About this file
This is a Request for Quote (RFQ) for EHRM Infrastructure Upgrades at the Major William Edward Adams Department of Veterans Affairs Clinic in Craig, Colorado. The solicitation is a total set-aside for certified Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a project magnitude between $25,000 and $100,000, using NAICS code 541330 with a small business size standard of $45 million. The project involves three primary work components: installing a new HVAC system with ductless mini-split systems, implementing physical security improvements including a continuous security hinge and card reader, and supporting telecommunication updates.
Key dates include a non-mandatory site visit on August 15, 2025, at 11:00 AM Mountain Time, with all questions due by August 20, 2025, at 11:00 AM MT. The solicitation closes on August 27, 2025, at 11:00 AM MT. The contract period of performance is 90 days after Notice to Proceed, with work to be conducted during normal business hours (Monday through Friday). Offerors must be verified and listed in the SBA certification database, have an Experience Modification Rate of 1.0 or less, and submit past performance information on two relevant federal, state, local government, or private contracts completed within the past five years. Proposals must include pricing, a signed LOS certification, and potentially a bid bond if over $150,000.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25925Q0700 0003.pdf | ||
| Sign-In Sheet Pre-bid Site Visit Craig EHRM 8-21-2025.pdf | ||
| S04 - Site Visit Meeting Doc.docx | DOCX document | |
| 36C25925Q0700 0002 EHRM Infrastructure Upgrades.pdf | ||
| 36C25925Q0700 0001.pdf | ||
| S02 Self-Performed and Subcontracted Worksheet.docx | DOCX document | |
| CRAIG DWGs.pdf | ||
| CRAIG Specs.pdf | ||
| CO2025001 07252025.pdf | ||
| ICRA.pdf | ||
| S22 - 852.219-75 LOS Certification.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25925Q0700
X
575-21-705GB
36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
Frankie Basham 918.577.3923
The contractor shall furnish all labor, equipment, materials, and supervision to complete the EHRM Infrastructure Upgrades at Major William Edward Adam Clinic, 1111 W. Victory Way, Centennial Mall, Suite 116, Craig, CO, 81625.
Important Notice: Apparent successful offerors must apply for and receive verification from the Small Business Administration (SBA) through the SBA certification databasevia 13 CFR Part 128, VAAR 819.7011, and VAAR 819.7003 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the SBA certification database at the time of offer submission. Failure to be both VERIFIED by SBA and VISIBLE on the SBA certification database at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the SBA and submit the required documents to obtain verification of their SDVOSB status if they have not already done so.
In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to close of solicitation.
Project magnitude: between $25,000 and $100,000. The NAICS code is 541330 - Small Business size standard is $45 M.
A non-mandatory site visit shall be on August 15, 2025, at 11:00 A.M. Mountain Time (MT). Contractors are asked to assemble at the main entrance.
All questions in relation to this solicitation must be submitted in writing via e-mail to frances.basham@va.gov and received no later than August 20, 2025, at 11:00 A.M. (MT).
Instructions, Conditions, and Notices to Offerors. All submitted proposals must be received in email by the closing date and time. This solicitation closes August 27, 2025 at 11:00 A.M. MT.
To avoid proposal rejection, proposal packages shall include the following: pricing, signed VAAR 852.219-75 LOS certification, and bid bond (if >$150,000). Proposals from non-verified SDVOSB contractors will also be rejected.
Offers received in any other format will result in the offeror's proposal not receiving further consideration.
