F108--Special Remediation Building 25 - CI
Solicitation number
36C26325Q0370
Issued by

About this file

This is a Request for Quotation (RFQ) issued by the Department of Veterans Affairs Network 23 Contracting Office for mold remediation services at Building 25 of the Central Iowa VA Health Care System in Des Moines, Iowa. The solicitation (36C26325Q0370) is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside under NAICS code 562910 with a size standard of 1000 employees.

The scope includes remediation of airborne microbial particles that exceed acceptable levels for a healthcare facility. Key requirements include placing the building under negative pressure, isolating the HVAC system, removing all carpet and ceiling tiles, removing contaminated drywall and insulation, and disinfecting all semi-porous and non-porous surfaces. A site walk-through is scheduled for February 25, 2025 at 2:00 PM CST, with registration required by February 24, 2024 at 1:00 PM CST. Quotes are due March 6, 2025 at 4:00 PM CST. The period of performance is 30 calendar days from notice to proceed. The pricing schedule includes separate line items for demolition services (146 hours), cleaning services (38 hours), and associated materials. Technical evaluation factors include vendor qualifications, quality control plan, and past performance, which when combined are more important than price.

View the file

Other files

File Type Posted
D.3 Mold Remediation Floor Plan, updated.pdf PDF
36C26325Q0370 A0001.pdf PDF
36C26325Q0370_1.docx DOCX document
D.1 Remediation Floor Plan.pdf PDF
D.2 Remediation Investigation Pictures.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE 1 OF 1. REQUISITION NO.

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL

TIME

9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

8(A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE

TELEPHONE NO. UEI: EFT:

PHONE: FAX:

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED

SEE ADDENDUM

19. 20. 21. 22. 23. 24.

ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)

PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212

7. FOR SOLICITATION

INFORMATION CALL:

STANDARD FORM 1449

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

636-25-2-9284-0003

36C26325Q0370 02-20-2025

Jennifer Watkins-Schoenig 319-688-3631 03-06-2025

4:00 PM CST

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

1303 5th St

Suite 300

Coralville IA 52241

X 100

X

562910

1000 Employees

N/A

Central Iowa VAHCS

3600 30th St.

Des Moines IA 50310

NETWORK 23 CONTRACTING OFFICE

1303 5th St, Suite 300

Coralville IA 52241

FMS-VA-2(101)

Financial Services Center

PO Box 149971

Austin TX 78714-9971

See CONTINUATION Page

Mold Remediation for Central Iowa VAHCS. See B.2 and B.3 for further details.

This solicitation is an SDVOSB Set Aside.

FAR 13.1 Simplified Acquisition Procedures

Comparative Evaluation, see provision 52.212-2 for items required to be submitted with proposals.

Interested vendors are encouraged to attend a site walk through on Tuesday, February 25th, 2025 at 2:00 PM CST, See B.2 for more details.

FOR CONSIDERATION, ALL QUESTIONS MUST BE RECEIVED 72 HOURS

BEFORE DATE STIPULATED IN BLOCK 8 OF THE SF1449 FORM.

EMAIL ALL QUESTIONS AND RESPONSES TO:

Jennifer.watkins-schoenig@va.gov and Joshua.imdacha@va.gov

SIGN SF1449 AND RETURN ALL PAGES WITH OFFER SUBMISSION.

See CONTINUATION Page

636-3650162-9284-854200-2542-636C57XXX-23NRNR009

X X

X 1

Joshua Imdacha

Contracting Officer

36C26325Q0370

Table of Contents

SECTION A

A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS

AND COMMERCIAL SERVICES

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

B.2 STATEMENT OF WORK

B.3 PRICE/COST SCHEDULE

SECTION C - CONTRACT CLAUSES

C.1 FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)

C.2 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

C.3 FAR 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW

INFORMATION (MAY 2024)

C.4 FAR 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN

1997)

C.5 SUPPLEMENTAL INSURANCE REQUIREMENTS

C.6 FAR 52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT,

AND VEGETATION (APR 1984)

C.7 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

C.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

C.9 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR

PERSONNEL (MAY 2020)

C.10 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

C.11 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

C.12 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS

(NOV 2018)

C.13 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..37

C.14 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT

STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (JAN 2025)

SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS

D.1 Remediation Floor Plan

D.2 Remediation Investigation Pictures

SECTION E - SOLICITATION PROVISIONS

E.1 FAR 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS

AND COMMERCIAL SERVICES (SEP 2023)

E.2 FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE

(FEB 1998)

E.3 FAR 52.204-24 REPRESENTATION REGARDING CERTAIN

TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT

(NOV 2021)

E.4 FAR 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT

ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)

