36C26123Q0535 0001.docx

DOCX document 26 KB Posted

Attached to
J041--HVAC Chiller Maintenance Service
Solicitation number
36C26123Q0535
Issued by

About this file

This document is an amendment to a solicitation for HVAC chiller maintenance services for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21. The amendment provides responses to offeror questions regarding the scope of work. It clarifies that the inspection of 39 chillers located across three VA facilities and development of a deficiency list must be submitted within 30 days of award, with corrective action scheduling to follow. Completion of the inspection and list within 90 days of award would be acceptable. Pricing for additional labor hours beyond the scope of the contract is to match rates in the contract. The requirement is new and there is no incumbent contract. Annual maintenance was last performed over 12 months ago on all equipment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 04/20/2023 640-23-1-5051-0006 none Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Central California Health Care System 855 M Street, Suite 1020 Fresno CA 93721 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Central California Health Care System 855 M Street, Suite 1020 Fresno CA 93721 To all Offerors/Bidders

36C26123Q0535 04-20-2023

X x x

The purpose of the Amendment is to post RFI questions and answers responses.

Rico Johnson Contracting Officer Questions and Answers 36C26123Q0535

Questions:

RFI 1. Page 8 of 74, 9.1, states that, “Immediately after contract award and no later than 30-days thereafter, the Contractor and the Government shall conduct a thorough inspection of the inventory (as detailed in Attachment A) and develop a list of existing deficiencies and required corrective actions”. This contract encompasses three separate VA locations and a total of 39 separate chillers. Please clarify if the VA means inspection and development of a list of existing deficiencies must begin within 30-days or that it must be completed within 30-days.

RFI 2. If the VA means inspection and development of a list of existing deficiencies shall be completed within 30-days, could the VA extend this period to 90 days after award?

RFI 3. If the VA did means inspection and development of a list of existing deficiencies shall begin within 30-days of award, how long will contractor have to complete this process?

RFI 4. Page 10 of 74, states, “The Contractor shall price labor hours within the price quoted in CLIN 1 in Section B, SUPPLIES OR SERVICES AND PRICES”. We do not see where contractor is to price labor hours, could the VA clarify where contractor is to provide this pricing?

RFI 5. Is this a new requirement?

RFI 6. If this is not a new requirement, please provide current contract number/information.

RFI 7. When were annuals last performed on all equipment?

Answers:

RFI 1: 30 days to submit a deficiency report within the 1st 30 days and corrective schedule following acceptance of proposed repairs.

RFI 2: 90 days for survey and repairs proposal submission is acceptable.

RFI 3: Repairs scope timeline is not defined, scope and length is dependent on findings and subject to acceptance of proposal. The VA wishes to correct issues in a timely fashion but with reasonable amounts per industry standards.

RFI 4: Labor pricing for additional services shall be the same as those quoted for the other services within this contract.

RFI 5: Yes, this is a new procurement to obtain HVAC Chiller Maintenance RFI 6: no other contract for reference.

RFI 7: in excess of 12 months.