41019_Special_Provisions_20260824_r1.pdf

PDF 452 KB Posted

Attached to
Kiefer Landfill Basin Discharge Piping
Solicitation number
41019
Issued by
Sacramento County, San Francisco City, California

About this file

This is a set of contract specifications for the County of Sacramento Department of Waste Management and Recycling for the Basin Discharge Piping project at Kiefer Landfill located at 12701 Kiefer Boulevard, Sloughhouse, California. The project involves furnishing all labor, materials, equipment, and incidentals necessary for the installation of approximately 1,150 feet of new HDPE piping to replace deteriorating 6-inch HDPE outlet pipe that currently transports treated water from the Groundwater Treatment Plant to infiltration basins. The scope of work includes installation of approximately 8-inch HDPE SDR 17 pipe and 6-inch HDPE SDR 17 pipe, connection to existing 12-inch PVC piping at South Deer Creek, installation of a new 2-inch air relief valve at Station 7+08, installation of 10-inch corrugated metal pipe culverts at two road crossing locations, excavation and trenching with backfill and compaction, repair of the access road, and demolition of the existing 6-inch HDPE piping. The contract completion time is 45 working days from the notice to proceed. A pre-bid conference will be held as noted in the Notice to Contractors. The project manager is Derek Cho, P.E., reachable at (916) 876-1083.

Payment for work items will be made on either a unit price (lineal foot), lump sum, or allowance basis, with payment made only after each portion of the project is completed. The bid includes eight items: mobilization and demobilization on a lump sum basis; layout of work and as-built drawings on a lump sum basis; furnish and install buried 12-inch Schedule 40 PVC pipe connection on a lump sum basis; furnish and install 8-inch HDPE SDR 17 pipe on a per lineal foot basis; furnish and install 6-inch HDPE SDR 17 pipe on a lump sum basis; furnish and install 2-inch air relief valve on a lump sum basis; excavate, trench, backfill, selective demolition and repair access road on a lump sum basis; and furnish and install 10-inch corrugated metal pipe at two crossings on a lump sum basis. Liquidated damages are assessed at $500 per calendar day for delays beyond the established contract completion date. The County of Sacramento Standard Construction Specifications (revised November 2024) are incorporated by reference and modified by these project specifications. All project plans and specifications can be downloaded from https://secure.procurenow.com.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Basin Discharge Piping Kiefer Landfill

COUNTY OF SACRAMENTO

Department of Waste Management and Recycling

CONTRACT SPECIFICATIONS

FOR

KIEFER LANDFILL BASIN DISCHARGE PIPING

12701 KIEFER BLVD, SLOUGHHOUSE CA 95683

CONTRACT NO. 41019

AUGUST 2026

PROJECT MANAGER

Derek Cho, P.E.

County of Sacramento

Department of Waste Management and Recycling

(916) 876-1083 choy@saccounty.gov

NOTE: The County of Sacramento Standard Construction Specifications, revised

November 2024, are hereby made a part of these Specifications. A copy of the Standard Construction Specifications may be downloaded from the County website at https://development.saccounty.gov/us/en/construction-management-inspection/standard-construction-specifications.html

Jennifer Claiborne, DIRECTOR

DEPARTMENT OF WASTE MANAGEMENT AND RECYCLING

KIEFER LANDFILL BASIN DISCHARGE PIPING

CONTRACT NO. 41019

TABLE OF CONTENTS FOR CONTRACT DOCUMENTS

DIVISION 1 – GENERAL REQUIREMENTS

MODIFICATIONS TO STANDARD CONSTRUCTION SPECIFICATIONS

3-2 Consideration of Bids 4-1 Intent of Contract Documents 4-1.02 Work and Limitations 4-2 Plans and Specifications Furnished 5-8.01 Submittals – General 5-9.01 Agency-Furnished Surveys 6-11 Existing Utilities 6-11.06 Utility Shutdowns and Connections 7-8.01 Allowable Times and Hours of Work 7-9 Temporary Facilities 7-9.02 Construction Site Utilities 7-10 Protection of Work, Persons and Property 8-10 Liquidated Damages 10-9 Sanitary Regulations

TECHNICAL SPECIFICATIONS

SECTION

011100 012000 013300 015700 028000 017400 022100 033000 312300 312333

DESCRIPTION

Special Provisions Measurement and Payment Submittals Temporary Controls Pressure Pipe Testing Construction Cleaning Layout of Work and Surveys Concrete Site Earthwork Trenching

334101 400500 400513 400524 400531 400578

HDPE pipe, fittings, and valves Piping Systems Piping Connection Steel Pipe Plastic Pipe Air Release and Vacuum Valves

DIVISION 1 - GENERAL REQUIREMENTS

All portions of the County of Sacramento Standard Construction Specifications dated November 2024 are hereby made part of these specifications. Modifications to the Standard Construction Specifications are noted below. The Standard Construction Specifications along with these project specifications shall be considered as one body of specifications.

MODIFICATIONS TO STANDARD CONSTRUCTION SPECIFICATIONS

3-2 CONSIDERATION OF BIDS

Sentence three of paragraph two shall be deleted and replaced with the following:

If the bid is missing a lump sum price or a unit price, in either the base bid or any alternate, then the bid will be deemed incomplete and the bid will be rejected as non-responsive.

4-1 INTENT OF CONTRACT DOCUMENTS

Add the following paragraphs to this section:

The project specifications use the Construction Specifications Institute (CSI) format. The CSI format divisions shall not operate to make the County an arbiter to establish subcontract limits between Contractor and/or subcontractors. The General Contractor is responsible to the County for all phases of construction and a complete job.

