36C25918R0391-010.docx

DOCX document 93 KB Posted

Attached to
Radiology Rooms 1 & 3 Federal contract opportunity
Solicitation number
36C25918R0391
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

36C25918R0391 36C25918R0391.docx

View the file

Other files for this federal contract opportunity

Other files attached to Radiology Rooms 1 & 3, newest first.
File Type Posted
36C25918C0232-000.docx DOCX document
36C25918R0391-00001000.docx DOCX document
36C25918R0391-00001004.docx DOCX document
36C25918R0391-00001003.pdf PDF
36C25918R0391-00001002.docx DOCX document
36C25918R0391-00001001.pdf PDF
36C25918R0391-013.pdf PDF
36C25918R0391-017.docx DOCX document
36C25918R0391-012.pdf PDF
36C25918R0391-015.pdf PDF
36C25918R0391-014.pdf PDF
36C25918R0391-011.pdf PDF
36C25918R0391-016.pdf PDF
36C25918R0391-018.docx DOCX document
36C25918R0391-009.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

REMODEL EXAM/X-RAY ROOMS IN RADIOLOGY

STATEMENT OF WORK

REMODEL EXAM/X-RAY ROOMS IN RADIOLOGY

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25918R0391 X 04-27-2018 442-18-1-1146-0001 442-18-002 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 shellie.murphy@va.gov

Shellie Murphy 303-712-5737 Contractor shall provide all labor, equipment, materials, and supervision necessary to perform all work required for this project in accordance with all the drawings, specifications, and the scope of work. The project is located at the Cheyenne VA Medical Center, 2360 E. Pershing Blvd, Cheyenne, WY 82001

Project magnitude: between $25,000 and $100,000. The NAICS code is 236220 - Small Business size standard is $36.5M.

In accordance with P.L. 109-461, this acquisition is 100% set aside for Service Disabled Veteran Owned Small Businesses concerns. See VAAR 852-219-10, Notice of Total Service Disabled Veteran Owned Small Business Set-Aside of this solicitation for information in regards to requirements in order to be considered. Offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) prior to contract award.

Failure to be both VERIFIED by CVE and VISIBLE on VetBiz prior to contract award will result in the offeror's proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the arorementioned required documents to obtain CVE verificaiton of their SDVOSB status if they have not already done so.

A site visit will be held on 10 May 2018 at 10:00 AM Mountain Standard Time (MST). Attendees will meet at Building 11, in the Engineering Conference Room, at the Cheyenne VAMC in Wyoming.

All questions in relation to this solicitation must be submitted in writing via e-mail to shellie.murphy@va.gov and received no later than 15 May 2018, 10:00 PM MST, in order to permit adequate time for the Government to reply to inquiries.

Instructions, Conditions, and Notices to Offerors: All submitted proposals must be received via e-mail by the closing date and time. The solicitation closes on 22 May 2018 at 2:00 PM MST.

X X 52.211-10 X 10 Days

2:00 PM MST

05-22-2018 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin

TX

78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.1 STATEMENT OF WORK5
REMODEL EXAM/X-RAY ROOMS IN RADIOLOGY5
1. Purpose5
2. Scope of Work5
3. Objectives6
4. Security Requirements7
5. Place of Performance7
6. Hours of Work7
8. General Requirements7
A.2 BID SCHEDULE8
E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.13
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)15
2.2 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
2.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)16
REPRESENTATIONS AND CERTIFICATIONS17
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)17
3.2 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)20
GENERAL CONDITIONS21
4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)21
4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)21
4.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)22
4.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)23
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)24
4.6 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)27
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)27
4.8 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011)29
4.9 VAAR 852.203-70 COMMERCIAL ADVERTISING (JAN 2008)29
4.10 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)29
4.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)30
4.12 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002)32
4.13 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002)32
4.14 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002)33
4.15 VAAR 852.236-76 CORRESPONDENCE (APR 1984)33
4.16 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002)33
4.17 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984)33
4.18 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984)34
4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984)34
4.20 VAAR 852.236-82 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS) (APR 1984)34
4.21 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984)37
4.22 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984)38
4.23 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008)38
4.24 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)38
4.25 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008)40
4.26 VAAR 852.236-91 SPECIAL NOTES (JUL 2002)41
4.27 VAAR 852.246-74 SPECIAL WARRANTIES (JAN 2008)41
4.28 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)42
4.29 WAGE DETERMINATION42
4.30 ATTACHMENTS52

A.1 STATEMENT OF WORK

Page 1 of Page 1 of

REMODEL EXAM/X-RAY ROOMS IN RADIOLOGY

1. Purpose

The purpose of this Statement of Work (SOW) is to establish the requirements for the remodel of xray labs number 1, 2 and 3 to allow for new and updated equipment to be installed by the equipment supplier. Existing equipment will be removed by others.

This SOW is provided to accomplish the replacement and/or modifications to existing electrical, raceways, support structures and data cabling to the afore mentioned x-ray/exam rooms. All work shall be planned and scheduled to minimize the construction activity impact on the operation of the medical center. All work shall be conducted with strict adherence to Cheyenne Medical Center and Veteran’s Health Administration regulations and infection control requirements.

2. Scope of Work

2.1Contractor shall assess the information provided and existing conditions.
2.2Contractor and/or Sub-contractors shall be responsible for clarification requests directed to the VAMC’s CO prior to the bidding of the work.
2.3Contractors shall adhere to the VAMC’s facility security requirements, including preparation of a fire safety plan, protection of all existing facility improvements and coordination with the COR.
2.4Contractor and/or Sub-contractors shall be responsible for the accuracy and scope of the specifications, drawings, and cost estimates in relation to areas or items addressed in this SOW. Any deficiencies in the documents shall be brought to the attention of the Contracting Officer prior to bid receipt.
2.5Contractor and/or Sub-contractors shall perform all necessary investigations and work to determine and verify work can be performed as specified.
2.6Contractor and/or Sub-contractors shall provide all materials and equipment as well as installation as required to accomplish the objective.
2.7Contractor and/or Sub-contractors shall provide material submittals to the COR prior to installation.
2.8Contractor and/or Sub-contractors are responsible for providing all tools and equipment necessary to perform this work.
2.9The medical center must remain operational throughout the construction period. Any required shutdowns shall be coordinated through the COR and a minimum of two weeks notification prior to the proposed date of the shutdown.
2.10All work performed and specified shall comply with applicable Local, State, and Federal code requirements, and VA Master Construction Specifications. It is the responsibility of the Contractor to understand and comply with all applicable municipal, county, state, and federal codes, laws, ordinances, standards, rules and regulations.

3. Objectives

Note: The drawings as provided by the equipment suppliers are typical and depict requirements for new complete installations. The lab equipment that is being removed and replaced is similar but not identical to the new equipment. Hence, it is necessary to assess the required alterations and additions to allow for a complete installation. We can reuse existing raceways and conductors whenever practical. Some of the existing rectangular duct raceway may require additional dividers to allow for three compartment separations between power, control and data.

Where flush mounted backing is called for on the drawings, it will be permissible to use 3/4” surface mounted plywood backing, painted to match existing walls.

Lab #3 will be done first. When it is completed, there will be approximately three weeks before work can begin work on Lab #2 and the same time frame after Lab #2 completion before starting on Lab #1. All labs will require additional CAT-6 cables per drawing provided. All data cables shall be tested nad certified.

The Contractor and/or Sub-contractors shall confirm the accuracy and understanding, and comply with the equipment supplier’s drawings to complete the following work as defined within this scope of work including but not limited to the following:

3.1 Lab #3: GE Healthcare drawings dated 12/18/17. Modify existing Unistrut structure per plans and specifications. Add two rails, (i.e. Item #2 on Drawing S1.

3.2 Relocate light fixtures away from rails.

3.3 Re-do ceiling grid and tile that allows for the added Unistrut.

3.4 Prepare floor for new equipment. A portion of existing trench will need to be filled with concrete.

3.5 Add section of 10” x 3-1/2” surface raceway from existing wall raceway to equipment cable entrance.

3.6 Provide additional raceways/conduit and cables as required to comply with drawings.

3.7 Lab #2: GE Healthcare drawings dated 2/9/18.

3.8 Lab #1: AGFA Health Care drawings dated 1/12/17 & 10/11/16. Sawcut floor for installation of 10” x 3-1/2” trench duct per drawings.

