov Contract Specialist: Tim Novak, timothy.novak@gsa.gov Contracting Officer’s Representative: Thomas Monaweck, thomas.monawekc@gsa.gov Property Manager: Jordan Dykstra, jordan.dykstra@gsa.gov Architect/Engineer: GH Forbes Associates - Scott Goodsell
QUESTIONS:
All questions shall be submitted in writing to Tim Novak at timothy.novak@gsa.gov with carbon copy to Della Ljungkull at della.Ljungkull@gsa.gov and Tom Monaweck at Thomas.monaweck@gsa.gov. The question submission period is extended from April 5, 2020 to no later than Friday, April 10, 2020 at 12:00 P.M. CST.
SAM
All contractors must be active in the System for Award Management (SAM), www.sam.gov, prior to submission of offers to be considered for award. BE ADVISED: If you are registering a new entity in SAM.gov or updating your entity, you must provide and mail an original, signed notarized letter (available here: https://goo.gl/DxrEBs ) stating that you are the authorized Entity Administrator. Read the FAQs (available here: https://goo.gl/jfW8q3 )for more information on these requirements and / or contact the Federal Service Desk at www.fsd.gov for additional questions or assistance.
CONTRACTUAL ITEMS
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
No oral statement made by a Government representative during the pre proposal conference, nor any written record of such oral statements as may be made and subsequently furnished to the offeror, will be deemed to have the effect of adding to, modifying, or otherwise varying from the written provisions of the Solicitation (including, but not limited to specifications, drawings and written amendments to the solicitation). In the event the discussion or questions raised during the pre proposal conference indicate a need to modify the Solicitation, an amendment to the Solicitation will be issued in writing; any such amendment to the Solicitation must be mailto:Della.ljungkull@gsa.gov mailto:timothy.novak@gsa.gov mailto:thomas.monawekc@gsa.gov mailto:jordan.dykstra@gsa.gov mailto:timothy.novak@gsa.gov mailto:Della.Ljungkull@gsa.gov mailto:Thomas.monaweck@gsa.gov
Pre-Proposal Conference Passenger and Freight Elevator Modernization acknowledged in the same manner and under the same conditions as all other written amendments to the Solicitation.
RECEIPT OF OFFERS
In order to be considered for award, offers conforming to the requirements of the Solicitation must be received no later than 11:00 AM Central on the following date and at the following email addresses:
Date: April 20, 2020 11:00 AM Central Submit electronically to: Della.Ljungkull@gsa.gov and Timothy.Novak@gsa.gov
II.A. Proposal Contents
Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
1. Price Proposal
2. Technical Proposal
3. Representations and Certifications
4. Standard Form 24, Bid Bond
5. GSA Form 527 – Contractor’s Qualification and Financial Information
6. Past Performance & Past Experience Reference Attachment A.2
7. Past Performance & Past Experience Reference Attachment B (submitted by references to Contracting Officer)
II.B. Proposal Format
Please include one (1) copy of your proposal containing the forms and information as requested in part II.C. Price Proposal and II.D. Technical Proposal.
Offerors are to submit an email with the subject line: “PROPOSAL Lansing Elevator”
Electronic Packages will contain pdf files as described below:
1. Attachment Labeled “(Contractor Name) Price Proposal Lansing Elevator”:
A: Standard Form 1442
2. Attachment Labeled “(Contractor Name) Technical Proposal Lansing Elevator”
Pre-Proposal Conference Passenger and Freight Elevator Modernization
3. Other information to submit with proposals shall be submitted as individual pdfs and labeled as follows:
A: Attachment Labeled “(Contractor Name) Attachment A.2 B: Attachment Labeled “(Contractor Name) Attachment B C: Attachment Labeled “(Contractor Name) SF 24 Bid Guarantee D: Attachment Labeled “(Contractor Name) GSA Form 527 E: Attachment Labeled “(Contractor Name) Reps and Certs
Proposals will only be accepted in electronic format, via email. No disc or faxed proposals will be accepted
Offerors that need to submit multiple emails due to file size limitations shall name their electronic submissions as follows:
“PROPOSAL Lansing Elevator Email 1 of X”, etc.
