S05 - RFIs and Responses2.pdf
PDF 260 KB Posted
- Attached to
- Z2DA--Booster Pumps Federal contract opportunity
- Solicitation number
- 36C25923R0081
About this file
This statement of work document outlines requirements for a construction services project to replace booster pumps at the Salt Lake City Veterans Affairs Medical Center. The project involves removing six existing six-inch butterfly valves, three pumps, three motors, and other components. New components to be provided and installed include six stainless steel triple offset butterfly valves, three 1,000 GPM pumps rated for 100 foot head pressure, three motors, piping, valves, and other accessories. The contractor must schedule work to be completed within a 48-hour window to minimize water pressure disruptions. The selection is for a 90-day period of performance beginning immediately upon notice to proceed. The selected contractor must adhere to extensive requirements for safety, scheduling, permitting, submittals, training, project management, and coordination with the VA during construction.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25923R0081 0002.docx | DOCX document | |
| S04 - Site Visit 6-5-2023 Sign In Sheet.pdf | ||
| 36C25923R0081 0001.docx | DOCX document | |
| S05 - RFIs and Responses.pdf | ||
| S04 - Site Visit Meeting Doc_Booster Pumps.pdf | ||
| 36C25923R0081_1.docx | DOCX document | |
| S02 - Specifications.pdf | ||
| S02 - Drawings (Emergency Booster Pumps Upgrade).pdf | ||
| S22 - Blank LOS Cert.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: 660-23-330 Replace Booster Pumps Salt Lake City VAMC RFI’s
Solicitation: 36C25923R0081
1. Is the schedule of the pipe 40 or 10 or 40S? The drawings show 40, but the spec’s show 10 for fittings:
A: Schedule 40 pipe.
2. The spec’s call out SS 312 for pipe and ss 316 for fittings. Is this intentional? Are they both 316?
A: Both SS 316.
3. Do the six 6” truly need to be replaced? This will require an outage or outages.
A: Yes. The VA Facility Plumber(s) will isolate the existing water valves before and after the booster pump vault and bypass the booster pumps so that the campus still receives water from the city. Yes, there will be a temporary outage of the booster pumps.
4. Are block valves available above stream and downstream of the system?
A: Isolation valves are available above stream and downstream of the booster pump vault.
5. Where are the located (reference to question 4)?
A: They are located within the vicinity of the booster pumps vault. The contractor should coordinate the isolation of the booster pumps with the COR. The COR will then contact the VA Facility Plumbers to operate existing valves and isolate.
6. Where can water be disposed when the system is drained for outages?
A: There is a sump pump in the bottom corner of the booster pump vault.
7. Can the existing pump and pipe supports be re-used? Any modifications required?
A: The existing motor supports should be re-used. The contractor should procure a motor/pump setup that fits the existing supports and bolt pattern. If the contractor cannot find a matching motor/frame size & bolt pattern, then the contractor would need to modify the existing supports.