The existing conditions depicted on the drawings and specifications are developed from record information. Exact locations, distances, dimensions, elevations, etc., shall be governed by actual field conditions and verified by the Contractor.

4-1.02 WORK AND LIMITATIONS

1. During the progress of work, the existing facilities shall be maintained without interruption, except by specific arrangement with the Project Inspector and then only at such times as approved in writing by the Project Inspector.

2. The Contractor shall coordinate the work of this contract through the Project Inspector assigned by the Engineer.

4-2 PLANS AND SPECIFICATIONS FURNISHED

The first paragraph shall be deleted and replaced with the following:

The Agency will provide the fully executed Contract for the Contractor’s use in prosecuting the Work. The Agency will not provide copies of Project Plans, Standard Drawings or State Plans, Project Specifications, Standard Construction Specifications or the State Specifications, and Special Provisions. Project Plans and Project Specifications can be downloaded from https://secure.procurenow.com

5-8.01 SUBMITTALS – GENERAL

Sentence one of paragraph five shall be replaced by the following:

Copies of all submittals shall be furnished electronically, an electronic copy will be returned after review.

5-9.01 AGENCY-FURNISHED SURVEYS

The entire section shall be deleted and replaced with the following:

The contractor shall be responsible for and shall perform all surveys and measurements necessary for layout and control of work in accordance with Section 5-9.03 of the Standard Construction Specifications.

6-11 EXISTING UTILITIES

6-11.06 UTILITY SHUTDOWNS and CONNECTIONS

The Project Inspector shall be notified two (2) working days in advance of any contemplated shutdown of electricity or other utility. The Project Inspector’s approval shall be obtained prior to any shutdown activity.

The Contractor shall schedule and coordinate all connections and other work to be performed by public and private utility organizations necessary for the completion of the project.

7-8.01 ALLOWABLE TIMES AND HOURS OF WORK

Add the following:

No deviations will be allowed without the written approval of the Engineer.

7-9 TEMPORARY FACILITIES

The Contractor shall obtain the prior approval of the Project Inspector for acceptable site access or before using any area or space for Contractor’s storage during construction operations. Materials, equipment, etc., shall not be piled or stored in any location which shall interfere with the conduct of normal functions of the building and/or facilities, and shall not constitute a hazard to persons or property. Any required safety precautions such as signs, danger signals, lanterns, barricades, etc., shall be provided by and installed by the Contractor during construction operations.

No advertising signs of any kind will be permitted except by written permission of the Engineer.

7-9.02 CONSTRUCTION SITE UTILITIES

WATER: KIEFER LANDFILL - Contractor may connect a temporary line to the existing fire hydrant at the site nearby for construction water supply for this project only. The contractor may not interfere with Kiefer Landfill operations when accessing water. The Contractor shall be responsible to verify all existing conditions associated with a water connection. Water used in construction must comply with Section 16 of the Standard Construction Specifications.

Contractor shall provide potable drinking water for their own use.

ELECTRICAL POWER: Contractor shall provide and maintain, during the course and progress of the work, all electrical power and wiring requirements to facilitate the work of all trades and services associated with the work. Generator(s) may be used onsite but must be fueled and serviced by the Contractor. No temporary electrical lines are available on site.

TELEPHONE: Contractor shall not have access to phones on site and therefore, shall arrange for their mobile phone if needed for on-site communication.

7-10 PROTECTION OF WORK, PERSONS AND PROPERTY

Provide temporary fencing, lock boxes etc., as required to protect material storage, equipment and building under construction from theft, vandalism and unauthorized entry.

The Contractor shall be responsible for all damage in the area of Work, or any other area in the building or on the site, caused by Contractor, his employees or subcontractors.

8-10 LIQUIDATED DAMAGES

Liquidated damages shall be $500.00 for each calendar day(s) delay beyond the established contract completion date that all work, is not completed.

10-9 SANITARY REGULATIONS

Add the following paragraph to this section:

The Contractor shall furnish, install, and remove at completion of the job, all sanitary (portable toilet) facilities required during project construction. Facilities shall be provided in sufficient quantities to comply with CAL-OSHA regulations. All such sanitary facilities shall be made available for use by all workers, subcontractors, consultants, and County personnel associated with the project. The type and location of the facilities shall be subject to acceptance by the Project Inspector. The Contractor shall maintain sanitary facilities in a proper, safe, operating, and sanitary condition for the duration of the work. Contractor’s employees shall not use existing facilities at the site.

END OF SECTION

DEPARTMENT OF WASTE MANAGEMENT AND RECYCLING

DIVISION 1 - GENERAL REQUIREMENTS

SECTION 011100 - SPECIAL PROVISIONS

1.01 BACKGROUND

Sacramento County Department of Waste Management & Recycling’s (DWMR) Kiefer Landfill Groundwater Treatment Plant (KTP), located across Kiefer Blvd from the landfill, includes numerous extraction and monitoring wells. Current system utilizes a 6” HDPE outlet pipe to transport treated water to the infiltration basins. The 6” HDPE is deteriorating and therefore will need to be replaced.

1.02 PROJECT LOCATION

12701 Kiefer Boulevard Sloughhouse, CA 95683

Access to the North work area is via the main Kiefer Landfill entrance on Kiefer Blvd, or via gate at 13153 Kiefer Blvd.

Access to the south work area via 13228 Kiefer Blvd, Sloughouse, CA - contractor, subcontractor, vendors, and/or suppliers will need to keep this gate closed except when entering and exiting the site.

