Construction of a temporary covered walkway (VA-18-00109708) Federal contract opportunity
Solicitation number
36C25918R0600
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

36C25918R0600 36C25918R0600.docx

View the file

Other files for this federal contract opportunity

Other files attached to Construction of a temporary covered walkway (VA-18-00109708), newest first.
File Type Posted
36C25918C0339-000.docx DOCX document
36C25918R0600-0006000.docx DOCX document
36C25918R0600-0005000.docx DOCX document
36C25918R0600-0004000.docx DOCX document
36C25918R0600-0004001.pdf PDF
36C25918R0600-0004002.docx DOCX document
36C25918R0600-0003000.docx DOCX document
36C25918R0600-0002001.pdf PDF
36C25918R0600-0002002.pdf PDF
36C25918R0600-0002000.docx DOCX document
36C25918R0600-0001002.pdf PDF
36C25918R0600-0001001.pdf PDF
36C25918R0600-0001005.pdf PDF
36C25918R0600-0001004.pdf PDF
36C25918R0600-0001003.pdf PDF
36C25918R0600-0001000.docx DOCX document
36C25918R0600-0001006.pdf PDF
36C25918R0600-0001007.pdf PDF
36C25918R0600-007.docx DOCX document
36C25918R0600-005.pdf PDF
36C25918R0600-004.pdf PDF
36C25918R0600-003.pdf PDF
36C25918R0600-006.pdf PDF
36C25918R0600-002.pdf PDF
36C25918R0600-000.docx DOCX document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT

NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV.

8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that t ime. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government accepta nce after the date offers are due will not be considered and will be rejected.

36C25918R0600 X 07-13-2018 442-18-014S 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 robyn.young2@va.gov

Robyn Young 307-433-3728 Contractor shall provide all labor, equipment, materials and supervision necessary to perform all work required for this project in accordance with the scope of work. The project is located at the Cheyenne, WY VA.

The project magnitude is between $25,000 and $100,000.

The NAICS code is 236220 - Small Business size standard is $36.5 Million.

In accordance with P.L. 109-461, this acquisition is 100% set aside for Service Disabled Veteran Owned Small Businesses concerns. See VAAR 852.219-10, Notice of Total Service Disabled Veteran Owned Small Business Set-Aside of this solicitation for information in regards to requirements in order to be considered. Offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) prior to contract award.

Failure to be bo th VERIFIED by CVE and VISIBLE on VetBiz prior to contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urgedto contact the CVE and submit the aforementioned required documents to obtain CVE verification of their SDVOSB statusif they have not already done so.

In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to award of a contract or agreement.

A site visit will be held on August 13, 2018, 10:00 A.M. Mountian Time. Attendees will meet in Building 11 at the Cheyenne, WY VAMC.

All questions in relation to this solicitation are due no later than August 17, 2018, at 2:00 P.M, MDT.

Please address questi ons to robyn.young2@va.gov.

X X 52.211-10 X

2:00 PM MDT

08-28-2018 X

14. NAME AND ADDRESS OF

OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN

COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by

(a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME

OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contra ctor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
1.2 BID SCHEDULE5
STATEMENT OF WORK6
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS9
E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.12
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)13
2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)14
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)15
2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)16
REPRESENTATIONS AND CERTIFICATIONS17
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)17
GENERAL CONDITIONS21
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)21
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)21
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)21
4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)22
4.5 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)25
4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)26
4.7 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)27
4.8 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)28
4.9 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)29
4.10 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002)30
4.11 VAAR 852.236-76 CORRESPONDENCE (APR 1984)30
4.12 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002)30
4.13 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984)30
4.14 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984)31
4.15 VAAR 852.236-82 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS) (APR 1984)31
4.16 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984)34
4.17 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984)34
4.18 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008)35
4.19 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993)35
4.20 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)35
4.21 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008)37
4.22 VAAR 852.236-91 SPECIAL NOTES (JUL 2002)38
4.23 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)39
4.24 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011)39

1.2 BID SCHEDULE

CONTRACT LINE ITEM NUMBER (CLIN) 0001 – Base Contractor is to provide all materials, labor and equipment to construct a temporary covered walkway from the West double door exit of the main Arrowhead building to the South entrance of the MRI Building as indicated in the SOW, specifications and drawings.

Page 1 of Page 1 of

STATEMENT OF WORK

1. Overview The intent of this project is to construct a temporary covered walkway from the West double door exit of the main Arrowhead building to the South entrance of the MRI Building. This is to allow patients a safe and secure way to get from the main building to the MRI trailer for their appointments.

Scope of Work:

Installation of the temporary covered walkway will require support and extension of electrical, fire protection, and fire alarm services from the existing MRI Building into the new walkway. Construction of the walkway will include the installation of wood framed walls with wood panel siding and a roof with asphalt shingles and gutter/ downspout. Two new doors will be provided (one with an ADA opener) along with four new operable windows which will provide natural light and ventilation. The walkway will be constructed and secured on top of the existing concrete between the two buildings. A short concrete sidewalk is being added to complete the path of exiting from the MRI Building’s secondary egress doors due to the new walkway cutting off the pervious exiting path. Contractor is responsible for all disconnections and reconnections of utility services.

2. Contractor Responsibilities

2.1. Contractor shall supply all labor and materials necessary to provide a complete and working system as outlined in the construction documents.

2.2. It is the responsibility of the Contractor to properly assess the contract documents and existing site conditions for the installation of the work.

2.3. If there is a discrepancy between the specifications and the construction drawings, the specifications or the more stringent condition shall apply.

2.4. Contractor shall be responsible for reviewing all drawings and specifications and shall submit Requests for Information (RFI’s) for any discrepancies or clarifications needed to provide a complete and working system. Contractor shall submit RFIs to the Contracting Officer for clarification prior to bidding the work.

2.5. Contractor is responsible for supplying all tools and equipment necessary to perform this work.

2.6. All shut-downs which affect hospital operations must be submitted a minimum of two weeks in advance to the COR for approval. Minor shut-downs must be submitted 3 days in advance.

2.7. Hot work permits are required and must be submitted a minimum of 3 days in advance for approval by the facility Safety Manager.

2.8. Work which produces high levels of noise shall not be undertaken without written approval of the COR.

2.9. Contractor shall maintain a set of contract drawings on site to record progress and as-built conditions which shall be updated no less than once a week.

2.10. Operation and Maintenance manuals are the responsibility of the Contractor and shall be written in such a manner as to facilitate work and maintenance on provided systems and equipment.

2.11. Schedules are to be updated weekly and submitted to the COR. A three week look ahead of all work to be performed shall be provided at each weekly project meeting.

2.12. All work performed shall comply with VA Master Specifications. It is the responsibility of the Contractor to understand and comply with all applicable municipal, county, state, and federal codes, laws, ordinances, standards, rules and regulations. All work shall be completed to generally accepted trade standards and accomplished in a workmanlike manner.

2.13. Electricians and supervisors on this project must show that they have taken an Arc Flash Safety Course.

3. Security Requirements

3.1. THE CONTRACTOR SHALL COMPLY WITH AGENCY PERSONAL IDENTITY VERIFICATION PROCEDURES IDENTIFIED IN THE CONTRACT THAT IMPLEMENT HOMELAND SECURITY PRESIDENTIAL DIRECTIVE-12 (HSPD-12), OFFICE OF MANAGEMENT AND BUDGET (OMB) GUIDANCE M-05-24, AND FEDERAL INFORMATION PROCESSING STANDARDS PUBLICATION (FIPS PUB) NUMBER 201.

3.2. THE CONTRACTOR SHALL INSERT THIS CLAUSE IN ALL SUBCONTRACTS WHEN THE SUBCONTRACTOR IS REQUIRED TO HAVE ROUTINE PHYSICAL ACCESS TO A FEDERALLY-CONTROLLED FACILITY AND/OR ROUTINE ACCESS TO A FEDERALLY-CONTROLLED INFORMATION SYSTEM.

3.3. Every worker must wear a valid VA ID badge at all times to work on this site. The VA Police will issue day badges to workers who produce valid IDs. Right-to-work documentation will be required for workers who are not US citizens.

4. Safety Requirements

4.1. Contractor shall adhere to the facility safety policy attached to this solicitation.

5. PLACE OF PERFORMANCE

VA Medical Center, Cheyenne 2360 E. Pershing Blvd Cheyenne, WY 82001

6. Travel The contractor shall not charge travel costs to the Government.

7. HOURS OF WORK

7.1. Normal work hours are from 0700 hrs. to 1530 hrs. It is anticipated that 50% of the contractor work will occur during this time period. The balance shall be from 1700 to 0100 at night or on weekends from 0700 hrs. to 1530 hrs. Requests for work performed outside of normal work hours must be submitted a minimum of one week in advance to the COR for approval.