E.5 FAR 52.237-1 SITE VISIT (APR 1984)

E.6 FAR 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL

SERVICES (NOV 2021)

E.7 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—

COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024)

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

1. Contract Administration: All contract administration matters will be handled by the following individuals:

a. CONTRACTOR:

b. GOVERNMENT: Contracting Officer 36C263

NETWORK 23 CONTRACTING OFFICE

1303 5th St

Suite 300

Coralville IA 52241

2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:

[X] 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or

[] 52.232-36, Payment by Third Party

3. INVOICES: Invoices shall be submitted in arrears:

a. Quarterly []

b. Semi-Annually []

c. Other [x] Upon satisfactory completion of work

4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment

Requests.

http://www.tungsten-network.com/

ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:

AMENDMENT NO DATE

B.2 STATEMENT OF WORK

REMEDIATION SERVICES FOR BUILDING 25

Project # 636A6-25-101

INTRODUCTION/BACKGROUND

Air quality testing in Building 25, VA Des Moines, revealed levels of airborne microbial particles that exceed an acceptable level for a healthcare facility. Due to this hazard, the building has been vacated of all patients and staff and will remain so until it is safe to occupy.

PROJECT OBJECTIVE

Remediation services to remove or clean all surfaces and materials located inside Building

25. Building to be placed under negative pressure, with additional units to be used as air filtrations. HVAC system to be isolated, all diffusers removed, cleaned, then set aside, all flex ducting to be removed (to later be replaced), and all duct openings to be sealed. All carpet in the building to be removed. All ceiling tiles in the building to be removed. All drywall (including above the drop ceiling) that has microbial growth or moisture damage to be removed. All pipe and ductwork insulation showing evidence of growth or moisture damage to be removed. All building semi and non-porous surfaces - such as but not limited to cabinetry, countertops, metal, glass, rubber baseboards, lighting and plumbing fixtures - needs to be thoroughly disinfected via appropriate cleaning methods.

SPECIFICATIONS

MOLD REMEDIATION TECHNICAL SPECIFICATIONS

PART 1 – GENERAL

1.01 SCOPE

A. This specification covers the remediation of mold including removal, cleanup and disposal of mold contaminated materials from building 25 on the Central Iowa Health campus, Des Moines, Iowa. The methods and procedures in this specification are based on the observations and previously collected background air samples.

B. An estimate of the amount of material to be removed or cleaned is not given. The determination of the actual amounts, for quote purposes, is the responsibility of the

Contractor. By submitting a quote, the Contractor acknowledges that he has investigated and satisfied himself as to:

a. The conditions affecting the work, including, but not limited to, physical conditions of the site which may affect site access, handling and storage of tools and materials, access to water, electricity or other utilities, or otherwise affect performance of required activities.

b. The character and quantity of all surface and subsurface materials or obstacles to be encountered as far as this information is reasonably ascertainable from an inspection of the site, including exploratory work done by the Building Owner or a designated consultant, as well as information presented in drawings and specifications included with this Contract. Any failure by the Contractor to acquaint himself with available information will not relieve him from the responsibility for estimating properly the difficulty or cost of successfully performing the work. The Building Owner is not responsible for any conclusions or interpretations made by the Contractor on the basis of the information made available by the Building Owner.

C. Interested vendors are encouraged to attend a site walk through at the Central Iowa VA

Medical Center located at 3600 30th Street, Building 25, Des Moines, Iowa 50310 on

Tuesday, February 25th, 2025, at 2:00 PM CST. Any vendors interested in attending the site visit must register by sending an email requesting attendance to Jennifer.Watkins-

Schoenig@va.gov before Monday, February 24th, 2024, at 1:00 PM CST. Vendors who do not register for the site visit before the deadline may be excluded from attendance.

Site visit attendance instructions will be provided to all registered vendors. Attending the site visit is not mandatory or required to be eligible for submitting a quote.

1.02 DESCRIPTION

A. The work specified herein shall be the remediation of mold by competent persons trained, knowledgeable and qualified in the techniques of remediation, handling and disposal of mold contaminated materials and the subsequent cleaning of contaminated areas, who comply with all applicable Federal, State and local regulations and are capable of, and willing to perform, the work of this Contract.

B. The Contractor shall supply all labor, materials, services, insurance, permits, licenses, patents, and equipment necessary to carry out the work in accordance with all applicable Federal, State and local regulations and these Specifications.

C. The Contractor is responsible for restoring the work area and auxiliary areas utilized during the remediation to conditions at least equal to original conditions. (This excludes any material removed as part of scope.) Any damages caused during the performance of remediation activities shall be repaired by the Contractor (e.g., paint peeled off by barrier tape, nail holes, water damage, broken glass) at no additional expense to the Owner.