Offerors shall note that in the case of multiple submissions, all emails shall be received by the Contracting Officer and Contract Specialist prior to the closing date and time of this solicitation in order for the submission to be considered timely.
II.C. Price Proposal
(1) Contents
The Price Proposal shall consist of the SF 1442 and Cost Breakdown, with prices and/or rates indicated for each price element shown on the cost breakdown form included in RFP. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) Additional Proposal Requirements
NA
Pre-Proposal Conference Passenger and Freight Elevator Modernization
II.D. Technical Proposal
Technical Proposals will be evaluated on the criteria described below. Each factor will be scored as follows:
EVALUATION FACTOR POINTS
POSSIBLE
POINTS
AWARDED WEIGHT WEIGHTED
SCORE
1. Past Experience
0-5 x
5.0
2. Project Management Plan
0-5 x 5.0 =
3. Past Performance 0-5 x
5.0
TOTAL SCORE (Max 75 Points)
Factor 1: Past Experience
This factor considers the extent of the Offeror’s past experience as a firm providing comparable construction services. The Offeror shall submit information on at least three (3), but no more than five (5), comparable projects that have been substantially completed by the contractor in the last five (5) years from issuance of the RFP.
Comparable construction services are defined by the following characteristics:
● The project involved construction and/or modernization of an elevator
● The project was performed in an occupied and functioning Government or
Commercial office building
● Total project construction cost at award exceeded $1,000,000
● Services were provided in a historic building.
● Services were in a building that required coordination with security personnel for security and access.
Projects over $1,000,000 will be given preference over projects submitted below $1,000,000. A contractor may submit examples between $500,000 and $1,000,000 but the Government will only evaluate if they do not have the minimum number over that Amount.
For each project presented in relation to this factor, the Offeror must explain how the
Pre-Proposal Conference Passenger and Freight Elevator Modernization characteristics of the project relate to the characteristics of this project. The comparability to this project is more important than the quantity of projects presented.
For each project presented the Offeror shall submit form A.2 as a part of their proposal package. Offeror will provide attachment B to their references who will complete the form and provide directly to the GSA by the closing date and time of the
RFP:
Standard for Evaluation:
1. At least (3) project examples have been submitted that meet the definition of comparable; and
2. All three (3) projects have received a rating of satisfactory or better from all references and the references indicate they would contract with the firm again
Scoring Guidelines
RATING DESCRIPTION
The proposal identifies at least three (3) comparable projects with adequate details that demonstrate significant, relevant experience
The proposal identifies at least three (3) comparable projects with details that demonstrate fairly relevant experience.
The proposal identifies at least three (3) comparable projects with sufficient details that demonstrate somewhat relevant experience.
The proposal identifies less than three (3) comparable projects. Limited details are provided that demonstrate little relevant experience.
The proposal identifies less than three (3) comparable projects. Few details are provided that demonstrate no relevant experience.
0 No project examples are identified in the proposal.
Factor 2: Project Management Plan
This factor considers the Offeror’s project management plan which indicates the processes that will be used to maximize the opportunity for successful completion of this requirement, within budget, and meeting quality expectations in accordance with the design specification for each elevator. The Project Management Plan will be evaluated
Pre-Proposal Conference Passenger and Freight Elevator Modernization as an indicator of the Offeror’s understanding of the requirements of this contract. The plan should identify and elaborate on significant project components such as safety, quality control, subcontractor identification and management, property manager and/or tenant coordination, system coordination, coordination with other ongoing projects, etc.
and should demonstrate the Offeror’s knowledge, programs and processes. This factor will be evaluated based on the Offeror’s written response; the written response shall not exceed three (3) double-sided pages.
Standard for Evaluation:
1. The project management plan describes the offeror’s approach for for the modernization of each elevator. The plan includes, but may not be limited to, scheduling and cost control methods, change order management, subcontractor identification and management, and goals for meeting or exceeding performance criteria.
2. As a part of the plan, offeror’s identify and propose a way to manage the most significant risks that may be associated with this project. Such risks may include matters that jeopardize performance within budget and schedule limitations, subcontractor performance, building occupancy, and/or site access.
RATING DESCRIPTION
5 The proposed project management plan is exceptionally clear and project specific, demonstrating a complete understanding of the contract requirements.
4 The proposed project management plan is clear and somewhat project specific, demonstrating a clear understanding of contract requirements.
3 The proposed project management plan is for the most part clear and demonstrates a general understanding of the contract requirements.
2 The proposed project management plan is very general and does not demonstrate a clear understanding of the contract requirements.
1 The proposed project management plan is vague and not at all project specific, demonstrating a lack of understanding of the contract requirements.
0 No project management plan is identified in the proposal.
Factor 3 Past Performance
Pre-Proposal Conference Passenger and Freight Elevator Modernization
This factor considers the Offeror’s Past Performance for the projects submitted under Evaluation Factor Number 1; past performance can be described as how an Offeror performed on a job. This factor will be evaluated based upon the responses from the references provided and any other sources that the Government may solicit to find references for other relevant, comparable work performed by the Offeror and may include institutional knowledge or other sources.
This factor considers the past performance of the Offeror and proposed subcontractors for key trades. The Offeror shall submit a minimum of three (3) and no more than five (5) references for comparable projects substantially completed in the last five (5) years.
References must be submitted for the projects presented in relation to Factor 1:
Experience. References must complete Attachment B: Past Performance Questionnaire and submit them directly to the Contracting Officer prior to the closing date and time of the subject RFP.
If the Contracting Officer becomes aware of required past performance information omitted from the Offeror’s proposal, the Contracting Officer may draw a negative inference from the omission of such information.
The quality of the Offeror’s past performance in carrying out the work of a comparable nature with reference to such aspects as quality of services rendered, control of exigencies (changes and claims), budget control, timeliness, business integrity and technical success are part of the consideration. The effectiveness of the Offeror’s management of the administration aspects of performance, their willingness to cooperate with or assist with routine matters and unexpected difficulties will also be evaluated. In accordance with FAR 15.306, the Offeror will be given the opportunity to respond to adverse past performance information.
The standard is met when:
1. The Government received three (3) past performance questionnaires for projects submitted under Evaluation Factor Number 3 Past Performance.
2. Services were completed in a Government or Commercial Office Building.
3. Services were provided in a historic building.
4. Services were in a building that required coordination with security personnel for security and access.
Scoring Guidelines
Past Performance Reference B Form provides the reference an opportunity to rate the
Pre-Proposal Conference Passenger and Freight Elevator Modernization offeror. The score provided will be the score given to the offeror.
FAR 15.305(a)(2)(iv) states, "In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available, the Offeror may not be evaluated favorably or unfavorably on past performance." Therefore, failure of the Offeror to provide a minimum of three relevant references under Factor 1, and/or the inability of the Government to complete a minimum of three reference checks after making a reasonable effort to do so, may result in the Offeror not being rated on the past performance factor. The Government is not required to conduct or complete reference checks on more than the three required references
Technical Information
1. Existing elevator (3 & 4) general info. (type, age, condition)
2. Watch and talk through videos of both elevator work areas. Talk through AE still photos to get an idea of working conditions.
3. What the existing elevators will be replaced with
4. Overview of the scope of work for the project, have drawings and specs ready for viewing if needed.
5. Any abnormal conditions to bring contractors attention to.
6. Working and operating conditions of the Courthouse itself. Business Hours, Building
Access, Storage, Parking, Loading Dock, etc
7. GSA security clearance process overview
8. RFI’s and answers to date