The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
10 90
X X 52.211-10
X
0 11:00 CDT
08-27-2025
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
A.3 STATEMENT OF WORK (SOW)
A.4 PRICE/COST SCHEDULE
ITEM INFORMATION
A.5 DELIVERY SCHEDULE
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
2.5 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025)
(DEVIATION FEB 2025)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
GENERAL CONDITIONS
4.1 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JAN 2025) ALTERNATE I (MAR 2020)
4.2 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
4.3 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.4 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.5 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
4.6 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN
2020)
4.7 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)
(DEVIATION)
4.8 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.9 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
4.10 WAGE DETERMINATION
4.11 List of Attachments
A.3 STATEMENT OF WORK (SOW)
SCOPE OF WORK
EHRM Craig VA CBOC
575-21-705GB
VA Western Colorado Healthcare System Grand Junction, Colorado
The Department of Veterans Affairs, Veterans Health Administration (VHA), hereafter referred to as the “VA”, “VAMC”, or the “Government”, has a requirement for EHRM Infrastructure Upgrades at the Major William Edward Adams Department of Veterans Affairs Clinic, Craig, CO.
SCOPE OF WORK:
The VA has directed the completion of a limited number of improvements at the Craig Clinic, as detailed in the attached IGCE:
1. New HVAC System:
a. Install a dedicated DX cooling system, consisting of ductless mini-split systems wall-mounted above the door.
b. Indoor unit cooling capacity will be determined by the number of data racks, estimated at 9,000 BTU (3/4 tons) per room.
c. Each indoor unit will use the manufacturer's programmable thermostat for control.
d. Condensing units will be installed on the roof, with ASTM B280 Type ACR copper refrigerant piping and ASTM B88 Type L copper condensate piping, both insulated with elastomeric insulation.
e. Provision of a small condensate pump where required by discharge location;
gravity drainage will be utilized where possible.
f. Reroute any existing ductwork or piping through the telecommunications room (TR), room 012 as needed.
g. Refer to the attached cut sheets for the basis of design.
2. Physical Security Improvements:
a. Install a continuous security hinge and card reader with dual authentication, networked back to the Grand Junction facility.
b. Specific components are detailed in the attached drawings.
3. Support for EHRM Telecommunication Updates:
a. Coordinate power needs for the new HVAC units.
b. Provide electrical design elements for Craig Clinic buildings.
c. Replace existing UPS in the telecommunications rack.
General Requirements
VHA Master Specification Table of Contents:
ICRA Requirements for Craig Clinic Alterations:
1. Craig Clinic will be occupied during performance of work, but immediate areas of alterations will be vacated. Therefore, the following ICRA requirements apply:
a. All work personnel shall have clean clothing and shoes at all times when in the facility. Hard hats and high visibility clothing shall also be clean.
b. All equipment, materials, waste carts, and transfer carts shall be wiped clean prior to entry into the hospital and shall remain clean at all times when moving throughout the hospital.
c. Clean interior and exterior surfaces of HEPA-filtered vacuum. Conduct a detailed inspection to ensure clean, intact filters and proper seating of the HEPA filter on the filter gasket.
d. Clean interior and exterior surfaces of HEPA-filtered portable air scrubber.
Conduct a detailed inspection to ensure clean, intact filters and proper seating of the HEPA filter on the filter gasket.
e. Have available a HEPA-filtered vacuum for vacuuming dust and debris from equipment, materials, carts, and personnel clothing.
f. Have available clean cloths and spray disinfectant or wipes for cleaning all equipment, materials, and carts.
g. Close door to work area – the room will serve as containment.
h. Remove all equipment and materials from the room prior to beginning work.
i. Place HEPA-filtered portable air scrubber inside the work area.
j. Securely seal and block off supply air diffusers.
k. Securely seal and block off return air grills.
l. Securely seal and block off exhaust air grills.
m. Place tacky mat at the corridor entrance into the work area. Change the tacky mat as needed so it remains effective at capturing dust and debris.
n. Place tacky mat within the work area at the exit to the adjacent corridor. Change the tacky mat as needed so it remains effective at capturing dust and debris.
o. Capture dust during drilling by placing the nozzle of a HEPA-filtered vacuum at the drill point.
p. Capture dust during cutting by placing the nozzle of a HEPA-filtered vacuum at the cut point.
q. Maintain a clean work area by vacuuming all affected surfaces with HEPA-filtered vacuums.
