Attachment C Specifications Addendum RFI 1 554-23-112 Install Infrastructure SPS.pdf
PDF 264 KB Posted
- Attached to
- Z2DA--Install Infrastructure to Support SPS Federal contract opportunity
- Solicitation number
- 36C25923Q0020
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S04 - Site Visit Meeting Doc.pdf | ||
| S04 - 554-23-112 Site Walk Attendance.pdf | ||
| Attachment B Photos new VA owned equipment.pdf | ||
| Attachment A InnoWave Pro Equipment Specs.pdf | ||
| S05 - Amendment Sections.pdf | ||
| 36C25923Q0020 0001.docx | DOCX document | |
| S02 - Drawings proj 554-23-112 Install Infrastructure SPS.pdf | ||
| 36C25923Q0020_1.docx | DOCX document | |
| S02 - Specifications proj 554-23-112 Install Infrastructure SPS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI 1 ADDENDUM
CONSTRUCTION SPECIFICATIONS
PROJECT
554- 23-112
Install Infrastructure to Support SPS
Rocky Mountain Regional
Veteran’s Administration Medical Center
1700 North Wheeling Street
Aurora, Colorado 80045
January 18, 2023
11-10-21
00 01 10-1
RFI 1 Addendum
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components 01-21
DIVISION 26 – ELECTRICAL
26 22 00 Low-Voltage Transformers 01-18 26 24 16 Panelboards 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17
01-01-21
13 05 41 - 1
SECTION 13 05 41
SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS
PART 1 - GENERAL
1.1 DESCRIPTION:
A. Provide seismic restraint in accordance with the requirements of the drawings, VA Handbook H-18-8: Seismic Design Requirements and this specification in order to maintain the integrity of non-structural components and equipment of the building so that they remain safe and functional in case of seismic event.
B. The design of seismic restraints of non-structural components to resist seismic load shall be based on Seismic Design parameters indicated below in accordance with VA H-18-8 in conjunction with ASCE 7 and ASCE
41, as specified in H-18-8 Section 4.0, for existing building retrofit projects. Specific requirements for Critical and Essential facilities are covered in Section 4.0 of H-18-8, including applying Ip = 1.5 for all nonstructural components in Critical facilities.
1. International Building Code
2. American Society of Civil Engineers Seismic Evaluation and Retrofit of Existing Buildings ASCE 41-17.
3. American Society of Civil Engineers, Minimum Design Loads and
Associated Criteria for Buildings and Other Structures ASCE 7-16
C. Definitions: Non-structural building components are components or systems that are not part of the building’s structural system whether inside or outside, above or below grade. Non-structural components of buildings include but are not limited to (Refer to VA H-18-8, ASCE 7 and ASCE 41 for additional examples):
1. Architectural Elements: Facades that are not part of the structural system and its shear resistant elements; cornices and other architectural projections and parapets that do not function structurally; glazing; nonbearing partitions; suspended ceilings;
stairs isolated from the basic structure; cabinets; bookshelves;
medical equipment; and storage racks, etc.
2. Electrical Elements: Power and lighting systems; substations;
switchgear and switchboards; auxiliary engine-generator sets;
transfer switches; motor control centers; motor generators; selector and controller panels; fire protection and alarm systems; special life support systems; and telephone and communication systems, etc.
13 05 41 - 2
3. Mechanical Elements: Heating, ventilating, and air-conditioning systems; medical gas systems; plumbing systems; sprinkler systems;
pneumatic systems; boiler/chiller/utility plant/other equipment and components, etc.
4. Transportation Elements: Mechanical, electrical and structural elements for transport systems, i.e., elevators and dumbwaiters, including hoisting equipment and counterweights.
1.2 RELATED WORK:
Related specifications include but are not limited to those shown below.
Coordinate all work with the applicable specification for that work.
A. Cast-In-Place Concrete: (NOT USED)
B. Structural Steel Framing: (NOT USED)
C. Metal Fabrication: Section 05 50 00, METAL FABRICATIONS
1.3 QUALITY CONTROL:
A. Shop-Drawing Preparation:
1. Non-structural seismic restraint systems shop drawings and delegated design calculations shall be prepared by a professional structural engineer with a minimum of 5 years’ experience in the design and detailing of seismic force restraints. The professional structural engineer shall be registered in the state where the project is located and submit qualifications with list of projects illustrating compliance with the experience requirement of this section.