1.03 SCOPE OF WORK

As detailed on the Construction Drawings:

1. Scope included approximately 1150 feet of new HDPE piping to be connected to existing

12” PVC piping at South Deer Creek. Most of the pipes will be placed above ground;

Provide new air relief valve at approximately 7+08. Provide new culvert pipes to protect HDPE piping at two road crossing locations. Repair access road after installation of piping.

1.04 TIME OF COMPLETION

The time of completion of all work described in this contract shall be 45 working days commencing as specified in Section 7-1, “Beginning of Work,” of the Standard Construction

1.05 PRE-BID CONFERENCE

A pre-bid conference will be held as noted in the NOTICE TO CONTRACTORS.

1.06 MANUFACTURER’S SPECIFICATIONS AND INSTRUCTIONS

A. Any deviation from the Manufacturer's printed recommendations shall be explained and acknowledged as correct for the circumstances, in writing, by the particular Manufacturer. The Contractor will be held responsible for all installations not conforming to the Manufacturer's recommendations. If any item of material or equipment is found to be installed not consistent with the Manufacturer's recommendations, the Contractor shall make all changes necessary to achieve such compliance.

B. Contractor shall secure all field measurements required for proper and accurate fabrication and installation of the work included in this Contract. Exact measurements are the Contractor's responsibility. The Contractor shall also furnish or obtain all templates, patterns, and setting instructions required for the installation of all work. All dimensions shall be verified by the Contractor in the field.

1.07 CONTRACTOR'S FIELD OFFICE

A space for a Contractor field office shall be made available.

1.08 ENGINEER'S FIELD OFFICE

An engineer’s field office is not required.

1.09 SPECIAL SECURITY REQUIREMENTS

The Contractor's workers and equipment shall be limited to the work areas as designated by this contract.

1.10 SCHEDULE OF WORK AND LIMITATIONS

A. Operations

During the progress of work, site operations shall be maintained without interruption, except by specific arrangement with the County and then only at such times as approved in writing by the Engineer. The Contractor will be required to maintain access to the operating portion of the site at all normal times of business. The Contractor will be required to provide alternate routes of access if construction activities interfere with the flow of traffic along the site's main access road.

B. Coordination of Contract Work

The Contractor shall coordinate the work of this contract through the Engineer. Progress meetings will be conducted weekly in accordance with the County of Sacramento Standard

Construction Specifications, Section 7-3 Preconstruction Conference and Progress Meeting.

The contractor shall submit a construction schedule and progress schedule in accordance with the County of Sacramento Standard Construction Specifications, Section 7-5.01 Progress Schedule.

C. Site Conditions

The CONTRACTOR shall be responsible for having determined the site conditions to his or her satisfaction, prior to the submission of a bid, the nature and location of the work, the type and quantity of materials to be encountered, the character of equipment and facilities needed preliminary to and during the execution of the work, the general and local conditions, and all other matters which can in any way affect the work under this Contract.

The prices established for the work to be done will reflect all costs pertaining to the work.

Any claims for extras based on site conditions will not be allowed.

1.11 NO WAIVER OF GOVERNMENT CLAIM PROCESS

No statement in this Agreement shall constitute a waiver of government claim filing requirements pursuant to Title 1, division 3.6 of the California Government Code or as otherwise set forth in local, state and federal law.

1.12 REFUSE

Refuse may be disposed of at the active face at the Kiefer Landfill between the hours of 6:30 AM and 3:00 PM Monday through Friday. Any refuse not transported to the landfill must be covered by a plastic tarp overnight. No disposal fee will be charged for disposal.

1.13 HEALTH AND SAFETY PLAN

The Contractor shall prepare a contract specific Health and Safety Plan, as required by California law, Sacramento County Code, and the Sacramento County Standard Construction Specifications (12-1.01.B), and meeting the satisfaction of the Engineer. The Health and Safety Plan shall include notification of USA 2 to14 days prior to excavation (800) 227-2600 or www.USANorth.org. Costs for all labor, equipment, and materials associated with preparation of a satisfactory Health and Safety Plan shall be paid for in the unit price bid for the various items of work, and no additional compensation will be allowed.

1.14 RECORD DRAWINGS SPECIFICATIONS

A. Maintain on the construction site, one set of the following record documents, which record actual revisions to the work:

1. Drawings

2. Specifications

3. Addenda

4. Request for information

5. Field instructions

6. Change orders and other modifications to the contract.

7. Reviewed shop drawings, product data and samples

8. Manufacturer’s instruction for assembly, installation, and operation

B. Ensure entries are complete and accurate, enabling future reference by the County.

C. Store record documents separate from documents used for construction.

D. Keep record information concurrent (within 7 days) of construction progress.

E. Specification: Legibly mark and record at each product section a description of the actual products installed, including the following:

1. Manufacturer’s name, product model, and number.

2. Product substitutions or alternates utilized.

3. Changes made by addenda and modifications.

F. Record (As-Built) Drawings

1. Legibly mark each item to record actual construction including:

a. Measured depths of foundations in relation to finished floor datum.

b. Measured horizontal and vertical locations of underground utilities and appurtenances referenced to permanent surface improvements. This shall include, but shall not be limited to piping, conduit, valves, stub outs, etc.

c. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the work. This shall include, but shall not be limited to piping, conduit, valves, stub outs, etc

d. Field changes of dimension and detail.

e. Details not on original contract drawings.

G. Progress Record Documents

Record Documents shall include all subcontractor changes and shall be kept current as the work progresses. Progress documents shall be made available and subject to review and approval by the Engineer at each progress payment.

