FMS-30 Inspection Testing Maint of Sprinkler Systems.doc
DOC document 77 KB Posted
- Attached to
- Z2DA--Site Preparation for X-ray #1 and #5
- Solicitation number
- 36C25921R0049
About this file
This document outlines requirements for inspection, testing and maintenance services for fire suppression sprinkler systems and fire hydrants at the Jack C. Montgomery VA Medical Center in Muskogee, Oklahoma. The Department of Veterans Affairs Facilities Management Service is responsible for proper maintenance of the medical center's sprinkler systems and must inspect, test and perform preventative maintenance on a weekly, monthly, quarterly, semiannual and annual basis in accordance with the detailed procedures provided. Notification requirements are specified when sprinkler systems must be shut down for work. All work must be documented in the facility's work order and asset management system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25921R0049 0002.docx | DOCX document | |
| 36C25921R0049 0001.docx | DOCX document | |
| Site Visit Station Map.pdf | ||
| 36C25921R0049_1.docx | DOCX document | |
| Combined Specs Final.pdf | ||
| Site Visit Hatbox Parking.pdf | ||
| Oklahoma XRAY Site Prep 100 Percent Review Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
VETERANS HEALTH ADMINSTRATION
JCM-VAMC-M
Facilities Management Service
INSPECTION, TESTING & MAINTENANCE OF WET PIPE FIRE SUPRESSION SPRINKLER SYSTEMS & FIRE HYDRANTS I.
PURPOSE.
To establish policy to provide guidance for inspection, testing and maintenance of Wet Pipe Fire Sprinkler systems & Fire Hydrants. Wet Fire Pipe Suppression Sprinkler systems is defined as all components of the system except Flow and Tamper switches included items are heads, drain valves, system piping, & Fire Pumps and all other components of the system which provides life safety protection for the facility. Fire Hydrant is defined as a valve connected on a water main for the purpose of supplying water to fire hose or other fire protection apparatus.
II.
POLICY.
To provide recommended practices and code requirments to the inspection, testing and maintenance of sprinkler equipment upon which the safety of life and property may depend.
III.
RESPONSIBILITIES.
The responsibility for proper maintenance of the medical center's sprinkler systems is assigned to Facilities Management Service. The Safety Officer will be responsible for QM of the program. The Maintenance and Repair (M&R) Section will perform testing as defined herein. Any testing or maintenance that occurs which renders system components inoperable or unusable will be reported to the Safety Manager. If any defects or impairments are revealed, corrective action will be taken. All outlined preventive maintenance will be documented via the AEMS/MERS system.
IV.
PROCEDURES
(1) INSPECTIONS:
A. Inspections Weekly
1. Perform no flow churn test on Fire Pump
2. Document fire pump pressures
B. Inspections Monthly
1. Spare sprinkler and sprinkler wrench
2. Pressure gages
C. Inspections Quarterly
1. Fire Department Connections
2. Alarm devices free from physical damage
D. Inspection Annual
1. Proper number and type of sprinkler heads
2. Visual of sprinkler heads
3. Visual of Pipe
4. Adequate heat in all areas
JCM-VAMC-M FMS Standard Operating Procedure FMS-30
Inspection, Testing & Maintenance of Sprinkler Systems May 3, 2004
(2) TESTING:
A. Testing Quarterly
1. Mechanical Water flow devices
2. Post indicator valves
B. Testing Semiannual
1. Electrical water flow devices
2. Valve supervisory switches
C. Testing Annual
1. Main Drain Test
2. Back flow test
3. Fire pump full flow test
(3) Notification:
When performing work that requires the sprinkler system to be shut down, a Utility Interruption Coordination work sheet will be completed as to FMS, SOP-39. Notification will be given to the Safety Officer. He/she will make appropriate notifications to staff, Directors Office and the VISN, if the outage will be more than 4 hours. The M&R Section will also notify the Boiler Plant, who will then notify the Muskogee City Fire Department. Shutdown of the system lasting more than 4 hours will have hourly fire watch checks by the Safety Staff or designees. Safety staff will notify the Boiler Plant of the status every hour during the fire watch.
(4) Fire Hydrants:
A. Testing Annually
1. Open each hydrant and flow for 1 minute to clear foreign materials
2. Observe proper drainage
3. Lubricate stems, caps, plugs, & threads B. Testing 5 Years
1. Full Flow test
(5) ALTERATIONS:
Any alteration to a sprinkler system should be done in accordance with NFPA 13, Standard for the Installation of Sprinkler Systems or other applicable NFPA Standards.
V.
REFERENCES.
MP-3, Part III, NFPA 13-A. NFPA 25
VI.
RESCISSIONS.
Engineering Standard Operated Procedure138-30, same subject dated
June 12, 2002.
//s// //s//
ROBERT WELSH BENJAMIN R. CAMPEAU, JR.
Chief, Facilities Management Service Associate Medical Center Director
Attachment – Appendix A
Dist: Each FMS Employee
| Date of Shutdown |
| System Item |
| Reason |
| Time back on |
JCM-VAMC-M FMS Standard Operating Procedure FMS-30 Appendix A Inspection, Testing & Maintenance of Sprinkler Systems May 3, 2004
FIRE SYSTEM SHUTDOWN AND NOTIFCATION LOG
JACK C. MONTGOMERY FMS Standard Operating Procedure FMS-30
VA Medical Center, Muskogee May 3, 2004