3.9 Refer to AGFA Health Care drawing dated 10/11/16 for added wiremold, floor tile and control console modifications.

4. Security Requirements

4.1 The contractor shall comply with Agency Personal Identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12 (HSPD-12), Office of Management and Budget (OMB) Guidance M-05-24, and Federal Information Processing Standards Publication (FIPS PUB) Number 201.

5. Place of Performance

VA Medical Center 2360 E. Pershing Blvd, Cheyenne, WY 82001

6. Hours of Work

6.1 Contractor is expected to conform to agency normal operation hours on Monday through Friday from 7:00am – 4:30pm (local time) excluding federal holidays, unless otherwise noted.

6.2 Work requiring shutdown, interruption, infection control, or potential interruption of power to critical areas of the Medical Center will require extensive coordination and planning with the COR and will require at least two weeks’ notice to the COR. Major shutdowns may have to occur on weekends.

7. Schedule and General Requirements

7.1 Construction shall be completed 90 calendar days from Notice to Proceed.

8. General Requirements

8.1 VA shall provide all available drawings for information purposes only.

8.2 An on-site job walk will be scheduled and notifications provided.

9. Escort and Security Police Check In:

9.1 All contractor personnel working onsite at the VA facility shall check in and out with VA Police dispatch located in the main hospital building. Access to work areas, and performance monitoring, will be provided by VA CORs. In all cases, the COR and Supervisory Facilities Manager shall be notified of any changes which may affect the response time of vital equipment.

10. Contract Administration Data:

Federal Legal Holidays: The following Federal legal holidays are observed by this facility:

New Year’s DayJanuary 1
Martin Luther King’s BirthdayThird Monday in January
President’s Day

Third Monday in February

Memorial Day

Last Monday in May

Independence Day

July 4

Labor Day

First Monday in September

Columbus Day

Second Monday in November

Veteran’s Day

November 11

Thanksgiving Day

Fourth Thursday in November

Christmas Day

December 25

A.2 BID SCHEDULE

CONTRACT LINE ITEM NUMBER (CLIN) 0001:

The Contractor is to provide all materials, labor, and equipment to provide construction services to remodel of x-ray labs number 1 and 3 to allow for new and updated equipment to be installed by the equipment supplier. Exam/x-ray room number 2 will only require adding additional data cables.

The contractor shall provide a price; Line Item 0001. See the SOW for details for requested pricing. The contractor shall include prices for all items listed in the pricing schedule and include all costs associated for work in the SOW, whether or not specifically listed in the pricing schedule. Work will be accomplished at the Cheyenne VAMC at 2360 E Pershing Blvd, Cheyenne, WY 82001.

CLIN
Description
Qty
Unit of issue

Firm Fixed Price Lump Sum Total amount

0001
Base Pricing

(SEE SOW FOR DETAILS)

Provide all work as described by the attached plans, specifications, and Wage Determinations for Veterans Administration project VA Project 442-18-002: Remodel Exam and X-ray room in radiology at the Cheyenne VAMC as described in the attached scope of work (SOW). Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 90 calendar days from receipt of notice to proceed.

1
Job
$

Grand Total

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

This is a Request for Proposal in accordance with FAR Part 13. Potential offerors must follow all instructions in order to be compliant with the solicitation.

It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.

The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ.

I.3A PRE-PROPOSAL SITE VISIT

A site visit will be held on 10 May at 10:00 AM Mountain Standard Time (MST). Interested contractors shall meet at the Cheyenne VAMC, Bldg 11, Engineering Conference Room. All offerors, consultants, subcontractors, manufacturers and suppliers are encouraged to attend this meeting to familiarize themselves with the project, project site, and to provide any questions in regard to this solicitation and project, in writing, prior to the scheduled conference date. See FAR Clause 52.236-3, Site Investigation and Conditions Affecting the Work, and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation.

I.4A SELECTION CRITERIA/PROPOSAL PREPARATION INSTRUCTIONS

Proposals will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:

Factor 1 – Past Performance Factor 2 - Safety Factor 3 – Price The Government reserves the right to award without discussions. Therefore, offerors are encouraged to provide their best proposals with the past performance information requested for evaluation. The Government, based on the proposal material presented, will award to the proposal that best demonstrates to be most advantageous for the Government.

Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. For purposes of this evaluation, a relevant project is further defined as experience repairing and replacing of automatic doors. Project shall have a minimum amount of $5,000.00 or more and completed within the past three years from the date of issuance of this RFP. The offeror shall submit past performance information using the Past Performance Questionnaire (PPQ) listed as an attachment to this solicitation. Include information that evidences customer satisfaction with offerors service and demonstrates offerors compliance with and fulfillment of the requirements of previous contracts. Completed PPQs should be submitted directly from your client via email to Shellie Murphy at Shellie.murphy@va.gov. If the offeror is unable to contact a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.

Basis of Evaluation: In order to be considered acceptable for this factor the offeror must have received satisfactory or better evaluations on a minimum of one (1) recent and relevant project.

In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. If that offeror is otherwise acceptable for non-price factors and has the lowest price the matter will be referred to the Small Business Administration for a Certificate of Competency, in accordance with the procedures contained in FAR Subpart 19.6, and 15 U.S.C. 637(b)(7).

Factor 2 – Safety

(a) Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

(1) OSHA or EPA Violation(s):

Offerors shall provide a letter affirming that the offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years. Additionally, the offeror may provide OSHA Form 300A, Summary of Work-Related Injuries and Illnesses to further substantiate this information.

(2) Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

(b) Basis of Evaluation: The Government will evaluate the documentation to ensure that the contractor has no more than three serious, or one repeat, or one willful OSHA or EPA violations(s) in the past three years; and must have an Experience Modification Rate (EMR) of equal to or less than 1.0.

Factor 3 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442 Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

•Comparison of proposed prices received in response to the RFP
•Comparison of proposed prices with the IGCE.
•Comparison of proposed prices with available historical information.

The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $25,000 and $100,000.

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.5B PROPOSAL REQUIREMENTS

General – Both technical and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email to shellie.murphy@va.gov. Emails are limited to five (5) MB. The proposal, in its entirety, shall not exceed two emails (one email for price proposal, and one email for technical proposal) of 5MB each. Technical proposals (not including past performance questionnaires) are limited to 30 pages. Price shall be in a separate electronic document from the technical and past performance portions of the proposal. The offeror’s technical response shall clearly address each evaluation factor listed in this solicitation. Failures to submit in the format required and clearly address those factors may result in rejection of the offer. Further details on electronic submission are outlined below. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Proposals shall be received by 2:00 PM MST on 22 May 2018. There will be no public opening of the proposals. Submit proposals to: shellie.murphy@va.gov.

Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control sufficient to establish appropriate status, offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation at the time of contract award. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of contract award will result in the offeror’s proposal being deemed non-responsive. All offerors are urged to contact the CVE and submit the aforementioned required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

I.6B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER

Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.

In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.

Acceptable Electronic Formats (Software) for Submission of Offers

1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Print or scan images of spreadsheets are not acceptable. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files)

1. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.

1. Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.

1. Please note that we can no longer accept .zip files due to increasing security concerns.

E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.

a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, or Bid depending on the solicitation type.

b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.

c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.

Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)

The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipients “inbox” is the official record of receipt.

Security Issues, Late Bids, Unreadable Offers

1. Late submission of offers are outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.

1. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.

1. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).

1. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.

1. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.2 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— 10 May2018, 1000 Mountain Standard Time

(c) Participants will meet at— Bldg 11, in the Engineering Conference Rm, Cheyenne VAMC (End of Provision)

2.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2016
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $36.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The offeror has completed the annual representations and certifications electronically via the SAM Web site accessed through https://www.acquisition.gov. After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause #
Title
Date
Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of Provision)

3.2 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

FAR Number
Title
Date
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

GENERAL CONDITIONS

4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days after receipt of award. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)

(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation…