36E77620R0004-0001001.pdf
PDF Posted
- Solicitation number
- 36E77620R0004
About this file
This document contains a justification for other than full and open competition and a notice of a federal contract opportunity for replacing patient lift systems at the Minneapolis VA Medical Center. The justification cites that MedCare is the only brand of patient lift that can meet the agency's needs, as the entire facility currently utilizes MedCare systems. Replacing them with another manufacturer's lifts would significantly increase costs and require extra staff training. The contract opportunity will be a single award firm-fixed-price design-build contract solicited using a Request for Proposal and set aside for Service-Disabled Veteran-Owned Small Businesses. The project scope involves replacing 49 ceiling lifts in the SCI/D building and installing 15 additional lifts in the ED building. The performance period is approximately 275 days and the estimated value is between $1,000,000 and $2,000,000. Questions must be submitted by November 30th to the email address provided.
36E77620R0004 0001 ATTACHMENT 13 - JA - Brand Name Items - Patient Lifts.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36E77620R0004-0005000.docx | DOCX document | |
| 36E77620R0004-0005001.docx | DOCX document | |
| 36E77620R0004-0004012.docx | DOCX document | |
| 36E77620R0004-0004013.pdf | ||
| 36E77620R0004-0003001.docx | DOCX document | |
| 36E77620R0004-0003000.docx | DOCX document | |
| 36E77620R0004-0002000.docx | DOCX document | |
| 36E77620R0004-0002001.docx | DOCX document | |
| 36E77620R0004-0001000.docx | DOCX document | |
| 36E77620R0004-014.docx | DOCX document | |
| 36E77620R0004-015.pdf | ||
| 36E77620R0004-027.pdf | ||
| 36E77620R0004-018.docx | DOCX document | |
| 36E77620R0004-023.docx | DOCX document | |
| 36E77620R0004-024.docx | DOCX document | |
| 36E77620R0004-016.pdf | ||
| 36E77620R0004-013.docx | DOCX document | |
| 36E77620R0004-021.docx | DOCX document | |
| 36E77620R0004-017.zip | ZIP file | |
| 36E77620R0004-022.docx | DOCX document | |
| 36E77620R0004-026.pdf | ||
| 36E77620R0004-019.docx | DOCX document | |
| 36E77620R0004-020.docx | DOCX document | |
| 36E77620R0004-025.docx | DOCX document |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
Justification and Approval
For
Other Than Full and Open Competition
1. Contracting Activity:
Veterans Health Administration (VHA), Program Contracting Activity Central (PCAC)
The proposed procurement, Request for Proposal (RFP) 36E77620R0004 is for Replace Patient Lift
Systems Design-Build project at the Minneapolis VA Medical Center (VAMC).
2. Nature and/or Description of the Action Being Processed:
This justification is to support for Replace Patient Lift Systems Design-Build project at the
Minneapolis VA Medical Center (VAMC) that will be awarded as a firm-fixed price contract. This justification is for other than full and open competition for the procurement of certain construction materials. The use of a particular brand name for the items listed below accommodates standardization of these items throughout the facility.
A. Patient Lifts
i. MedCare Brand
3. Description of Supplies/Services Required to Meet the Agency's Needs:
This procurement is to Replace Patient Lift Systems at the Minneapolis VA Medical Center (VAMC).
The scope includes everything necessary to construct a functional building that meets the requirements of the Department of Veterans Affairs. There is 1 (one) brand name items listed for which the VA is not able to accept equal or alternate items. The value for each of these items is listed below and the VAAR Construction magnitude for the entire project is between $1,000,000 and $2,000,000.00.
i. Patient Lifts
i. Medcare Brands
ii. Value: 60 each lift
iii. Unique Qualifications: Entire facility utilizes MedCare lift systems. This significantly reduces inventory requirements and engineering maintenance staff training requirements.
4. Statutory Authority Permitting Other than Full and Open Competition:
(X) (1) Only One Responsible Source and No Other Supplies or Services Will Satisfy
Agency Requirements per FAR 6.302-1; 41 USC §253(c)(l)
() (2) Unusual and Compelling Urgency per FAR 6.302-2;
() (3) Industrial Mobilization, Engineering, Developmental or Research Capability or Expert Services per FAR 6.302-3;
() (4) International Agreement per FAR 6.302-4
() (5) Authorized or Required by Statute FAR 6.302-5;
() (6) National Security per FAR 6.302-6;
() (7) Public Interest per FAR 6.302-7;
5. Demonstration that the Contractor's Unique Qualifications or Nature of the Acquisition Requires the Use of the Authority Cited Above (applicability of authority):
These items have been standardized throughout the Minneapolis VAMC. Installing a different manufacturers' system will create significant duplication in cost for the facility, and in most cases