H. Final Record (As-Built) Documents

The Contractor shall submit two completed set of Record Drawings and Specifications, to the Engineer a minimum of one week prior to the final inspection. These Record Documents shall include certification by the Contractor that the Record Drawings and Specifications are a true representation of the Work as actually constructed. The Work will not be formally accepted until the Record Documents are reviewed and accepted by the Engineer.

In addition to the two complete sets Record Drawings and Specifications, after Record Drawings are accepted by the Engineer, Contractor shall submit electronic Record Documents.

I. Measurement and Payment

In addition to the retention provided for in Sections 8-7, 8-8 and 8-9 of the Standard Construction Specifications, the County shall retain ten percent (10%) of each progress or final payment when Record Documents are found not to be in compliance with the contract requirements. Full compensation for Record Documents is included in the prices paid for the various items of work and no separate payment will be made.

SECTION 012000 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.01 SUMMARY

A. Section includes general requirements for measurement and payment as they apply to this Contract.

B. The Contractor will compute all quantities. Where necessary, such computations will be based upon surveys performed by the Contractor. Quantities for final payment will be reviewed and approved by the County.

1.02 RELATED SECTIONS

A. Measurement and Payment - Section 8 of the Standard Construction Specifications

B. Section 013300 - Submittals

1.03 Measurement of Quantities

A. Measurement Standards: All work to be paid for at a Contract price per unit of measurement will be verified by the County consistent with United States Standard Measures.

B. Measurement by Volume:

1. Measurement by volume will be by the cubic dimension listed or indicated in the Bid

Schedule. Method of volume measurement will be as determined or directed by the County.

2. Confirmation of volume may be required by utilizing weighing methods. In this event, such volumes will be converted to weight measurement for payment purposes. Factors for conversion from weight measurement to volume measurement will be determined by the County and shall be agreed by the

Contractor before such method of measurement of pay quantities will be accepted.

C. Measurement by Area: Measurement by area will be by the square dimension listed, or indicated in the Bid Schedule. Method of square measurement will be as determined or directed by the County.

D. Linear Measurement: Linear measurement will be by the linear dimension listed or indicated in the Bid Schedule. Method of linear measurement will be as determined or directed by the County. Generally, items, components, or work to be measured will be measured at the centerline of the item in place.

E. Lump-Sum Measurement: Lump-sum measurement will be for the entire item, unit of work, structure, or combination thereof, as listed or indicated in the Bid Schedule.

F. Allowance: Payment under an allowance item will only be made upon acceptance and approval of quantities of work, invoices or other appropriate documentation as determined by the Agency.

1.04 Field Measurement for Payment

A. The Contractor shall compute all quantities of work performed or of materials and equipment delivered to the site for payment purposes.

B. The County may at any time verify quantities calculated by the Contractor.

1.05 Payment

A. Payment will be full compensation for furnishing all labor, materials, tools, equipment, transportation, permit fees, services, and incidentals, as specified, and for performing all work necessary for completing the erection or installation of the item or work classification, including all adjusting and balancing, testing, cleaning, and all other incidental work.

B. Full compensation for all expenses involved in conforming to the requirements for measuring materials or work shall be considered as included in the unit or lump-sum prices paid for the materials or work being measured, and no additional compensation will be permitted.

C. Full compensation for an item of work for which no measurement or payment is specified will be considered to be included in the applicable related item of work in the Bid Schedule or incidental of the Contract.

1.06 Values of Unit Prices

A. The number of units and quantities contained in the Bid Schedule are approximate only, and final payment will be made for the actual number of units and quantities, which are incorporated in or made necessary by the work included in this Contract.

B. In the event that work and materials, or equipment are required to be furnished to a greater or lesser extent than is indicated by the Construction Drawings and Specifications, such work and materials or equipment shall be furnished in greater or lesser quantities.

1.07 Changes and Extra Work

A. Changes and extra work ordered by the County will be measured and paid for consistent with the requirements of Changes and Claims - Section 9 of the Standard Construction

1.08 Rejected Materials

A. Quantities of material wasted or disposed of in a manner not called for under the Contract;

rejected loads of material, including material rejected after it has been placed by reasons of the failure of the Contractor to conform to the provisions of the Contract; material not unloaded from the transporting vehicle; material placed outside the limits indicated on the Drawings or established by the County; or material remaining on hand after completion of the work, will not be paid for, and such quantities shall not be included in the final total quantities. No compensation will be permitted for loading, hauling, and disposing of rejected material. Contractor is responsible for removing rejected and unused materials from site.

1.09 Contract Bid Items

REQUIREMENTS INCLUDED

A. This section includes the items of work and the basis of payment for these tasks. The Contractor shall bid items listed below separately and provide a total sum for all work items.

The Contractor is responsible for supplying all materials, equipment and labor necessary for the complete construction and installation of all work as described in these specifications and as shown on the Construction Drawings. Payment for each work item will be made on either a unit price (EA), lump sum (LS), allowance (AL), lineal foot (LF), vertical foot (VF), cubic yard (CY), acre (AC), or square foot (SF) basis, and only after that portion of the project has been completed.

Item 1. Mobilization and Demobilization. This task includes any and all temporary facilities and utilities, health and safety plans, and construction equipment mobilization and demobilization required for this project. This section shall also include all submittals, site cleanup and BMP necessary for the work involved.

Payment for this work will be made on a lump sum (LS) basis. Payment shall be made in accordance with Section 8-1 of the Standard Specification.

Item 2. Layout of Work, and As-Built Drawings. This task includes furnishing all labor, materials, tools, equipment, incidentals, for doing all the work involved in surveys for layout and performance of work, measurement and payment, and as-built drawings. Payment shall be made on a lump sum (LS) basis.