1.03 APPLICABLE STANDARDS AND GUIDELINES

A. All work under this Contract shall be done in strict accordance with all applicable

Federal, State, and Local regulations, standards, and codes governing mold remediation and any other trade work done in conjunction with the remediation.

B. The most recent edition of any relevant regulation, standard, document or code shall be in effect. Where conflict among the requirements or with these Specifications exists, the most stringent requirements shall be utilized.

C. Specific requirements:

a. Title 29, Code of Federal Regulations, 1926. Occupational Safety and Health

Administration (OSHA), U.S. Department of Labor.

1.04 QUALITY ASSURANCE

A. Offerors must be licensed as required by the Iowa Bureau of Labor.

B. Offerors shall demonstrate prior experience on mold remediation projects of similar nature and scope through the submission of letters of reference from the Owners including the name, address, and telephone numbers of contact person (someone specifically familiar with the Contractor's work) for at least three (3) previous users of service.

C. The Owner reserves the right to reject quotes for any reason that serves the best interests of the Owner or building occupants. The Owner also reserves the right to waive any technicality or irregularity in a quote. Failure to submit requested information/documentation can result in automatic disqualification of quote package.

1.05 SUBMITTALS AND NOTICES

Pre-remediation:

A. Submit the location of the landfill to be used for disposal of the mold contaminated material.

B. Submit a list of all personnel who will be involved in the remediation activity including, supervisors, workers, and any other personnel or agent who may be responsible for any aspect of the remediation activities.

C. Submit documentation from a physician that all employees or agents have been medically monitored to determine whether they are physically capable of working while wearing the respirator required without suffering adverse health effects.

D. Submit documentation of respirator fit testing for all employees and agents who must enter the work area. Document NIOSH approval of all respiratory protective devices utilized on-site.

E. Submit a list of equipment for this project.

F. With the Owner or Owner's representative, inspect the premises wherein all remediation and remediation related activities will occur and submit a statement signed by both, agreeing on building and fixture condition prior to the commencement of the work.

G. Submit manufacturer's certification that HEPA vacuums, negative pressure ventilation units, and other local exhaust ventilation equipment conform to ANSI

29.2-79.

H. When rental equipment is to be used in remediation areas or to transport mold contaminated waste, a written notification concerning intended use of the rental equipment must be provided to the rental agency with a copy submitted to the

Owner.

During remediation activities:

A. Submit weekly job progress reports detailing remediation activities and progress.

B. Submit copies of all transport manifests, trip tickets and disposal receipts for all mold waste materials removed from the work area during the remediation process.

C. Post in the clean room area of the worker decontamination enclosure:

a. A list containing the names, addresses, and telephone numbers of the

Contractor, the Owner, the Assessment Professional, the testing laboratory and any other personnel who may be required to assist during remediation activities.

b. A logbook to record names of all personnel who enter the work area.

c. A copy of emergency procedures.

d. Telephone numbers of all emergency personnel and principals for this remediation project.

The project will not be considered completed until all submittals are received by the owner. This will affect payment for the project.

1.06 SITE SECURITY

A. The work area is to be restricted only to authorized, trained, and protected personnel.

These may include the Contractor's employees, employees of

Subcontractors, Owner employees and representatives, state and local inspectors and any other designated individuals.

B. Entry into the work area by unauthorized individuals shall be reported immediately to the Owner by the Contractor.

C. Access to the work area shall be through a single worker decontamination system.

All other means of access (doors, windows, hallways, etc.) shall be blocked or locked so as to prevent entry to or exit from the work area. The only exceptions for this rule are the waste pass out airlock which shall be sealed except during the removal of containerized mold waste from the work area, and emergency exits in case of fire or accident. Emergency exits shall not be locked from the inside;

however, they shall be sealed with polyethylene sheeting and tape until needed.

D. The Contractor shall have control of site security during remediation operations whenever possible, in order to protect work efforts and equipment.

E. Contractor will have Owner's assistance in notifying building occupants of impending activity and enforcement of restricted access by Owner's employees.

1.07 EMERGENY PLANNING

A. Emergency planning shall be developed prior to remediation initiation and agreed to by Contractor and Owner.

B. Emergency planning shall include considerations of fire, explosion, toxic atmospheres, electrical hazards, slips, trips and falls, confined spaces, and heat related injury. Written procedures shall be developed and employee training in procedures shall be provided.

C. Employees shall be trained in evacuation procedures in the event of workplace emergencies.

PART 2 – MATERIALS AND EQUIPMENT

2.01 MATERIALS

General:

A. Deliver all materials in the original packages, containers, or bundles bearing the name of the manufacturer and the brand name.