2. Submit design tables and information used for the design-force levels, stamped and signed by a professional structural engineer registered in the State where project is located.
B. Coordination:
1. Do not install seismic restraints until seismic restraint submittals are approved by the Contracting Officers Representative (COR).
2. Coordinate trapezes or other multi-pipe hanger systems prior to submission of shop drawings for review.
C. Seismic Certification:
In structures assigned to Seismic Design Category C, D, E, or F, permanent equipment and components are to have Special Seismic
Certification in accordance with requirements of section 13.2.2 of ASCE
7, including those required in existing buildings within Section
13.7.1.3.3, 13.7.7.3.3 and 13.7.8.3.3 of ASCE 41, except for equipment and components that are considered inherently rugged as listed in
Section 4.2.2 of VA H-18-8, and shall comply with section 13.2.6 of
ASCE 7.
13 05 41 - 3
1.4 SUBMITTALS:
A. Submit a complete and coordinated set of bracing and signed and sealed anchorage drawings and calculations for all non-structural elements requiring seismic restraint by the delegated professional structural engineer mentioned in Section 1.3.A.1 for review prior to installation including:
1. Description, layout, and location of all items to be anchored or braced with anchorage or brace points noted and dimensioned.
2. Details of all anchorage and bracing at large scale with all members, parts brackets shown, together with all connections, bolts, welds etc. clearly identified and specified. Details shall be coordinated with all project conditions and trades prior to shop drawing submission for review.
3. Complete calculations including but not limited to seismic design criteria, computer model input and output, seismic design forces and capacities, design tables and information used for all proprietary design elements such as post installed anchors, stamped and signed by a professional structural engineer specified in section 1.3 A.1.
4. For all post installed anchorages submit the appropriate
International Code Council Engineering Service (ICC-ES) evaluation reports, California’s Office of Statewide Health Planning and
Development(OSHPD) pre-approvals, or lab test reports verifying compliance with OSHPD Interpretation of Regulations 28-6.
5. Delegated professional structural engineer qualifications.
B. Submit for review prior to installation, the following for seismic protection of piping in addition to items noted in Section 1.4.A:
1. Single-line piping diagrams on a floor-by-floor basis. Show all suspended piping for a given floor on the same plain.
2. Type of pipe (Copper, steel, cast iron, insulated, non-insulated, etc.).
3. Pipe contents.
4. Structural framing for the seismic and gravity support and the main superstructure for which the bracing and or anchorage is attached.
5. Location of all gravity load pipe supports and spacing requirements.
6. Numerical value of gravity load reactions.
7. Location of all seismic bracing.
8. Numerical value of applied seismic brace loads.
13 05 41 - 4
9. Type of connection (Vertical support, vertical support with seismic brace etc.).
10. Seismic brace reaction type (tension or compression): Details illustrating all support and bracing components, methods of connections, and specific anchors to be used.
C. Submit for review prior to installation, the following items for seismic protection of suspended ductwork and suspended electrical and communication cables, in addition to items noted in Section 1.4.A:
1. Details illustrating all support and bracing components, methods of connection, and specific anchors to be used.
2. Numerical value of applied gravity and seismic loads and seismic loads acting on support and bracing components.
3. Maximum spacing of hangers and bracing.
1.5 APPLICABLE PUBLICATIONS:
A. The Publications listed below (including amendments, addenda revisions, supplements, and errata) form a part of this specification to the extent referenced. The publications are referenced in text by basic designation only.
B. American Concrete Institute (ACI):
355.2-19................Qualification for Post-Installed Mechanical
Anchors in Concrete and Commentary
C. American Institute of Steel Construction (AISC):
Load and Resistance Factor Design, Volume 1, Second Edition
D. ASTM International (ASTM):
A36/A36M-19.............Standard Specification for Carbon Structural
Steel
A53/A53M-18.............Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and
Seamless
A307-14e1...............Standard Specifications for Carbon Steel Bolts, Studs, and Threaded Rod 60,000 PSI Tensile
Strength
A325-14.................Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum
Tensile Strength
A325M-14................Standard Specification for High-Strength Bolts for Structural Steel Joints [Metric]
13 05 41 - 5
A490-14a................Standard Specification for Heat-Treated Steel
Structural Bolts, 150 ksi Minimum Tensile
Strength
A490M-14a...............Standard Specification for High-Strength Steel
Bolts, Classes 10.9 and 10.9.3, for Structural
Steel Joints [Metric]
A500/A500M-18...........Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in
Rounds and Shapes
A501/A501M-14...........Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing
A615/A615M-20...........Standard Specification for Deformed and Plain
Carbon Steel Bars for Concrete Reinforcement
A992/A992M-11(2015).....Standard Specification for Steel for Structural
Shapes for Use in Building Framing
A996/A996M-16...........Standard Specification for Rail Steel and Axle
Steel Deformed Bars for Concrete Reinforcement
E488/E488M-18...........Standard Test Methods for Strength of Anchors in Concrete Elements
E. American Society of Civil Engineers
1. Minimum Design Loads and Associated Criteria for Buildings and Other
Structures (ASCE 7) Edition as indicated in section 1.1 B of this specification. Associated Criteria for Buildings and Other