Item 3. Furnish & Install Buried 12” Schedule 40 PVC Pipe, and Connect to

Existing Network, including excavation, and backfill - Supply all materials, equipment, labor, and incidentals necessary for the installation of the underground water line connection at Deer Creek at 0+00, as specified in these Specifications, as shown on the Construction Drawings, including excavation, backfilling and necessary and as directed by the Engineer. Payment for this item will be on a Lump Sum (LS) basis.

Item 4. Furnish and install 8” HDPE SDR 17 Pipes - Supply all materials, equipment, labor, and incidentals necessary for the installation of new HDPE Piping, fittings, anchoring, and all accessories in these Specifications, as shown on the Construction Drawings, and as directed by the Engineer. Payment for this item will be on a per lineal foot (LF) basis.

Item 5. Furnish and install 6” HDPE SDR 17 Pipes - Supply all materials, equipment, labor, and incidentals necessary for the installation of new 6” HDPE Piping, fittings, anchoring, and all accessories in these Specifications, as shown on the Construction Drawings, and as directed by the Engineer. Payment for this item will be on lump sum (LS) basis.

Item 6 Furnish and install 2” Air Relief Valve at STA 7+08 - Supply all materials, equipment, labor, and incidentals necessary for the installation of new 2” Air Relief Valve, with all ductile transition piping and fittings, and all accessories in these Specifications, as shown on the Construction Drawings, and as directed by the Engineer. Payment for this item will be on a lump sum (LS) basis.

Item 7 Excavate, Trench and Backfill, Selective Demolition and repair access road

– Supply all material, equipment, labor and incidents for all earthwork for the installation of the complete waterline (excluded the excavation, backfill, and compaction at Deer Creek). Work included excavating, compaction and backfilling for existing waterline for connection, access road excavation, slope repair at station 8+50, access road repair with compaction and backfill. Include hauling of excess material to Kiefer Landfill. Include demolition and disposal of 6” HDPE piping. Payment for this item will be on a lump sum (LS) basis.

Item 8 Furnish and install 10" Corrugated Metal Pipe at 2 Crossings (0+46 and 11+00).

Supply all materials, equipment, labor and incidentals necessary for the installation of the 10" CMP and all accessories in these Specifications, as shown on the Construction Drawings, and as directed by the Engineer. Payment for this item will be on a lump sum (LS) basis.

SECTION 013300

SUBMITTALS

PART 1 - GENERAL

SUMMARY

A. Provide submittals consistent with the Standard Specification, Section 5 – Control of Work and Materials. In addition, comply with the following requirements specified herein.

B. Submit shop drawings to the County/Engineer sufficiently in advance consistent with prearranged schedule to cause no delay in the County's/Engineer's own work or in that of any other subcontractor and to afford ample time for consideration, checking, correcting, and rechecking. Show complete details of construction and methods of installation including sizes, dimensions, setting numbers, types of materials, provision of hardware, accessory items, build-ins, opening sizes, cut-outs, joints, required blocking, welds, anchorage to other construction, and other pertinent items. Verify dimensions on the job and correlate work with adjoining work.

C. All shop drawings must be submitted in the same size sheets as County's/Engineer's drawings or on 11" x 17" size sheets.

D. Four copies of approved shop drawings will be required for County's/Engineer's use unless otherwise indicated. Contractor shall determine the number of and furnish such additional copies as may be needed.

E. County/Engineer will return to Contractor two red-lined copies of any shop drawing which has been rejected or returned for revisions. Make additional submittals as required. County's/Engineer's approval of such drawings or schedules shall not relieve Contractor from responsibility for any resulting deficiencies or related unapproved deviations from the Construction Drawings and Specifications.

F. No shop drawings shall be distributed for field use without appropriate County's/Engineer's approval.

RELATED SECTIONS

A. 011100 – Special Provisions B. 015700 - Temporary Control

C. 022100 - Layout of Work and Surveys D. 312300 - Site Earthwork E. 400531 - Plastic Pipe

OTHER TYPES OF SUBMITTALS

A. Other related drawings pertain to drainage facilities and other fabricated materials.

B. Survey Submittals: Consistent with Section 022100 - Layout of Work and

Surveys, final as-built drawings of surveys performed by the Contractor shall be submitted. As-built drawings shall be submitted before submitting invoice for final payment.

C. Site-Specific Safety Plan: Consistent with the Special Provisions, a Site-Specific Safety Plan shall be submitted which addresses health and safety issues and complies with OSHA, Cal-OSHA, and all other regulatory agency requirements.

D. Project Record Documents: Consistent with the Special Provisions, Project Record Documents shall be submitted before submitting invoice for final payment.

E. Water Pollution Control Plan: Consistent with Section 015700 - Temporary Controls, a Water Pollution Control Plan shall be submitted to address water pollution and the plan to be implemented by the Contractor during the Contract work.

F. Material Submittals: Consistent with the requirements of applicable Specification Sections.

G. Material delivery tickets or bills of lading.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

A. The following submittal log has been developed for the Contractor’s convenience and general information, and in no way limits the responsibility of the Contractor from submitting all submittals required by these specifications or the standard specifications.

Submittal Log

Submittal Specification

Reference Comment

Construction Plan and Schedule 011100-1.10 Prior to start of work and prior to each construction sequence

Manufacturer Instruction 011100-1.06 As required before work begins

Preconstruction Survey 022100-1.04 Prior to start of work

Contractor’s Health and Safety Plan 011100-1.13 Prior to start of work

Water Pollution Control Plan 015700-1.04 Prior to start of work

Heavy Equipment Emissions 015700-1.09 4 business days prior to start of work

Record Documents 011100-1.14 At completion and before submitting final invoice

All Piping Material, fittings, flanges, Air Relief and Vacuum Valve and accessories

Division 33 Division 40

15 days after notice to proceed.