B. Store all materials subject to damage off the ground, away from wet or damp surfaces, and under cover sufficient enough to prevent damage or contamination.

C. Polyethylene sheeting for walls and stationary objects shall be a minimum of 4 mil thick. For floors and all other sheeting of at least 6 mil thickness shall be used in widths selected to minimize the frequency of joints.

D. Tape - Duct, glass fiber, or other type capable of sealing adjacent sheets of polyethylene and capable of sealing polyethylene to dissimilar finished or unfinished surfaces under both wet and dry conditions including the use of amended water.

E. polyethylene sheeting utilized for worker decontamination enclosure shall be opaque white or black in color.

F. Disposal bags shall be of 6 mil polyethylene.

G. Disposal drums shall be metal or fiberboard with locking ring tops.

2.02 EQUIPMENT

General:

A. A sufficient quantity of negative pressure ventilation units equipped with HEPA filtration shall be utilized to provide one workplace air change every 15 minutes or a static pressure within the work area of at least -0.02 inches of water column. These ventilation units must be commercially produced units and not self-manufactured.

Ventilation units to be exhausted outside. The Contractor shall furnish a copy of their calculations to obtain this air flow or static pressure if requested by the

Owner.

B. Air purifying respirators equipped with HEPA filters will be required. A sufficient supply of filters shall be available in the clean change area. This requirement may be modified by the assessment professional if air sampling results indicate the need for more protection.

C. Air purifying respirators with dual high efficiency (HEPA) filters may be utilized during work area preparation activities. Spectacle kits and eyeglasses must be provided for employees who wear glasses and who must wear full face piece respirators.

Respirators shall be provided that have been tested and approved by the National

Institute of Occupational Safety and Health for use in mold contaminated atmospheres.

D. Full body disposable protective clothing, including head, body and foot coverings

(unless using footwear as described in Section 2.02 (A)(6) consisting of material impenetrable by mold (Tyvek or equivalent) shall be provided to all workers in sizes adequate to accommodate movement without tearing.

E. Additional safety equipment (e.g., hard hats, eye protection, safety shoes meeting the applicable ANSI Standard, disposable PVC gloves) as necessary, shall be provided to all workers and authorized visitors.

F. Nonskid footwear shall be provided to all remediation workers. Disposable clothing shall be adequately sealed to the footwear to prevent body contamination.

G. A sufficient supply of disposable mops, rags and sponges for work area decontamination shall be available.

H. Mobile radios, telephones, etc. as required by the project will be provided by the contractor.

Removal/Cleaning Equipment:

A. Sufficient supply of scaffolds, ladders, lifts and hand tools shall be provided as needed.

B. Sprayers with pumps capable of providing a water stream or mist for dust control.

C. Rubber dustpans and rubber squeegees shall be provided for cleanup.

D. Brushes utilized for removing loose mold containing material shall have nylon or fiber bristles, not metal.

E. A sufficient supply of HEPA filtered vacuum systems shall be available during cleanup.

PART 3 – EXECUTION

3.01 PREPARATION

A. Post caution signs at any location and approaches to a location where airborne concentrations of mold may exceed ambient background levels. Additional signs may need to be posted following construction of workplace enclosure barriers.

B. Shut down and lock out electric power to all work areas as necessary if wet conditions warrant. Provide temporary power and lighting. Ensure safe installation

(including ground faulting) of temporary power sources and equipment by compliance with all applicable electrical code requirements and OSHA requirements for temporary electrical systems.

C. Shut down and lock out all heating, cooling and air conditioning system (HVAC) components that are in, supply or pass through the work area. Seal all intake and exhaust vents in the work area with tape and 6 mil polyethylene. Also seal any seams in system components that pass through the work area. Remove all HVAC system filters and place in labeled 6 mil polyethylene bags for staging and eventual disposal as mold contaminated waste.

D. Due to HVAC being offline during winter conditions, Contractor to provide temporary heat to maintain indoor temperature of 60 degrees Fahrenheit throughout building.

E. The Contractor shall provide sanitary facilities for remediation personnel outside of the enclosed work area and maintain them in a clean and sanitary condition throughout the Project.

F. Seal off all windows, doorways, elevator openings, corridor entrances, drains, ducts, grills, grates, diffusers, skylights, and any other openings between the work area and uncontaminated areas outside of the work area with 4 mil polyethylene sheeting and tape.

G. Barrier walls will be constructed of 4 mil polyethylene sheeting extending from the ceiling to floor.

3.02 WORKPLACE EXITS

Worker Decontamination Enclosure System:

A. Worker decontamination enclosure systems shall be provided at all locations where workers will enter or exit the work area.

B. Worker decontamination enclosure systems constructed at the work site shall utilize

6 mil opaque white or black polyethylene sheeting or other acceptable materials for privacy. Detailed descriptions of portable, prefabricated units, if used, must be submitted for the Owner's approval. Plans must include floor plan with dimensions, materials, size, thickness, plumbing, and electrical utilities.

C. The worker decontamination enclosure system shall consist of at least a clean room and an airlock.

D. Entry and exit from the decontamination enclosure system chamber shall be through curtained doorways consisting of two sheets of overlapping polyethylene sheeting.

One sheet shall be secured at the top and left side, the other sheet at the top and right side. Both sheets shall have weights attached to the bottom to ensure that they hang straight and maintain a seal over the doorway when not in use.

E. The clean room shall be sized to adequately accommodate the work crew. Benches shall be provided as well as hooks for hanging up street clothes. Shelves for storing respirators shall also be provided in this area. Clean work clothes: clean disposable clothing, replacement filters for respirators, towels, and other necessary items shall be provided in adequate supply in the clean room. A location for postings shall also be provided in this area. Whenever possible, a lockable door shall be used to permit access into the clean room from outside the work area. Lighting, heat, and electricity shall be provided as necessary for comfort. This space shall not be used for storage of tools, equipment or materials, or as an office space.

Waste Container Pass Out Airlock:

A. The waste container pass out airlock shall be the same as the exit entry airlock.

Emergency Exits:

A. Emergency exits shall be established and clearly marked with duct tape arrows or other effective designations to permit easy identification from anywhere within the work area. They shall be secured to prevent access from uncontaminated areas and still permit emergency exiting. These exits shall be properly sealed with polyethylene sheeting which can be cut to permit egress if needed. These exits may be the worker decontamination enclosure, the waste pass out airlock and/or other alternative exits satisfactory to fire officials.

3.03 ISOLATION OF THE WORKPLACE

Maintenance of Enclosure Systems:

A. Following completion of the construction of all polyethylene barriers and decontamination system enclosures, allow overnight settling to ensure that barriers will remain intact and secured to walls and fixtures before beginning actual remediation activities.

B. All polyethylene barriers inside the workplace, in the worker decontamination enclosure system, in the waste container pass out airlock and at partitions constructed to isolate the work area from occupied areas shall be inspected at least twice daily, once prior to the start of each day's remediation activities. Document inspections and observations in the daily Project log.

C. Damage and defects in the enclosure system are to be repaired immediately upon discovery.

D. Negative pressure to be monitored with a continuous reading device. A record of this shall be furnished to the Owner. Use smoke tubes to test the effectiveness of the barrier system when directed by the Owner.

E. At any time during the remediation activities after barriers have been erected, if visible material is observed outside of the work area or if damage occurs to barriers, work shall immediately stop, repairs be made to barriers, and debris/residue cleaned up using appropriate HEPA vacuuming and wet mopping procedures.

F. Install and initiate operation of negative pressure ventilation equipment as needed to provide one air change in the work area every 15 minutes or produce a static pressure of -0.02 inches of water column. (See Section 2.02 (A)) Openings made in the enclosure system to accommodate these units shall be made airtight with tape and/or caulking as needed. If more than one unit is installed, they should be turned on one at a time, checking the integrity of wall barriers for secure attachment and the need for additional reinforcement. Ensure that adequate power supply is available to satisfy the requirements of the ventilating Units. Negative pressure ventilation units shall be exhausted to the outside of the building whenever feasible. Additional negative pressure ventilation units may be exhausted inside the work area to provide continuous air cleaning. They shall not be exhausted into occupied areas of the building. Twelve-inch extension ducting shall be used to reach from the work area to the outside when required. Careful installation, air monitoring and daily inspections shall be done to ensure that the ducting does not release fibers into uncontaminated building areas.

G. Once constructed and reinforced as necessary, with negative pressure ventilation units in operation as required, test enclosure for leakage utilizing smoke tubes.

Repair or reconstruct as needed.

3.04 WORKPLACE ENTRY AND EXIT PROCEDURES

Personnel Entry and Exit:

A. All workers and authorized personnel shall enter the work area through the worker decontamination enclosure system. Workers shall not eat, chew, or smoke once they have entered the work area. Eating may take place just outside the clean room.

Smoking, at any time during the project, is prohibited on the Central Iowa VA Des

Moines Campus.

B. All personnel, before entering the work area, shall read and be familiar with all posted regulations, personal protection requirements (including workplace entry and exit procedures) and emergency procedures. A sign off sheet shall be used to acknowledge that these procedures have been reviewed and understood by all personnel prior to entry.

