S04 -Site Visit Meeting Doc.docx
DOCX document 18 KB Posted
- Attached to
- Z2DA--660-22-114 Non-Sterile Compounding Room Update Federal contract opportunity
- Solicitation number
- 36C25922Q0417
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25922Q0417 RFI.docx | DOCX document | |
| 36C25922Q0417 0002.docx | DOCX document | |
| Update Non Sterile Compounding Room Specs V2.docx | DOCX document | |
| Past Performance Questionnaire.docx | DOCX document | |
| 36C25922Q0417 0001.docx | DOCX document | |
| Walkthrough Attendance Sheet.pdf | ||
| Specs.docx | DOCX document | |
| Solicitation_Instructions to Offerors - Under SAP.docx | DOCX document | |
| 36C25922Q0417_1.docx | DOCX document | |
| Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting
FOR
The contractor is to provide all labor, tools, materials, equipment and supervision required to update the Non-Sterile Compounding Room at the Salt Lake City VA Medical Center.
Location: Salt Lake City VAMC, 500 Foothill Drive Salt Lake City, UT 84148.
AGENDA:
· Introduction of Christina Beeler-Blackburn CO, Alonso Bernal Gonzales COR, and Sylwia Zak CS
· The pre-bid meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send Quote:
· Electronic submissions to sylwia.zak@va.gov
· Pertinent Dates:
· Quotes due on 7/21/2022 at 11AM MT via email
· Questions due on 7/8/2022 at 2PM MT via email
· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded
· Masks are required at all times while on VA property. Entrance screenings will be conducted each day.
· Confirmation of construction range is between $25,000 and $100,000.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 50 calendar days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.