8. Schedule and general requirements

8.1. Construction shall be completed 30 days from Notice to Proceed.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

This is a Request for Proposal in accordance with FAR Part 13. Potential offerors must follow all instructions in order to be compliant with the solicitation.

It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.

The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ.

I.3A PRE-PROPOSAL SITE VISIT

A site visit will be held on August 13, 2018, 10:00 A.M. MDT. Interested contractors shall meet at the Cheyenne, WY VAMC, Facilities management Bldg. 11. All offerors, consultants, subcontractors, manufacturers and suppliers are encouraged to attend this meeting to familiarize themselves with the project, project site, and to provide any questions in regards to this solicitation and project, in writing, prior to the scheduled conference date. See FAR Clause 52.236-3, Site Investigation and Conditions Affecting the Work, and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation.

I.4A SELECTION CRITERIA/PROPOSAL PREPARATION INSTRUCTIONS

Proposals will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:

Factor 1 – Past Performance Factor 2 – Price The Government reserves the right to award without discussions. Therefore offerors are encouraged to provide their best proposals with the past performance information requested for evaluation. The Government, based on the proposal material presented, will award to the proposal that best demonstrates to be most advantageous for the Government.

Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. For purposes of this evaluation, a relevant project is further defined as a project including Renovations to an active commercial facility. Project shall have a minimum amount of $35,000.00 or more and completed within the past three years from the date of issuance of this RFP. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).

Completed PPQs should be submitted directly from your client via email to Robyn Young at robyn.young2@va.gov. If the offeror is unable to contact a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.

Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.

In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. If that offeror is otherwise acceptable for non-price factors and has the lowest price the matter will be referred to the Small Business Administration for a Certificate of Competency, in accordance with the procedures contained in FAR Subpart 19.6, and 15 U.S.C. 637(b)(7).

Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442 Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

•Comparison of proposed prices received in response to the RFP
•Comparison of proposed prices with the IGCE.
•Comparison of proposed prices with available historical information.

The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: $25,000.00 - $100,000.

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.5B PROPOSAL REQUIREMENTS

General – Both technical and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email to Andrew.stigen@va.gov. Emails are limited to five (5) MB. The proposal, in its entirety, shall not exceed two emails (one email for price proposal, and one email for technical proposal) of 5MB each. Technical proposals (not including past performance questionnaires) are limited to 30 pages. Price shall be in a separate electronic document from the technical and past performance portions of the proposal. The offeror’s technical response shall clearly address each evaluation factor listed in this solicitation. Failures to submit in the format required and clearly address those factors may result in rejection of the offer. Further details on electronic submission are outlined below. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Proposals shall be received by 2:00 PM Mountain Time on August 28, 2018. There will be no public opening of the proposals. Submit proposals to: robyn.young2@va.gov.

Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control sufficient to establish appropriate status, offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation at the time of contract award. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of contract award will result in the offeror’s proposal being deemed non-responsive. All offerors are urged to contact the CVE and submit the aforementioned required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

I.6B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER

Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.

In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.

Acceptable Electronic Formats (Software) for Submission of Offers

1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Print or scan images of spreadsheets are not acceptable. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files)

1. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.

1. Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.

1. Please note that we can no longer accept .zip files due to increasing security concerns.

E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.

a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, or Bid depending on the solicitation type.

b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.

c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.

Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)

The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipients “inbox” is the official record of receipt.

Security Issues, Late Bids, Unreadable Offers

1. Late submission of offers are outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.

1. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.

1. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).

1. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.

1. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.

2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
7.5 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Laramie County, WY.

(End of Provision)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— August 13, 2018, 10:00 A.M. MDT

(c) Participants will meet at— Bldg 11 Cheyenne, WY VAMC (End of Provision)

2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2016
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $36.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The offeror has completed the annual representations and certifications electronically via the SAM Web site accessed through https://www.acquisition.gov. After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause #
Title
Date
Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of Provision)

GENERAL CONDITIONS

4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 days after NTP. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)

(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for…