C. All personnel shall proceed first to the clean room and appropriately don respiratory protection and launderable and/or disposable coveralls, head covering, and foot covering. Hard hats, eye protection, and gloves shall also be utilized if required.

Clean respirators and protective clothing shall be provided and utilized by each person for each separate entry into the work area.

D. Personnel wearing designated personal protective equipment shall proceed from the clean room through the airlock into the main work area.

E. Before leaving the work area all personnel shall remove gross contamination from the outside of respirators and the outer protective clothing by brushing and/or wet wiping procedures. Each person shall clean bottoms of protective footwear just prior to entering the airlock.

F. Personnel shall proceed to the airlock where they remove the outer protective equipment except respirators. Deposit disposable and/or launderable clothing back into the work area into appropriately labeled containers for disposal and/or laundering.

G. Reusable, contaminated footwear shall be stored in the airlock when not in use in the work area. Upon completion of remediation, it shall be disposed of as mold contaminated waste. Rubber boots may be decontaminated at the completion of the remediation project for reuse.

H. Still wearing respirators, personnel shall proceed to the clean room, clean the outside of the respirators and the exposed face area under running water prior to removal of respirator. Various types of respirators will require slight modification of these procedures.

I. Don clean disposable and/or launderable clothing if there will be later reentry into the work area or street clothes if it is the end of the work shift.

J. These procedures shall be posted in the clean room and equipment room.

Waste Container Pass Out Procedures:

A. Mold contaminated waste that has been containerized shall be transported out of the work area through the waste container pass out airlock or through the worker decontamination enclosure if a separate airlock has not been construction.

B. Waste pass out procedures shall utilize two teams of workers, an "inside" team and an "outside" team.

C. The inside team wearing appropriate protective clothing and respirators for inside the work area shall clean the outside, including bottoms, containers (bags, drums, or wrapped components) using HEPA vacuums and wet wiping techniques and transport them into the waste container pass out airlock.

D. The outside team, wearing appropriately assigned respirators, shall enter the airlock from the outside of the work area, remove them from the airlock to the outside. No worker from the outside team shall further enter the work area through this airlock.

The exit from this airlock shall be secured when not in use to prevent unauthorized entry.

3.05 PERSONNEL PROTECTION REQUIREMENTS

Training:

A. Prior to commencement of remediation activities, the Contractor shall have one person designated as a competent supervisor. This person shall be on-site at all times.

B. Special on-site training on equipment and procedures unique to this job site shall be performed as required.

C. Training in emergency response and evaluation procedures shall be provided.

Respiratory Protection:

A. All respiratory protection shall be provided to workers in accordance with the written respiratory protection program, which includes all items in OSHA 29 CFR 1910.134

(b)(1-11). This program shall be posted in the clean room of the worker decontamination enclosure system.

B. Workers shall be provided with personally issued, individually identified respirators.

C. Respirator types shall be utilized according to the following schedule:

a. FULL FACE Air purifying respirators with dual HEPA filters shall be utilized by workers during remediation operations.

b. FULL FACE Powered air purifying respirators equipped with HEPA filters may be used during remediation activities.

Fit Testing:

A. Workers must perform positive and negative air pressure fit tests each time a respirator is put on, wherever the respirator design so permits. Powered air purifying respirators shall be tested for adequate flow as specified by the manufacturer.

B. Workers shall be given a qualitative fit test in accordance with procedures detailed in the OSHA Lead Standard (29 CFR 1910.1025, Appendix D, Qualitative Fit Test

Protocols) for all respirators to be used on this remediation project. An appropriate administered quantitative fit test may be substituted for the qualitative fit test.

C. Documentation of adequate respirator fit must be provided to the Owner.

D. No one wearing a beard shall be permitted to don a respirator and enter the work area.

Protective Clothing:

A. Disposable clothing including head, foot, and full body protection shall be provided in sufficient quantities and adequate sizes for all workers and authorized visitors.

B. Launderable clothing, if required, shall be provided in sufficient quantities and adequate sizes for all workers and authorized visitors.

C. Hard hats, protective eyewear, gloves, rubber boots, and/or other footwear shall be provided as required for workers and authorized visitors. Safety shoes may be required for some activities.

3.06 COMMENCEMENT OF WORK

A. Enclosure systems have been constructed and tested.

B. Negative pressure ventilation systems are functioning adequately.

C. All pre-remediation submissions, notifications, postings, and permits have been provided and are satisfactory to the Owner.

D. All equipment for remediation, cleanup, and disposal are on hand.

E. All worker training is completed.

F. Contractor receives written permission from the Owner to commence remediation.

3.07 REMOVAL/CLEANING PROCEDURES

Protection of Materials Not Being Removed:

A. Materials that are not being removed are to be protected from any damage that may occur during work. The acoustic ceiling tile suspension grid is to be cleaned yet remain in place and is not to be damaged during the removal of the tiles.

Level One:

A. Clean and isolate active work areas in accordance with Section 3.01.

B. Wet all mold containing materials with an approved biocide solution using equipment capable of providing a fine spray mist, to reduce airborne concentrations when the material is disturbed. Keep all removed material wet enough to prevent release until it can be containerized for disposal.

C. Removal and cleaning:

ALL acoustic ceiling tiles, ALL carpet throughout the entire building are to be removed and properly disposed of.

Non-Porous Materials - All non-porous surfaces are to be cleaned using a detergent solution or solution of contractor's choice that will re move mold. HEPA vacuums may be used along with the solution for cleaning.

All materials need to be dried. Examples of non-porous materials include:

• Metal

• Glass

• Hard plastics

• Plumbing fixtures

All HVAC diffusers are to be removed, thoroughly cleaned (as detailed above) and set aside per

Owner’s direction to be re-installed later.

Semi-Porous – (e.g. wood doors, unsealed concrete) All semi-porous surfaces are to be cleaned using a detergent solution or solution of contractor's choice that will remove mold. This solution must be approved by owner. HEPA vacuums may be used along with the solution for cleaning. All materials need to be dried. Examples of semi-porous materials include:

• Wood

• Concrete

Porous Materials - Remove all porous materials where visible mold growth or evidence of moisture is present. The materials should be removed, bagged and discarded.

Examples of porous materials include:

• Drywall

• Insulation of all types

• Carpet (all being removed, regardless of evidence)

• Acoustic ceiling tiles (all being removed, regardless of evidence)

D. Containers (6 mil polyethylene bags) shall be sealed when full. Bags shall not be overfilled. They should be securely sealed to prevent accidental opening and leakage by tying tops of bags in an overhead knot or by taping in gooseneck fashion. Do not seal bags with wire or cord. Bags shall be decontaminated on exterior surfaces by wet cleaning and HEPA vacuuming.

E. Large components removed intact may be wrapped in 2 layers of 6 mil Polyethylene sheeting secured with tape for transport to the landfill.

F. Mold containing waste with sharp edged components (e.g., nails, screws, metal lath, tin sheeting) will tear the polyethylene bags and sheet and shall be reinforces with extra bags or wrapping.

3.08 CLEANUP PROCEDURE

A. Remove and containerize all visible accumulations of mold containing material and mold contaminated debris utilizing rubber dust pans, rubber squeegees, HEPA vacuums, etc.

B. Remove all containerized waste from the work area and waste container pass out airlock.

C. Decontaminate all tools and equipment and remove at the appropriate time in the cleaning sequence.

D. Inspect the work area for visible residue. If any accumulation of residue is observed, it will be assumed to be mold and the work area must be re-cleaned.

E. The work area shall be cleaned until it in compliance with criteria agreed upon by the

Contractor and Owner prior to initiation of remediation activities.

F. Following the satisfactory completion of clearance criteria remaining barriers may be removed and properly disposed of. A final visual inspection by the Owner shall ensure that no contamination remains in the work area. Unsatisfactory conditions may require additional cleaning and air monitoring (see Section 3.11, Reestablishment of the Work Area).

3.09 CLEARANCE TESTING

A. Following the completion of cleanup operations, the Remediation Contractor shall notify the Owner (or Industrial Hygiene consultant selected by owner) when the building area is ready for clearance testing. Remediation Contractor will not be responsible for performing clearance testing. The Owner (via contracted Industrial

Hygienist) shall arrange for collecting samples.

3.10 DISPOSAL PROCEDURES

General:

A. As the work progresses, to prevent exceeding available storage capacity onsite, sealed and labeled containers of mold containing waste shall be removed and stored in the dumpster on-site until it is transported to the prearranged disposal location.

B. All Waste Shipment Records shall be delivered to the Owner. A recommended record keeping format utilizes the Waste Shipment Record (WSR) which includes the names and addresses of the Generator (Owner), Contractor, Transporter, and

Disposal Site, the estimated quantity of the mold waste and the type of containers used.

Transportation to the Landfill:

A. Once drums, bags and wrapped components have been removed from the work area, they shall be loaded into an enclosed truck or dumpster for transportation.

B. Any debris or residue observed on containers or surfaces outside of the work area resulting from cleanup or disposal activities shall be immediately cleaned up using

HEPA filtered vacuum equipment and/or wet methods as appropriate.

C. Large metal dumpsters are sometimes used for mold waste disposal. These should have doors or tops that can be closed and locked to prevent vandalism or other disturbance of the bagged mold debris and wind dispersion of mold fibers. Bags shall be placed, not thrown, into these containers to avoid splitting.

Disposal at the Landfill:

A. Upon reaching the landfill, trucks are to approach the dump location as closely as possible for unloading of the mold containing waste.

B. Bags, drums, and components shall be inspected as they are off loaded at the disposal site. Waste containers shall be placed on the ground at the disposal site, not pushed or thrown out of the trucks.

C. Following the removal of all containerized waste, the truck cargo area shall be decontaminated using HEPA vacuums and/or wet methods to meet the no visible residue criteria.

3.11 RE-ESTABLISHMENT OF THE WORK AREA AND SYSTEMS

A. Re-establishment of the work area shall only occur following the completion of cleanup procedures and after clearance criteria have been met and documented to the satisfaction of the Owner.

B. The Contractor and Owner shall visually inspect the work area for any remaining visible residue. Evidence of contamination will necessitate additional cleaning requirements in accordance with Section 3.07.

C. Following satisfactory clearance of the work area, remaining polyethylene barriers may be removed and disposed of as mold contaminated waste.

D. At the discretion of the Contractor, mandatory requirements for personal protective equipment may be waived following the removal of all barriers.

E. Re-secure mounted objects removed from their former positions during area preparation activities.

F. Relocate objects that were removed to temporary locations back to their original positions.

G. Reestablish HVAC, mechanical and electrical systems in proper working order.

Remove contaminated HVAC system filters and dispose of as mold contaminated waste. Decontaminate filter assembly using HEPA vacuums and wet cleaning techniques. Install new filters in HVAC systems. Dispose of old filters.

H. Repair all areas of damage that occurred because of remediation activities.

3.12 PERIOD OF PERFORMANCE

Upon notice to proceed, Contractor shall have 30 calendar days to complete the scope detailed in this document.

3.13 SECURTIY AND CONDUCT REQUIREMENTS

The contractor’s personnel, while on VA property, shall adhere to all requirements and regulations that govern the VA Health Care System and its property. Among all other requirements, the VA Health Care System and its property is now entirely smoke-free. No firearms or weapons are permitted on the premises.

The contractor shall be responsible for ensuring compliance by its employees with all VA procedures governing building access and security. The VA Representative will assist the contractor personnel in obtaining requisite identification badges to enter the facilities. All contractor personnel entering or performing work are subject to Federal background checks and fingerprinting to obtain required identification and badges.

Employees of the contractor and sub-contractors shall always conduct themselves in a professional manner while on VA property.

Physical or verbal misconduct may be grounds for removing employees from VA property, or grounds for arrest by the VA Police. Employees may be banned from VA property because of inappropriate or illegal behavior. The contractor shall not be entitled to any compensation from the Government for any costs resulting from employee misconduct (including, but not limited to, delays in contract completion) and may be held liable for costs incurred by the Government because of employee misconduct.

Tobacco and Vaping products are prohibited at the Des Moines VA Facility. Any person needing to use these products must do so off the VA property.

Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and

Handbooks as VA and VA personnel regarding information and information system security.

APPENDICES: See Section D

D.1 Remediation Floor Plan

D.2 Remediation Investigation Pictures

B.3 PRICE/COST SCHEDULE

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

146.00 HR __________________ __________________

Demolition Services

PRINCIPAL NAICS CODE: 562910 - Remediation Services PRODUCT/SERVICE CODE: F108 - Environmental Systems Protection - Environmental Remediation

38.00 HR __________________ __________________

Cleaning Services

PRINCIPAL NAICS CODE: 562910 - Remediation Services

0.00

Materials

PRINCIPAL NAICS CODE: 562910 - Remediation Services

0003AA

1.00 JB __________________ __________________

Materials- Demolition

PRINCIPAL NAICS CODE: 562910 - Remediation Services PRODUCT/SERVICE CODE: F108 - Environmental Systems Protection - Environmental Remediation MANUFACTURER PART NUMBER (MPN): Materials- Demolitio LOCAL STOCK NUMBER: Materials- Demolitio

0003AB

1.00 JB __________________ __________________

Materials- Cleaning

PRINCIPAL NAICS CODE: 562910 - Remediation Services

GRAND TOTAL __________________

SECTION C - CONTRACT CLAUSES

C.1 FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The

Government must exercise its post-acceptance rights—

(1) Within a reasonable time after the defect was discovered or should have been discovered;

and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims

Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the

Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the

Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the

Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by

Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the…

This is the start of the file's text. The full file is on GovTribe.