39.45-H75 Bid Schedule.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
MM-39. 45-H. 75, Rapid Creek Culvert Replacement
Solicitation number
IFB-25-RCC-83
Issued by
Larimer County, Colorado

About this file

The document is a bid schedule for Mesa County, Colorado, detailing a culvert replacement project on Rapid Creek Road (39.45-H.75 Bridge). The project involves replacing an existing 120-inch corrugated metal pipe (CMP) with a 10' x 8' Reinforced Concrete Box Culvert (RCBC), including road improvements. The bid schedule itemizes 44 different construction and environmental mitigation line items, covering activities such as clearing and grubbing, rock excavation, structure backfill, erosion control, guardrail installation, seeding, and traffic management. The total project budget is set at $80,000, with a line item for Force Account - Minor Contract Revisions at $80,000.

The bid schedule indicates a comprehensive approach to infrastructure replacement, with detailed provisions for environmental restoration, including native seeding, soil conditioning, and erosion control measures. The project includes specific allocations for construction surveying, mobilization, public information services, and traffic control. Notable elements include concrete work, reinforcing steel, delineators, and temporary barrier installation. The document suggests a thorough, methodical approach to the culvert replacement, with extensive attention to environmental mitigation and road restoration components, reflecting a holistic infrastructure improvement strategy for Mesa County.

View the file

Other files

File Type Posted
39.45-H75 Construction Plans.pdf PDF
39.45-H75 Geotech Memo.pdf PDF
IFB-25-RCC-83 F.pdf PDF
39.45-H75 Geotech Report.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

39.45-H.75 Culvert Replacement

ITEM NUMBERSUMMARY OF APPROXIMATE QUANTITIES - (SCHEDULE A) MESA COUNTY
CONTRACT REF NUMBERCONTRACT ITEM DESCRIPTIONQUANTITYUNIT COSTEXTENDED COST
QUANTITYUNIT
1201-00000CLEARING AND GRUBBINGLS1$0.00
2201-00004REMOVAL OF CULVERTEA1$0.00
3202-01110REMOVAL OF GUARDRAILLF85$0.00
4202-00220REMOVAL OF ASPHALT MATSY861$0.00
5203-00400ROCK EXCAVATIONCY710$0.00
6203-00210BORROW (CIP)CY3,324$0.00
7206-00000STRUCTURE EXCAVATIONCY550$0.00
8206-00100STRUCTURE BACKFILL (CLASS 1)CY300$0.00
9208-00001SILT DIKELF130$0.00
10208-00002EROSION LOG TYPE 1 (12 INCH)LF750$0.00
11208-00011EROSION BALES (WEED FREE)EA20$0.00
12208-00045CONCRETE WASHOUTEA1$0.00
13208-00207EROSION CONTROL MANAGEMENTLS1$0.00
14606-00301GUARDRAIL TYPE 3 (6-3 POST SPACING)LF219$0.00
15210-00010RESET MAILBOXEA1$0.00
16212-00032SOIL CONDITIONINGAC1$0.00
17212-00700ORGANIC FERTILIZERLB80$0.00
18212-00702BIOTIC SOIL AMENDMENT (HYDRAULIC APPLIED)LB1,200$0.00
19212-00703HUMATELB65$0.00
20212-00704MYCORRHIZAELB3$0.00
21212-00707SEEDING (NATIVE) HYDRAULICAC1$0.00
22213-00003MULCHING (WEED FREE)AC1$0.00
23213-00061MULCH TACKIFERLB300$0.00
24216-00101SOIL RETENTION BLANKET (CLASS 1)SY750$0.00
25304-06007AGGREGATE BASE COURSE (CLASS 6)CY475$0.00
26420-00102GEOTEXTILE (EROSION CONTROL) (CLASS 1)SY945$0.00
27403-33741HOT MIX ASPHALT (HMA) (SX75) (PG 64-22)TON153$0.00
28506-00030GROUTED RIPRAPCY3$0.00
29506-00218RIPRAP (18 INCH)CY15$0.00
30601-03000CONCRETE CLASS D (WALL, FOOTING, APRON)CY190$0.00
31602-00020REINFORCING STEEL (EPOXY COATED)LB29,700$0.00
32603-708108'X10' CONCRETE BOX CULVERTLF88$0.00
33606-01390END ANCHORAGE TYPE 3KEA4$0.00
34610-00010MEDIAN COVER MATERIAL (DECORATIVE)SF4,896$0.00
35612-00001DELINEATOR (TYPE I)EA50$0.00
36619-501602-INCH PLASTIC PIPELF28$0.00
37620-00020SANITARY FACILITYEA2$0.00
38625-00000CONSTRUCTION SURVEYINGLS1$0.00
39626-00000MOBILIZATIONLS1$0.00
40626-01101PUBLIC INFORMATION SERVICESLS1$0.00
41630-00012TRAFFIC CONTROLLS1$0.00
42630-80370BARRIER (TEMPORARY)LF222$0.00
43700-00000DETOUR ROAD MAINTENANCELS1$0.00
44700-00010FORCE ACCOUNT - MINOR CONTRACT REVISIONSFA1$ 80,000.00$80,000.00
TOTAL (SCHEDULE A) MESA COUNTY$80,000.00

TOTAL PROJECT $80,000.00

File details come from the government source that posted it. Updated .