Structures (ASCE 7): 7-16
F. International Building Code (IBC) Edition as indicated in Section 1.1 B of this specification.
G. VA Handbook H-18-8 Seismic Design Requirements, VA H-18-8, November
2019(REVISED MAY 1,2020)
H. National Uniform Seismic Installation Guidelines (NUSIG)
I. Sheet Metal and Air Conditioning Contractors National Association
J. (SMACNA): Seismic Restraint Manual - Guidelines for Mechanical Systems, 3RD EDITION 2008 (or most recent) and Addendum
1.6 REGULATORY REQUIREMENT:
A. IBC as shown in Section 1.1 B of this specification.
B. Exceptions: The omission of seismic restraints shall be allowed only in accordance with VA H-18-8, ASCE 7 and ASCE 41.
13 05 41 - 6
PART 2 - PRODUCTS
2.1 STEEL:
A. Structural Steel: ASTM A36, A36M, and A992.
B. Structural Tubing: ASTM A500, Grade B.
C. Structural Tubing: ASTM A501.
D. Steel Pipe: ASTM A53/A53M, Grade B.
E. Bolts & Nuts: ASTM A307, A325, A325M, A490, and A490M.
2.2 CAST-IN-PLACE CONCRETE: (NOT USED)
PART 3 - EXECUTION
3.1 CONSTRUCTION, GENERAL:
A. Provide equipment supports and anchoring devices to withstand the seismic design forces, so that when seismic design forces are applied, the equipment cannot displace, overturn, or become inoperable.
B. Provide anchorages in conformance with recommendations of the equipment manufacturer and as shown on approved shop drawings and calculations.
C. Construct seismic restraints and anchorage to allow for thermal expansion.
D. Testing Before Final Inspection:
1. Test 10-percent of anchors in masonry and concrete per ASTM E488, and ACI 355.2 to determine that they meet the required load capacity. If any anchor fails to meet the required load, test the next 20 consecutive anchors, which are required to have zero failure, before resuming the 10-percent testing frequency.
2. Before scheduling Final Inspection, submit a report on this testing indicating the number and location of testing, and what anchor-loads were obtained.
3. Construct seismic restraints and anchorages to not interfere with other trades or damage existing or in-situ elements of the constructed building.
3.2 EQUIPMENT RESTRAINT AND BRACING:
A. See drawings for equipment to be restrained or braced.
3.3 MECHANICAL DUCTWORK AND PIPING; BOILER PLANT STACKS AND BREACHING;
ELECTRICAL BUSWAYS, CONDUITS, AND CABLE TRAYS; AND TELECOMMUNICATION WIRES
AND CABLE TRAYS
A. Support and brace mechanical ductwork and piping; electrical busways, conduits, and cable trays; and telecommunication wires and cable trays including boiler plant stacks and breeching to resist directional forces (lateral, longitudinal and vertical).
13 05 41 - 7
B. Brace duct and breeching branches with a minimum of 1 brace per branch.
C. Provide supports and anchoring so that, upon application of seismic forces, piping remains fully connected as operable systems which will not displace sufficiently to damage adjacent or connecting equipment or building members.
D. Piping Connections: Provide flexible connections where pipes connect to equipment. Make the connections capable of accommodating relative differential movements between the pipe and equipment under conditions of earthquake shaking.
- - - E N D - - -
11-01-22
26 22 00 - 1
SECTION 26 22 00
LOW-VOLTAGE TRANSFORMERS
PART 1 – GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, connection, and testing of low-voltage dry-type general-purpose transformers, indicated as transformers in this section.
1.2 RELATED WORK
A. Section 03 30 00, CAST-IN-PLACE CONCRETE: Requirements for concrete equipment pads.
B. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS: Requirements for seismic restraint of nonstructural components.
C. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:
Requirements that apply to all sections of Division 26.
D. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:
Low-voltage conductors.
E. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path for possible ground fault currents.
F. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduit.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compliance with drawings and specifications.
b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, temperature rise, wiring and connection diagrams, plan, front, side, and rear elevations, accessories, and device nameplate data.
c. Certification from the manufacturer that representative transformers have been seismically tested to International
26 22 00 - 2
Building Code requirements. Certification shall be based upon simulated seismic forces on a shake table or by analytical methods, but not by experience data or other methods.//
2. Manuals:
a. Submit, simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets and wiring diagrams.
1) Schematic signal and control diagrams, with all terminals identified, matching terminal identification in the transformers.
2) Include information for testing, repair, troubleshooting, assembly, disassembly, and factory recommended/required periodic maintenance procedures and frequency.
b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.
3. Certifications: Two weeks prior to final inspection, submit the following.
a. Certification by the manufacturer that the transformers conform to the requirements of the drawings and specifications.
b. Certification by the Contractor that the transformers have been properly installed, adjusted, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.
B. International Code Council (ICC):
IBC-21..................International Building Code
C. National Fire Protection Association (NFPA):
70-23...................National Electrical Code (NEC)
D. National Electrical Manufacturers Association (NEMA):
TR 1-19.................Transformers, Step Voltage Regulators and
Reactors
ST 20-14................Dry Type Transformers for General Applications
E. Underwriters Laboratories, Inc. (UL):
UL 506-17...............Standard for Safety - Specialty Transformers
26 22 00 - 3
UL 1561-11..............Standard for Safety - Dry-Type General Purpose and Power Transformers
F. United States Department of Energy:
10 CFR Part 431.........Energy Efficiency Program for Certain
Commercial and Industrial Equipment
PART 2 - PRODUCTS
2.1 TRANSFORMERS
A. Unless otherwise specified, transformers shall be in accordance with
NEMA, NFPA, UL and as shown on the drawings.
B. Transformers shall have the following features:
1. Self-cooled by natural convection, isolating windings, indoor dry-type. Autotransformers will not be accepted, except as specifically allowed for buck-boost applications.
2. Rating and winding connections shall be as shown on the drawings.
3. Ratings shown on the drawings are for continuous duty without the use of cooling fans.
4. Copper windings.
5. Insulation systems:
a. Transformers 30 kVA and larger: UL rated 220 °C (428 °F) system with an average maximum rise by resistance of 150 °C (302 °F) in a maximum ambient of 40 °C (104 °F).
b. Transformers below 30 kVA: Same as for 30 kVA and larger or UL rated 185 °C (365 °F) system with an average maximum rise by resistance of 115 °C (239 °F) in a maximum ambient of 40 °C (104
°F).
6. Core and coil assemblies:
a. Rigidly braced to withstand the stresses caused by short-circuit currents and rough handling during shipment.
b. Cores shall be grain-oriented, non-aging, and silicon steel.
c. Coils shall be continuous windings without splices except for taps.
d. Coil loss and core loss shall be minimized for efficient operation.
e. Primary and secondary tap connections shall be brazed or pressure type.
f. Coil windings shall have end filters or tie-downs for maximum strength.
7. Average audible sound levels shall comply with NEMA.
26 22 00 - 4
8. If not shown on drawings, nominal impedance shall be as permitted by
NEMA.
9. Single phase transformers rated 15 kVA through 25 kVA shall have two
5% full capacity taps below normal rated primary voltage. All transformers rated 30 kVA and larger shall have two 2.5% full capacity taps above, and four 2.5% full capacity taps below normal rated primary voltage.
10. Core assemblies shall be grounded to their enclosures with adequate flexible ground straps.
11. Enclosures:
a. Comprised of not less than code gauge steel.
b. Outdoor enclosures shall be NEMA 3R.
c. Temperature rise at hottest spot shall conform to NEMA Standards, and shall not bake and peel off the enclosure paint after the transformer has been placed in service.
d. Ventilation openings shall prevent accidental access to live components.
e. The enclosure at the factory shall be thoroughly cleaned and painted with manufacturer's prime coat and standard finish.
12. Standard NEMA features and accessories, including ground pad, lifting provisions, and nameplate with the wiring diagram and sound level indicated.
13. Dimensions and configurations shall conform to the spaces designated for their installations.
14. Transformers shall meet the energy conservation standards for transformers per the United States Department of Energy’s 10 CFR
Part 431.
2.2 NONLINEAR TRANSFORMERS
A. Nonlinear transformers shall be as specified in Paragraph 2.1, with additional features as specified below.
B. Transformers shall be designed to withstand the overheating effects caused by harmonics resulting from non-linear (non-sinusoidal) loads.
C. Neutral rating shall be 200% of rated secondary phase current.
D. Transformers with K factor of 13 shall be provided, if K factor is not shown on contract drawings.
26 22 00 - 5
2.3 ENERGY SAVING HARMONIC CANCELLATION TRANSFORMERS (NOT USED)
2.4 BUCK-BOOST TRANSFORMERS (NOT USED)
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation of transformers shall be in accordance with the NEC, as recommended by the equipment manufacturer and as shown on the drawings.
B. Anchor transformers with rustproof bolts, nuts, and washers, in accordance with manufacturer’s instructions, and as shown on drawings.
C. In seismic areas, transformers shall be adequately anchored and braced per details on structural contract drawings to withstand the seismic forces at the location where installed.
D. Exterior Location: (NOT USED)
E. Install transformers with manufacturer's recommended clearance from wall and adjacent equipment for air circulation. Minimum clearance shall be 150 mm (6 inches).
F. Install transformers on vibration pads designed to suppress transformer noise and vibrations.
3.2 ACCEPTANCE CHECKS AND TESTS
A. Perform tests in accordance with the manufacturer's recommendations.
In addition, include the following:
1. Visual Inspection and Tests:
a. Compare equipment nameplate data with specifications and approved shop drawings.
b. Inspect physical and mechanical condition.
c. Inspect all field-installed bolted electrical connections, using the calibrated torque-wrench method to verify tightness of accessible bolted electrical connections.
d. Perform specific inspections and mechanical tests as recommended by manufacturer.
e. Verify correct equipment grounding.
f. Verify proper secondary phase-to-phase and phase-to-neutral voltage after energization and prior to connection to loads.
3.3 FOLLOW-UP VERIFICATION
A. Upon completion of acceptance checks, settings, and tests, the contractor shall demonstrate that the transformers are in good operating condition, and properly performing the intended function.
---END---
26 24 16 - 1
SECTION 26 24 16
PANELBOARDS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, and connection of panelboards.
1.2 RELATED WORK
A. Section 09 91 00, PAINTING (NOT USED)
B. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS: Requirements for seismic restraint of non-structural components.
C. Section 25 10 10, ADVANCED UTILITY METERING (NOT USED)
D. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:
Requirements that apply to all sections of Division 26.
E. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:
Low-voltage conductors.
F. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path for possible ground fault currents.
G. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits.
H. Section 26 05 73, OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY (NOT
USED)
I. Section 26 09 23, LIGHTING CONTROLS (NOT USED)
J. Section 26 43 13, SURGE PROTECTIVE DEVICES (NOT USED)
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compliance with drawings and specifications.
b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, circuit
26 24 16 - 2 breakers, wiring and connection diagrams, accessories, and nameplate data.
c. Certification from the manufacturer that a representative panelboard has been seismically tested to International Building
Code requirements. Certification shall be based upon simulated seismic forces on a shake table or by analytical methods, but not by experience data or other methods.
2. Manuals:
a. Submit, simultaneously with the shop drawings, complete maintenance and operating manuals including technical data sheets, wiring diagrams, and information for ordering circuit breakers and replacement parts.
1) Include schematic diagrams, with all terminals identified, matching terminal identification in the panelboards.
2) Include information for testing, repair, troubleshooting, assembly, and disassembly.
b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.
3. Certifications: Two weeks prior to final inspection, submit the following.
a. Certification by the manufacturer that the panelboards conform to the requirements of the drawings and specifications.
b. Certification by the Contractor that the panelboards have been properly installed, adjusted, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.
B. International Code Council (ICC):
IBC-21..................International Building Code
C. National Electrical Manufacturers Association (NEMA):
PB 1-11.................Panelboards
250-20..................Enclosures for Electrical Equipment (1,000V
Maximum)
D. National Fire Protection Association (NFPA):
70-23...................National Electrical Code (NEC)
26 24 16 - 3
70E-21..................Standard for Electrical Safety in the Workplace
E. Underwriters Laboratories, Inc. (UL):
50-15...................Enclosures for Electrical Equipment
67-09...................Panelboards
489-16..................Molded Case Circuit Breakers and Circuit
Breaker Enclosures
PART 2 - PRODUCTS
2.1 GENERAL REQUIREMENTS
A. Panelboards shall be in accordance with NEC, NEMA, UL, as specified, and as shown on the drawings.
B. Panelboards shall have main breaker or main lugs, bus size, voltage, phases, number of circuit breaker mounting spaces, top or bottom feed, flush or surface mounting, branch circuit breakers, and accessories as shown on the drawings.
C. Panelboards shall be completely factory-assembled with molded case circuit breakers and integral accessories as shown on the drawings or specified herein.
D. Non-reduced size copper bus bars, rigidly supported on molded insulators, and fabricated for bolt-on type circuit breakers.
E. Bus bar connections to the branch circuit breakers shall be the
“distributed phase” or “phase sequence” type.
F. Mechanical lugs furnished with panelboards shall be cast, stamped, or machined metal alloys listed for use with the conductors to which they will be connected.
G. Neutral bus shall be 100% rated, mounted on insulated supports.
H. Grounding bus bar shall be equipped with screws or lugs for the connection of equipment grounding conductors.
I. Bus bars shall be braced for the available short-circuit current as shown on the drawings, but not be less than 10,000 A symmetrical for
120/208 V and 120/240 V panelboards, and 14,000 A symmetrical for
277/480 V panelboards.
J. In two-section panelboards, the main bus in each section shall be full size. The first section shall be furnished with subfeed lugs on the line side of main lugs only, or through-feed lugs for main breaker type panelboards, and have field-installed cable connections to the second section as shown on the drawings. Panelboard sections with tapped bus or crossover bus are not acceptable.
K. Series-rated panelboards are not permitted.
26 24 16 - 4
2.2 ENCLOSURES AND TRIMS
A. Enclosures:
1. Provide galvanized steel enclosures, with NEMA rating as shown on the drawings or as required for the environmental conditions in which installed.
2. Enclosures shall not have ventilating openings.
3. Enclosures may be of one-piece formed steel or of formed sheet steel with end and side panels welded, riveted, or bolted as required.
4. Provide manufacturer’s standard option for prepunched knockouts on top and bottom endwalls.
5. Include removable inner dead front cover, independent of the panelboard cover.
B. Trims:
1. Hinged “door-in-door” type.
2. Interior hinged door with hand-operated latch or latches, as required to provide access only to circuit breaker operating handles, not to energized parts.
3. Outer hinged door shall be securely mounted to the panelboard enclosure with factory bolts, screws, clips, or other fasteners, requiring a key or tool for entry. Hand-operated latches are not acceptable.
4. Inner and outer doors shall open left to right.
5. Trims shall be flush or surface type as shown on the drawings.
2.3 MOLDED CASE CIRCUIT BREAKERS
A. Circuit breakers shall be per UL, NEC, as shown on the drawings, and as specified.
B. Circuit breakers shall be bolt-on type.
C. Circuit breakers shall have minimum interrupting rating as required to withstand the available fault current, but not less than:
1. 120/208 V Panelboard: 10,000 A symmetrical.
2. 120/240 V Panelboard: 10,000 A symmetrical.
3. 277/480 V Panelboard: 14,000 A symmetrical.
D. Circuit breakers shall have automatic, trip free, non-adjustable, inverse time, and instantaneous magnetic trips for less than 400 A frame. Circuit breakers with 400 A frames and above shall have magnetic trip, adjustable from 5x to 10x. Breaker trip setting shall be set in the field, based on the approved protective device study as specified
26 24 16 - 5 in Section 26 05 71, ELECTRICAL SYSTEM PROTECTIVE DEVICE STUDY as required. Coordinate with COR.
E. Circuit breaker features shall be as follows:
1. A rugged, integral housing of molded insulating material.
2. Silver alloy contacts.
3. Arc quenchers and phase barriers for each pole.
4. Quick-make, quick-break, operating mechanisms.
5. A trip element for each pole, thermal magnetic type with long time delay and instantaneous characteristics, a common trip bar for all poles and a single operator.
6. Electrically and mechanically trip free.
7. An operating handle which indicates closed, tripped, and open positions.
8. An overload on one pole of a multi-pole breaker shall automatically cause all the poles of the breaker to open.
9. Ground fault current interrupting breakers, shunt trip breakers, lighting control breakers (including accessories to switch line currents), or other accessory devices or functions shall be provided where shown on the drawings.
10. For circuit breakers being added to existing panelboards, coordinate the breaker type with existing panelboards. Modify the panel directory accordingly. Coordinate with the COR.
2.4 SURGE PROTECTIVE DEVICES (NOT USED)
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be in accordance with the manufacturer’s instructions, the NEC, as shown on the drawings, and as specified.
B. Locate panelboards so that the present and future conduits can be conveniently connected.
C. In seismic areas, panelboards shall be adequately anchored and braced per details on structural contract drawings to withstand the seismic forces at the location where installed.
D. Install a printed schedule of circuits in each panelboard after approval by the COR. Schedules shall reflect final load descriptions, room numbers, and room names connected to each circuit breaker.
Schedules shall be printed on the panelboard directory cards and be installed in the appropriate panelboards
26 24 16 - 6
E. Mount panelboards such that the maximum height of the top circuit breaker above the finished floor shall not exceed 1980 mm (78 inches).
F. Provide blank cover for each unused circuit breaker mounting space.
G. Panelboards accessible to the public (NOT USED)
H. Rust and scale (NOT USED)
I. Panelboard enclosures shall not be used for conductors feeding through, spliced, or tapping off to other enclosures or devices.
3.2 ACCEPTANCE CHECKS AND TESTS
A. Perform in accordance with the manufacturer's recommendations. In addition, include the following:
1. Visual Inspection and Tests:
a. Compare equipment nameplate data with specifications and approved shop drawings.
b. Inspect physical, electrical, and mechanical condition.
c. Verify appropriate anchorage and required area clearances.
d. Verify that circuit breaker sizes and types correspond to approved shop drawings.
e. To verify tightness of accessible bolted electrical connections, use the calibrated torque-wrench method or perform thermographic survey after energization.
f. Vacuum-clean enclosure interior. Clean enclosure exterior.
3.3 FOLLOW-UP VERIFICATION
A. Upon completion of acceptance checks, settings, and tests, the
Contractor shall demonstrate that the panelboards are in good operating condition and properly performing the intended function.
26 29 21 - 1
SECTION 26 29 21
ENCLOSED SWITCHES AND CIRCUIT BREAKERS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, and connection of fused and unfused disconnect switches (indicated as switches in this section), and separately-enclosed circuit breakers for use in electrical systems rated 600 V and below.
1.2 RELATED WORK
A. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS: Requirements for seismic restraint of non-structural components.
B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:
Requirements that apply to all sections of Division 26.
C. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:
Low-voltage conductors.
D. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path for possible ground faults.
E. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits.
F. Section 26 24 16, PANELBOARDS: Molded-case circuit breakers.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compliance with drawings and specifications.
b. Submit the following data for approval:
1) Electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, fuses, circuit breakers, wiring and connection diagrams, accessories, and device nameplate data.
26 29 21 - 2
c. Certification from the manufacturer that representative enclosed switches and circuit breakers have been seismically tested to
International Building Code requirements. Certification shall be based upon simulated seismic forces on a shake table or by analytical methods, but not by experience data or other methods.
2. Manuals:
a. Submit complete maintenance and operating manuals including technical data sheets, wiring diagrams, and information for ordering fuses, circuit breakers, and replacement parts.
1) Include schematic diagrams, with all terminals identified, matching terminal identification in the enclosed switches and circuit breakers.
2) Include information for testing, repair, troubleshooting, assembly, and disassembly.
b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.
3. Certifications: Two weeks prior to final inspection, submit the following.
a. Certification by the manufacturer that the enclosed switches and circuit breakers conform to the requirements of the drawings and specifications.
b. Certification by the Contractor that the enclosed switches and circuit breakers have been properly installed, adjusted, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.
B. International Code Council (ICC):
IBC-21..................International Building Code
C. National Electrical Manufacturers Association (NEMA):
FU l-12.................Low Voltage Cartridge Fuses
KS l-13.................Heavy Duty Enclosed and Dead-Front Switches
(600 Volts Maximum)
D. National Fire Protection Association (NFPA):
70-23...................National Electrical Code (NEC)
26 29 21 - 3
E. Underwriters Laboratories, Inc. (UL):
98-16...................Enclosed and Dead-Front Switches
248 1-11................Low Voltage Fuses
489-16..................Molded Case Circuit Breakers and Circuit
Breaker Enclosures
PART 2 - PRODUCTS
2.1 FUSED SWITCHES RATED 600 AMPERES AND LESS
A. Switches shall be in accordance with NEMA, NEC, UL, as specified, and as shown on the drawings.
B. Shall be NEMA classified General Duty (GD) for 240 V switches, and NEMA classified Heavy Duty (HD) for 480 V switches.
C. Shall be horsepower (HP) rated.
D. Shall have the following features:
1. Switch mechanism shall be the quick-make, quick-break type.
2. Copper blades, visible in the open position.
3. An arc chute for each pole.
4. External operating handle shall indicate open and closed positions, and have lock-open padlocking provisions.
5. Mechanical interlock shall permit opening of the door only when the switch is in the open position, defeatable to permit inspection.
6. Fuse holders for the sizes and types of fuses specified.
7. Solid neutral for each switch being installed in a circuit which includes a neutral conductor.
8. Ground lugs for each ground conductor.
9. Enclosures:
a. Shall be the NEMA types shown on the drawings.
b. Where the types of switch enclosures are not shown, they shall be the NEMA types most suitable for the ambient environmental conditions.
c. Shall be finished with manufacturer’s standard gray baked enamel paint over pretreated steel.
10. Electrically operated switches (NOT USED)
2.2 UNFUSED SWITCHES RATED 600 AMPERES AND LESS
A. Shall be the same as fused switches, but without provisions for fuses.
2.3 FUSED SWITCHES RATED OVER 600 AMPERES TO 1200 AMPERES
A. Shall be the same as fused switches, and shall be NEMA classified Heavy
Duty (HD).
26 29 21 - 4
2.4 MOTOR RATED TOGGLE SWITCHES
A. Type 1, general purpose for single-phase motors rated up to 1 horsepower.
B. Quick-make, quick-break toggle switch with external reset button and thermal overload protection matched to nameplate full-load current of actual protected motor.
2.5 CARTRIDGE FUSES
A. Shall be in accordance with NEMA FU 1.
B. Shall be as required by code and in accordance with Coordination Study.
C. Shall be in accordance with manufacturers recommendations.
2.6 SEPARATELY-ENCLOSED CIRCUIT BREAKERS
A. Provide circuit breakers in accordance with the applicable requirements in Section 26 24 16, PANELBOARDS.
B. Enclosures shall be the NEMA types shown on the drawings. Where the types are not shown, they shall be the NEMA type most suitable for the ambient environmental conditions.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be in accordance with the NEC, as shown on the drawings, and manufacturer’s instructions.
B. In seismic areas, enclosed switches and circuit breakers shall be adequately anchored and braced per details on structural contract drawings to withstand the seismic forces at the location where installed.
C. Fused switches shall be furnished complete with fuses. Arrange fuses such that rating information is readable without removing the fuses.
3.2 ACCEPTANCE CHECKS AND TESTS
A. Perform in accordance with the manufacturer's recommendations. In addition, include the following:
1. Visual Inspection and Tests:
a. Compare equipment nameplate data with specifications and approved shop drawings.
b. Inspect physical, electrical, and mechanical condition.
c. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method.
d. Vacuum-clean enclosure interior. Clean enclosure exterior.
26 29 21 - 5
3.3 SPARE PARTS
A. Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project.
Deliver the spare fuses to the COR.
| 00 00 Title Page RFI addendum 2023-01-18 |
| 00 01 10 Table of Contents RFI addendum 2023-01-18 |
| 13 05 41 Seismic Restraint Requirments for Non-Structural Components |
| 26 22 00 Low-Voltage Transformers |
| 26 24 16 Panelboards |
| 26 29 21 Enclosed Switches and Circuit Breakers |
| PART 1 - GENERAL |
| 1.1 DESCRIPTION |
| 1.2 RELATED WORK |
| 1.4 SUBMITTALS |
| 1.5 APPLICABLE PUBLICATIONS |
| PART 2 - PRODUCTS |
| 2.1 FUSed SWITCHES RATED 600 AMPERES AND LESS |
| 2.2 UNFUSED SWITCHES RATED 600 AMPERES AND LESS |
| 2.3 FUSed SWITCHES RATED OVER 600 AMPERES TO 1200 AMPERES |
| 2.4 MOTOR RATED TOGGLE SWITCHES |
| 2.5 cartridge fuses |
| PART 3 - EXECUTION |
| 3.1 INSTALLATION |
| 3.3 SPARE PARTS |
File details come from the government source that posted it. Updated .