SECTION 015700

TEMPORARY CONTROLS

PART 1 - GENERAL

SUMMARY

A. Section includes temporary controls required during the term of the Contract for the protection of the environment, and the health and safety of workers and general public.

B. Temporary controls shall include furnishing all equipment, materials, tools, accessories, incidentals, labor, and performing all work for installation of equipment and construction of facilities, including their maintenance and operation during the term of the Contract.

C. Temporary controls shall include, but not be limited to, the following:

1. Dust control

2. Noise control

3. Pollution and sediment control

4. Air pollution control

D. The work shall be performed as specified in this Specification and as required by the County/Engineer. The equipment and accessories shall be maintained in clean, safe, and sanitary condition at all times until completion of the Contract.

E. Upon completion of the Contract, the temporary controls shall be left in the status specified in Article 1.12 of this section.

F. The requirements specified herein are in addition to requirements specified elsewhere in the Contract Documents. Temporary controls shall meet the requirements for all-weather service.

G. All land disturbances related to the temporary controls shall be minimized to the greatest extent possible and the land restored, to the extent reasonable and practical, to its original contours by grading to provide positive drainage.

RELATED SECTION – NOT APPLICABLE

APPLICABLE PUBLICATIONS

A. All required facilities, equipment, and utilities shall also be constructed, installed, maintained, and operated consistent with applicable federal, state, county, and utility laws, rules, and regulations. Notwithstanding contrary provisions of General Conditions and Special Conditions, nothing in the Construction Drawings and Specifications shall be construed to permit work not conforming to such laws, rules, and regulations.

SUBMITTALS

A. A Water Pollution Control Plan (WPCP) – See Section 10-4.06 of the County

Construction Plans and Specifications

DUST CONTROL

A. The Contractor shall be responsible for providing adequate dust control measures during the term of the Contract. Dust palliatives shall not be used without written authorization of the Engineer.

B. Dust control shall consist of furnishing water supply, required equipment, additives, accessories, and incidentals, and carrying out proper and efficient measures wherever and as often as necessary to reduce dust nuisance, and to prevent dust originating from construction operations during the completion of the Contract, as required by the County/Engineer.

C. Water shall be applied by means of pressure-type distributors or pipelines equipped with a spray system or hoses with nozzles that will ensure a uniform application of water.

D. All equipment used for the application of water shall be equipped with a positive means of shut off.

E. Unless otherwise permitted by the County/Engineer or unless all the water is applied by means of pipelines, at least one mobile unit shall be available at the Site in operating condition for applying water at the Site during construction.

POLLUTION CONTROL

A. Pollution of Waterways:

1. The Contractor's construction and related activities shall be performed by methods that prevent entrance or accidental spillage of solid or liquid matter, contaminants, debris, and other objectionable pollutants and wastes into streams, water courses (flowing or dry), and underground water sources.

Such pollutants and wastes will include, but will not be restricted to refuse, earth and earth products, garbage, cement, concrete, sewage effluent, industrial waste, radioactive substances, hazardous chemicals, oil and other petroleum products, aggregate processing tailings, and mineral salts.

Pollutants and wastes shall be disposed of consistent with applicable permit provisions or in a manner acceptable to and approved by the County/Engineer.

2. Prior to the start of work, the Contractor shall prepare a Water Pollution Control Plan (WPCP) meeting the requirements of Section 10-4 of the County’s Standard Construction Specifications.

B. Storage and Disposal of Petroleum Products:

1. Petroleum products covered by this section include gasoline, diesel fuel, lubricants, heating oils, and refined and used oil. During project construction, all petroleum products shall be stored in such a way as to prevent contamination of all ground and surface waters.

2. Lubricating oil may be brought into the project area in steel drums or other means, as the Contractor elects. If the total volume of stored oil is greater than 1,320 gallons, then the Contractor shall provide secondary containment facilities. Used lubricating oil shall be stored in steel drums, or other approved means, and shall be returned to the supplier for disposal. It shall not be burned or otherwise disposed of at the project area.

3. If the total volume of stored petroleum products is greater than 1,320 gallons and these products are stored aboveground, the Contractor shall prepare a spill prevention control and countermeasure plan consistent with applicable EPA and other state regulations.

TRAFFIC AND SAFETY CONTROLS

A. The Contractor shall post construction areas and roads with traffic control signs or devices used for protection of workmen, the public, and equipment. The signs or devices shall conform to the American National Standards Institute Manual on Uniform Traffic Control Devices for Streets and Highways, and the Standard Construction Specifications.

B. Signs or traffic control devices shall be removed or covered as soon as they have served their purpose. It is particularly important to remove any markings on road surfaces which under conditions of poor visibility could cause a driver to turn off the road or into traffic moving in the opposite direction.

C. Barricades for protection of employees shall conform to the portions of the American National Standards Institute Manual on Uniform Traffic Control Devices for Streets and Highways relating to barricades.

D. Material Haul on Public Roads: All requirements stated in the permits shall be followed for using public roads for hauling materials to the Site.

E. Flag persons, properly equipped with International Orange protective clothing and flags, shall be provided at all such times, as necessary, to direct or divert pedestrian or vehicular traffic.

F. The Contractor shall construct and maintain fences, planking, barricades, lights, shoring, and warning signs as required by local authorities and federal and state safety ordinances, and as required, to protect the property from injury or loss and as necessary for the protection of the public and provide walks around any obstructions made in a public place for carrying on the work covered in this section. All such protection shall be left in place and maintained until removal is authorized.

G. In addition, the Contractor shall guard and protect all workers, pedestrians, and the public from excavations, blasting operations, construction equipment, all obstructions, and other dangerous items or areas by means of adequate railings, guard rails, temporary walks, barricades, warning signs, sirens, directional signs, overhead protection, planking, decking, danger lights, etc.

AIR POLLUTION CONTROL

A. The Contractor shall comply with all air pollution control rules, regulations, ordinances, and statutes which apply to any work performed pursuant to the contract, including any air pollution control rules, regulations, ordinances, and statutes specified in Section 11017 of the Government Code.

HEAVY EQUIPMENT EMISSIONS

A. The Contractor shall submit in accordance with Section 013300 a plan for approval by the Sacramento Metropolitan Air Quality Management District (SMAQMD) demonstrating that the heavy-duty (>50 horsepower) off-road vehicles to be used in the construction project, and operated by either the prime contractor or any subcontractor, will achieve a fleet-averaged 20 percent NOx reduction and 45 percent particulate reduction compared to the most recent California Air Resources Board (CARB) fleet average. Compliance shall be demonstrated using the SMAQMD construction mitigation calculator, which is accessible at http://www.airquality.org/. The calculator is updated regularly by the SMAQMD and may not necessarily be the one used for the project.

B. The Contractor's initial submittal shall include a comprehensive inventory of all off-road construction equipment, equal to or greater than 50 horsepower, which will be used for 40 or more hours during the construction project. The inventory shall include the horsepower rating, engine production year, and hours of use or fuel throughout for each piece of equipment. The equipment inventory and mitigation calculator shall be updated and submitted monthly throughout the duration of the project, except that the submittal shall not be required for any 30-day period in which no construction activity occurs.

C. The Contractor shall ensure that emissions from all off-road diesel-powered equipment used on the project site do not exceed 40 percent opacity for more than three minutes in any one hour. Any equipment found to exceed 40 percent opacity shall be repaired immediately, and the County/Engineer and SMAQMD shall be notified within 48 hours of identification of non-compliant equipment. The Contractor shall perform a visual survey of all in-operation equipment, at least weekly, and a monthly summary of the visual survey results shall be submitted to the County/Engineer throughout the duration of the project, except that the monthly summary shall not be required for any 30-day period in which no construction activity occurs. The monthly summary shall include the quantity and type of vehicles surveyed as well as the dates of each survey. The SMAQMD and/or other officials may conduct periodic site inspections to determine compliance. Nothing in this section shall supersede other SMAQMD or state rules or regulations.

POWER GENERATOR EMISSIONS

A. The Contractor is responsible for obtaining all permits, complying with regulations, and performing all monitoring and reporting required by the use of fossil fuel powered electricity generators on the project.

MAINTENANCE

A. Contractor shall maintain all temporary controls in good working condition during the term of the Contract for the safe and efficient transport of equipment and supplies, and for construction of permanent works, as required by the County/Engineer.

STATUS OF COMPLETION

A. Upon completion of the work, or prior thereto, when so required by the

County/Engineer, Contractor shall remove all temporary controls, and restore disturbed areas as required by the County/Engineer.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

(Not Used)

SECTION 017400

CONSTRUCTION CLEANING

PART 1 - GENERAL

SUMMARY

A. Section Includes:

1. Cleanup during construction

2. Final cleaning of the Site prior to acceptance of the project by the

County/Engineer B. The requirements specified in this section are supplemental to the requirements specified in the General Specifications.

GENERAL

A. It is required that the entire Site be kept in a neat and orderly condition, and the

County/Engineer may, at any time during construction, order a general cleanup of the Site as a part of the work under this section.

B. Contractor shall dispose of waste, trash, and debris in a safe, acceptable manner, consistent with applicable laws and ordinances and as prescribed by authorities having jurisdiction. Class III municipal solid waste which is excavated may be disposed of at the working face of the landfill as allowed by the County/Engineer. All refuse shall be taken across the landfill scale prior to disposal. No charge will be made to the Contractor for proper disposal. No other waste material or debris shall be buried on the Site. Burning of trash and debris on the Site will not be permitted.

CLEANUP DURING CONSTRUCTION

A. Cleanup: The Contractor will be required to clean up construction work areas including all office facilities and dispose of waste material. Cleanup of construction work areas will be required on a daily basis. At the close of each day's work all small quantities of waste and debris resulting from construction activities and from office facilities shall be gathered up and disposed of as designated in paragraph B below. Waste and debris shall not be allowed to accumulate in such quantities as to create an unsightly appearance, or safety or fire hazard, nor shall it interfere in any way with free access to, and operation of existing facilities.

B. Waste Disposal: The Contractor shall provide suitable receptacles for all construction and office waste material such as wrapping paper, discarded containers, scrap lumber, scrap metals, etc.

FINAL SITE CLEANUP

A. Prior to final inspection, the entire Site shall be thoroughly cleaned and shall be put into a neat, acceptable condition. All construction waste and unused materials, dunnage, loose rock and stones, excess earth, and debris of any description resulting from the work shall be removed from the entire Site.

B. All pavements and paved walks shall be hosed down and scrubbed clean where necessary.

C. All construction areas shall be thoroughly cleaned to the satisfaction of the County/Engineer prior to final acceptance of the completed Contract.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

(Not Used)

SECTION 022100

LAYOUT OF WORK AND SURVEYS

PART 1 - GENERAL

SUMMARY

A. Section includes general requirements for survey work to be performed by the Contractor for layout of work features, for performance of work, and for field measurements of work quantities for payment purposes.

B. Before commencing any surveys, the Contractor shall give the County/Engineer two working days' written notice in advance so that the County/Engineer may witness such work.

RELATED SECTION

A. Section 012000 – Measurement and Payment

DESCRIPTION

A. Reference Points: The reference points to be provided by the County/Engineer will include referenced monuments, survey control line(s), and elevation benchmarks in the vicinity of the project. If displaced by the Contractor, replacement of these reference points will be at the expense of the Contractor.

All other necessary reference points shall be established by the Contractor.

B. The Contractor shall furnish all necessary detail surveys including all lines, grades, and appropriate surveys as specified. Contractor shall stake out the line they intend to install the water line and electrical cable. Provide elevation profile of the final water line with survey points every 100’. Provide final grade survey points on existing disturbance area.

C. The County/Engineer reserves the right to perform any desired checking and correction of the Contractor's surveys, but this shall not relieve the Contractor of the responsibility for adequate performance of the work. The County/Engineer will complete any checking within two working days of the Contractor's completed survey.

D. Equipment and Personnel: The Contractor's instruments and other survey equipment shall be accurate, suitable for the surveys required, consistent with recognized professional standards, and in proper condition and adjustment at all times.

E. Field Notes and Records: The Contractor shall record surveys in field notebooks.

The original pages of such records shall be furnished to the County/Engineer at intervals required by the County/Engineer. The County/Engineer will have up to two working days to review the data and notify the Contractor of any errors.

A duplicate of each field notebook shall be furnished to the County/Engineer when filled or completed.

F. Use by the County/Engineer: The County/Engineer may at any time use line and grade points and markers established by the Contractor. The Contractor's surveys are a part of the work and may be checked by the County/Engineer or representatives of the County/Engineer at any time. The Contractor shall be responsible for (1) any lines, grades, or measurements which do not comply with specified or proper tolerances, or which are otherwise defective and (2) any resultant defects in the work. The Contractor will be required to conduct resurveys or check surveys to correct errors indicated by review of the field notebooks or otherwise detected.

SURVEYS FOR LAYOUT AND PERFORMANCE OF WORK

A. The Contractor shall perform all surveys for layout and performance of the work, reduce the field notes, make necessary calculations, and prepare drawings necessary to carry out such work.

SURVEYS FOR MEASUREMENT FOR PAYMENT

A. When the Specifications or the County/Engineer require Bid Schedule items of work to be measured by surveying methods, the Contractor shall perform the surveys. The Contractor will reduce the field notes and calculate final quantities for payment purposes. A duplicate of the note reductions and calculations will be given to the County/Engineer for review and approval.

SURVEYS FOR AS-BUILT DRAWINGS

A. The Contractor shall perform as-built surveys at a 50-foot intervals along installed pipe. As-built survey points shall be taken at the top-of-pipe.

Existing ground which was disturbed during excavation, trenching or backfilling shall be survey as well.

B. These as-builts will be submitted on drawings to the County/Engineer indicating location of survey point (i.e., northing, easting, and elevation). The County/Engineer shall have up to two working days to review and approve the as-built surveys. After final approval by the County/Engineer the Contractor shall submit three sets of final drawings.

SURVEY ACCURACY AND SURVEY STAKE SETTING TOLERANCE

A. Control traverse field surveys and computations shall be performed to an accuracy of at least 1:25,000.

B. The tolerances generally applicable in setting survey stakes shall be as set forth below. Such tolerances shall not supersede stricter tolerances required by the drawings or Specifications and shall not otherwise relieve the Contractor of responsibility for measurements in compliance therewith.

Type of Line or Mark Horizontal Position Elevation

Permanent reference points 1 in 10,000 ±0.01 foot

General excavation earthwork 1 in 2,000 ±0.1 foot

C. Tolerances for designed thicknesses shown on Construction Drawings and for elevations shown on the Contract Drawings shall be ±0.10 foot, unless otherwise stated in these Specifications or on the Drawings.

SECTION 028000

PRESSURE TESTING OF PIPE

GENERAL

REQUIREMENTS INCLUDED

Leak testing shall be conducted by the Contractor on the following lines, as applicable:

All liquids distribution piping installed by the Contractor.

The procedure and equipment to be used shall be approved by the Engineer prior to testing.

The Contractor shall perform leakage tests on all non-perforated piping after installation and before backfilling where pipe is buried or encased. The Contractor shall test the entire pipeline again after all pipes are cleaned and buried.

At the Contractor’s discretion, pipe may be tested in fused sections prior to installation to reduce the potential of repairs needed following installation. This method does not replace the requirement to test the pipe after installation.

PRODUCTS

TESTING EQUIPMENT

The Contractor shall provide necessary piping connections between the section of line being tested and the nearest available source of air, or test fluid, together with test pumping equipment, pressure gauge and other equipment, materials, and facilities necessary to make the specified tests. The Contractor shall provide temporary sectionalizing devices and vents as required for testing. Vents are to be left plugged if not required for the permanent installation.

EXECUTION

TESTING PROCEDURE

The following procedures will be performed by the Contractor, as outlined below:

The specified test pressures shall be as measured at the horizontal centerline of the lowest point of the piping under test.

Each pipeline shall be adequately braced and supported before tests are made. Partial backfilling between joints of pipelines in trenches is permissible to prevent movement under test pressure, subject to approval by the Engineer.

Pipelines that…