r. Contain construction waste before transport in tightly covered containers. All trash carts shall be wiped clean (on all surfaces and wheels) prior to exiting the work area and again prior to re-entry into the hospital after dumping at the loading dock. This may necessitate placing cleaning materials at the loading dock entrance.
s. Cover transport receptacles or carts; tape covering down unless solid lid. All covers shall be clean and not stored on the floor when not in use; the covers shall be stored in a clean container or bag.
t. Remove or isolate HVAC system in areas where work is being done to prevent contamination of the duct system.
u. Install plastic sheeting above the ceiling up to the ceiling deck.
v. Seal holes, pipes, conduits, and all other penetrations through the containment barrier.
w. Place HEPA-filtered portable air scrubber inside the work area.
x. Do not begin construction work until barriers and other infection controls are inspected by the Infection Preventionist or Facilities representative.
y. Contain construction waste before transport in tightly covered containers. All trash carts shall be wiped clean (all surfaces and wheels) prior to exiting the work area and again prior to re-entry into the hospital after dumping at the loading dock. This may necessitate placement of cleaning materials at the loading dock entrance.
z. Cover transport receptacles or carts; tape covering down unless solid lid. All covers shall be clean and not stored on the floor when not in use; the covers shall be stored in a clean container or bag.
aa. Maintain a clean work area by vacuuming with HEPA-filtered vacuums.
bb. Maintain a clean work area. Use dust suppressant when broom sweeping.
cc. Workers are required to vacuum their clothes with a HEPA vacuum while in the anteroom and before exiting the worksite.
dd. Maintain a clean work area. Use dust suppressant when broom sweeping.
ee. Workers are required to vacuum their clothes with a HEPA vacuum while in the anteroom and before exiting the worksite.
ff. Access above the ceiling using a containment cube that has been cleaned on all interior and exterior surfaces.
gg. Prior to exiting the cube, thoroughly clean (vacuum and wipe with disinfectant) the cube interior and all materials and equipment within the cube.
hh. All work personnel shall thoroughly vacuum clothing and shoes prior to exiting the containment cube. Hard hats and high visibility clothing shall also be clean.
ii. Contain construction waste in tightly covered cleanable containers.
jj. Use a cutout box when cutting drywall and/or installing electrical box and/or pulling cable into the box.
kk. Contain construction waste in tightly covered cleanable containers.
ll. At the completion of work, but prior to removal of the barriers, thoroughly wipe walls and floor with disinfectant.
mm. Perform a construction area clean by wiping all work surfaces with disinfectant.
nn. Perform a construction area clean by wet mopping.
oo. Perform a construction area clean by vacuuming the floor, walls, and other affected surfaces at the completion of work using a HEPA-filtered vacuum.
pp. Remove isolation of HVAC system in areas where work was performed.
qq. Perform test, balance, and adjustment of the HVAC system as required by
Facilities Management.
rr. Do not remove barriers from the work area until the completed project is inspected by the Infection Preventionist, Facilities Director, or Safety.
ss. Remove barrier materials carefully to minimize the spreading of dirt and debris associated with construction.
Delivery Period
The project must be completed within 90 days from the Notice to Proceed.
Hours of Work
- Work shall be conducted during normal CBOC business hours (Monday through Friday, excluding federal holidays).
- To minimize clinic impact, work after regular hours (4 PM to midnight MST) is allowed with COR approval.
- Weekend and federal holiday work require a 10-day advanced written notification to the COR.
- Inspections necessitate prior five-day notification to the COR.
Submittals
The contractor must submit the following:
1. Submittal log of all anticipated submittals.
2. Updated RFI log with all responses at each progress review meeting.
3. Comprehensive work schedule, including sequencing, durations, and critical path, for approval within 45 days of Notice to Proceed.
4. A 4-week look-ahead schedule at every construction progress meeting.
5. Approved schedule of values before the first invoice, with updates transmitted with each invoice.
6. Environmental compliance and monitoring plans.
7. Site-Specific Safety Plan (accident prevention plan) submitted 15 calendar days before the preconstruction meeting.
8. Activity Hazard Analysis Plan submitted 15 calendar days before each construction phase.
9. Demolition and staging plans.
10. Interim Life Safety Measures (ILSM) for related construction procedures.
11. Employee details, OSHA training proofs, and TB test results provided 15 days before site arrival.
12. Name and proof of 30-hour OSHA certification for designated site personnel provided at the preconstruction meeting.
13. Updated utility as-builts in CAD format upon project completion, reviewed at every construction progress meeting.
Federal Legal Holidays:
The following Federal legal holidays are observed by this facility:
New Year’s Day January 1 Martin Luther King’s Birthday Third Monday in January President’s Day Third Monday in February Memorial Day Last Monday in May Juneteenth Third Wednesday of June
Independence Day July 4 Labor Day First Monday in September Columbus Day Second Monday in November Veteran’s Day November 11 Thanksgiving Day Fourth Thursday in November Christmas Day December 25
Period of Performance: 90 Days After NTP
A.4 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBE
R
DESCRIPTION OF
SUPPLIES/SERVIC
ES
QUANTIT
Y
UNI
T UNIT PRICE AMOUNT
1.00 JB ________________
EHRM Infrastructure Upgrades at Craig Community Based Outpatient Clinic (CBOC) according to the SOW.
Contract Period: Base POP Begin: 09-01-2025 POP End: 11-30-2025 PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries
GRAND TOTAL ________________
A.5 DELIVERY SCHEDULE
ITEM
NUMBER SHIPPING INFORMATION QUANTITY
DELIVERY
DATE
1.00
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR QUOTE
This is a Request for Quote in accordance with FAR Part 13. Potential offerors must follow all instructions to be compliant with the solicitation.
It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.
The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4. Certified SDVOSB/VOSB listed in the SBA certification database at https://veterans.certify.sba.gov/ (see 13 CFR 128). A joint venture may be considered eligible if it meets the requirements in 13 CFR part 128, and the managing joint venture partner makes the representations under VAAR 819.7003 paragraph (b). An offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed.
Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETCERT.
I.3A SITE VISIT
See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation.
I.4A SELECTION CRITERIA/QUOTE PREPARATION INSTRUCTIONS
Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures
Award will be made based on the following factors:
Factor 1 - Past Performance
Factor 2 - Price
Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous and best value for the Government.
Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size, and complexity. For purposes of this evaluation, a relevant project is further defined as completing construction modifications in a medical facility environment. Project shall have a minimum amount of $25,000.00 or more and completed within the past five years from the date of issuance of this RFQ. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the https://veterans.certify.sba.gov/ contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).
Completed PPQs should be submitted directly from your client via email to Frankie Basham at frances.basham@va.gov. If you have any questions, please contact Frankie Basham at frances.basham@va.gov. If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.
Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.
The Government also reserves the right to award to the lower priced offeror with lower past performance rating if the Contracting Officer (CO) determines the price difference does not merit awarding to the higher priced offeror. In that event, the CO shall make an integrated assessment best value award decision.
Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF 1442
Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
• Comparison of quoted prices received in response to the RFQ
• Comparison of quoted prices with the IGCE.
• Comparison of quoted prices with available historical information.
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
Special Standard of Responsibility
Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
1. OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.
2. Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0. If an offeror’s EMR is above 1.0, the offeror must submit a written explanation of the EMR from its insurance carrier on the insurance carrier’s letterhead, mailto:frances.basham@va.gov describing the reasons for the EMR and the anticipated date the EMR may be reduced to 1.0 or below.
Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Between $25,000 and $100,000
I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.
I.3B METRIC PRODUCTS:
Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.
If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
I.4B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the SF 1442, Solicitation, Offer and Award.
I.5B QUOTE REQUIREMENTS
General – Both past performance information and price proposal shall be submitted in response to this solicitation. Quotes shall be submitted via email to frances.bashaam@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, one attachment for LOS certification, and one attachment for past performance information) not to exceed 15MB. Quote can be submitted in one email if 15MB or less. All proposals over $150,000.00 require a digital Bid Bond with wet signatures and surety seals, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the offer price. This shall be included with the submitted proposal.
Failure to furnish the required bid guarantee in the proper form and amount, by the solicitation due date/time, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. See FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Failure to submit in the format required and clearly address those factors may result in rejection of the offer.
Electronic copies of the quotes will be time/date stamped by Microsoft Outlook upon receipt of email.
Further details on electronic submission are outlined below.
Quotes shall be received by 11:00 AM (MT) on August 27,2025. There will be no public opening. Submit quotes to: frances.basham@va.gov.
Important Notice: Apparent successful offerors must apply for and receive verification from the Small Business Administration (SBA) through the SBA certification database via 13 CFR Part 128, VAAR 819.7011, and VAAR 819.7003 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the SBA certification database at the time of offer submission. Failure to be both VERIFIED by SBA and VISIBLE on the SBA certification database at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors mailto:frances.bashaam@va.gov are urged to contact the SBA and submit the required documents to obtain verification of their SDVOSB status if they have not already done so.
Or
Meet Federal Acquisition Regulation (FAR) class deviation regarding certification of Service- Disabled Veteran Owned Small Business concerns as per CAAC Letter 2024-02, effective January 1, 2024, until SAM.gov is updated to reflect the SBA’s certification or otherwise rescinded.
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals – Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications
– Commercial Products and Commercial Services. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications— Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
I.6B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER
Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.
In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.
Acceptable Electronic Formats (Software) for Submission of Offers
1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Print or scan images of spreadsheets are not acceptable. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF (purpose: contracting can open the PDF version and engineering can open AutoCAD files).
2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.
3. Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.
4. Please note that we can no longer accept .zip files due to increasing security concerns.
http://contracting.tacom.army.mil/acqinfo/ebidnotice.htm#macros#macros
5. E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.
a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, or Bid depending on the solicitation type.
b. Size: Maximum size of the e-mail message shall not exceed 15 megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.
c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents.
Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.
Each electronic offer must also include a signed and scanned SF 1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)
The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipients “inbox” is the official record of receipt.
Security Issues, Late Bids, Unreadable Offers
1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.
2. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.
3. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus, or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).
4. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet, and the spreadsheet saved in PDF format to ensure that your quote is readable.
5. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—
SECONDARY SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
http://contracting.tacom.army.mil/acqinfo/ebidnotice.htm#email#email
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I
(FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
August 15, 2025 at 11 AM (MT)
(c) Participants will meet at—
Main Entrance.
(End of Provision)
2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY
REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Provision)
2.5 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the provision.
(b) The use in this solicitation of any VAAR Acquisition Regulation (48 CFR Chapter FEDERAL ACQUISITION REGULATION (48 CFR Chapter 1)) provision with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.
(End of Provision)
FAR
Number
Title Date
52.204-7 SYSTEM FOR AWARD MANAGEMENT NOV 2024
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE
REPORTING
AUG 2020
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN
2025) (DEVIATION FEB 2025)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $45 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(xiv) [Reserved].
(xv) [Reserved].
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of biobased products in USDA-designated product categories; or include the clause at 52.223-2, Reporting of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) [Reserved].
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate.
(Basic, Alternates II and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $50,000, the basic provision applies.
(B) If the acquisition value is $50,000 or more but is less than $100,000, the provision with its Alternate II applies.
(C) If the acquisition value is $100,000 or more but is less than $102,280, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan— Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[X] (i) 52.204-17, Ownership or Control of Offeror.
[X] (ii) 52.204-20, Predecessor of Offeror.
[] (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[] (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.
[] (v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.
[] (vi) 52.227-6, Royalty Information.
[] (A) Basic.
[] (B) Alternate I.
[] (vii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .