36C25719Q1334-001.pdf
PDF 896 KB Posted
- Attached to
- NTX Ceiling Lifts Federal contract opportunity
- Solicitation number
- 36C25719Q1334
About this file
36C25719Q1334 36C25719Q1334.pdf
View the file
Other files for this federal contract opportunity
Show all 50
NTX Ceiling Lifts has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF 1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. DUNS: DUNS+4:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. 2/2012)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 82
549-19-2-205-0437
36C25719Q1334 08-20-2019
Rolando A Pasayan 210 694 6248 09-11-2019
1500 CST
Department of Veterans Affairs VISN17 Network Contracting Activity 7400 Merton Minter Blvd. (10N17/90C) San Antonio TX 78229
X 100
X
Y
339113
1000 Employees
N/A
X
DALLAS VA MEDICAL CENTER
LOGISTICS
4500 S. LANCASTER RD
DALLAS TX 75216
VISN17 Network Contracting Activity 7400 Merton Minter Blvd. (10N17/90C) San Antonio TX 78229
Electronic Submission of Invoices http://www.ob10.com/us/en/#&panel1-1 Austin, TX 78714-9971 for submitting invoices.
(877) 353-9791 (512) 460-5540
See CONTINUATION Page
This solicitation is for CEILING LIFTS for the Dallas VA and Bonham VA.
The Government intends to award a firm-fixed price contract to the Lowest Price Technically Acceptable (LPTA) vendor.
See schedule for details.
Site visit information will be attached with RFQ LAST day to submit questions for site visit is 08/27/2019
@ 1400 CST.
NO other questions will be answered after the 1st Amendment.
$0.00 See CONTINUATION Page
X X
Michael J. Tusinger Contracting Officer
36C25719Q1334
Table of Contents
SECTION A
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
B.2 INSTRUCTIONS TO OFFERORS
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
B.4 DELIVERY SCHEDULE
SECTION C - CONTRACT CLAUSES
C.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
C.2 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT
STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS (OCT 2018)
C.3 52.237-1 SITE VISIT (APR 1984)
C.4 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
C.5 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)
C.6 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND
COMPLIANCE (JUL 2018)
C.7 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
C.8 VAAR 852.246-71 REJECTED GOODS (OCT 2018)
C.9 VAAR 852.247-73 PACKING FOR DOMESTIC SHIPMENT (OCT 2018)
C.10 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN
2008)
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS
SECTION E - SOLICITATION PROVISIONS
E.1 GRAY MARKET LANGUAGE (MAY 2016)
E.2 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
E.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
E.4 52.233-2 SERVICE OF PROTEST (SEP 2006)
E.5 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION
(OCT 2018)
E.6 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
E.7 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014)
E.8 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—
COMMERCIAL ITEMS (OCT 2018)
E.9 VAAR 852.273-74 AWARD WITHOUT EXCHANGES (JAN 2003)
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C257
VISN17 Network Contracting Activity
7400 Merton Minter Blvd. (10N17/90C)
San Antonio TX 78229
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
[x] 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or
[] 52.232-36, Payment by Third Party
3. INVOICES: Invoices shall be submitted in arrears:
a. Quarterly []
b. Semi-Annually []
c. Other [X] Upon Receipt
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
Department of Veterans Affairs
Electronic Submission of Invoices http://www.ob10.com/us/en/#&panel1-1
Austin, TX 78714-9971 for submitting invoices.
B.2 INSTRUCTIONS TO OFFERORS
Evaluation Factors for Award
This solicitation is issued as a Total SDVOSB set-aside. The vendor must be registered for NAICS 339113 in SAM to be eligible for award.
Quotations due 09/11/2019 at 3:00 p.m. CST.
Email quotes to rolando.pasayan@va.gov
Point of Contact:
Rolando A. Pasayan
Contract Administrator
Regional Procurement Office West (RPO West)
Network Contracting Office 17 (NCO 17)
7400 Merton Minter Blvd. (10N17/90C)
San Antonio, TX 78229
Phone: 210-694-6248 rolando.pasayan@va.gov
Late quotes or documentation will not be accepted. All questions, comments, or inquiries are to be submitted in writing to the Point of Contact, referenced above, prior to the closing of the solicitation.
I. Basis of Award
The Government intends to award a contract resulting from this solicitation to the responsible offeror whose quote conforming to the solicitation meets or exceeds the requirement at the lowest price, Lowest Price Technically Acceptable (LPTA). The quotes will be evaluated based on the evaluation factors listed below. The technical acceptability will be evaluated on an "acceptable" or "unacceptable" basis. The lowest price contractor will first be evaluated. If determined to be technically “unacceptable,” the next lowest price response will be evaluated, and so on, until an offer is determined to be “acceptable.” The following areas will be evaluated:
mailto:susan.flores2@va.gov
EVALUATION FACTOR CRITERIA:
1. TECHNICAL-Contractor Shall address each technical evaluation criteria sub category, a – i for their respective quote to be technically acceptable. Those offerors who fail to address each sub category will not be eligible to receive the award.
a. Ceiling lifts must have a continuous charge rail that charges the lift anywhere in the room and must have been successfully proven to work with existing supports which are Guldmann GH2 ceiling mounts and wall mounts; otherwise, new supports must be included in the quote. Ceiling lifts that are to be placed on existing Guldmann GH2 ceiling lift rail must be proven to charge and be safe and functional on those rails;
otherwise, new rail must be included in the quote. Ceiling lift rail designs must avoid blocking the function of privacy curtains.
b. Ceiling lifts must have a double positioning lock feature where specified, and on those specified lifts, the motion of the traverse or lift on the traverse must be able to be stopped independently.
c. Ceiling lifts must comply with ISO 10535 and UL standards and be suitable for heavy, repeated use as found in an intensive care, therapy or radiology environment, including repeated repositioning operations such as one 20-second-long heavy lift per minute for 4 minutes.
d. Ceiling lifts must have weight capacities and scales as specified in the Statement of Work pages 4-28, with compact 2-point hanger bars that are quickly removable without tools. Rubber flaps are not acceptable. . Scales must display weight in pounds or kilograms on the hand control and must not reduce lifting height, and the hand control must stay connected to the lift.
e. Ceiling lifts must be compatible with and warranted for use with other manufacturers’ loop slings that are suitable for 2-point hanger bars, including the full range of Guldmann lifting, therapy, and repositioning slings, Alpha Modalities repositioning and lifting slings, Barton car slings, Medco ambulation slings, Horcher loop-based lifting and repositioning slings, Invacare lifting slings, HoverTech HoverSlings, and EZ-Way lifting and ambulation slings.
f. Ceiling lifts must be able to lower patients easily in an emergency without the use of a ladder or tools, with a sustained pull on a red cord.
g. Ceiling lifts must allow sleep in inpatient rooms, including no warning beeps or flashing lights during normal operation or when there are battery problems.
h. Quote must have a minimum of a 3 year warranties on tracks, installation, motors, and all newly installed parts and must cover labor, shipping, and travel. This warranty service is expected to be generally completed onsite and must not require facility staff to ship a lift back to the vendor.
i. Vendor must describe how they will ensure minimal downtime when support and parts are needed during the warranty period and how they will provide education for users and biomedical engineering staff.
2. PAST EXPERIENCE:
Contractors shall provide a minimum of three (3) references indicating same/ similar services/projects for similar installations, including room-coverage systems mounted both by wall and by ceiling, curtain crossing, and connections between rooms., Contractor shall also list number of years’ experience with installation onto Guldmann continuous-charge rails and supports.
3. PRICE - Contractor shall complete B.4 Price/Cost Schedule. The schedule may be altered, or an alternate schedule used where appropriate in order to express quote details.
The Government intends to award the contract resulting from this solicitation without discussions. However, the Government reserves the right to conduct discussions if it determines discussions to be in its best interest.
Statement of Work: Ceiling lift Replacements in Dallas VAMC and Bonham VA
A. General Information
1. Title of Project: Ceiling lift Replacements in Dallas VAMC and Sam Rayburn Memorial Veterans Center
2. Scope of Work: The contractor shall provide all labor, supervision and all other resources required to deliver the requirements stated herein, except as may otherwise be specified in this statement of work. 550-pound, 770-pound, or 825-pound advanced ceiling lifts as specified (with fast motion, continuous-charge room-covering rail systems, and tool-free emergency lowering, plus scales where specified) are to be delivered, installed, and tested, in up to 309 places as listed in the location list. In each case, functioning lifts will be traded in (and there will be 6 extra traded-in motors because the GH2 Twin lifts had two lifts each). Any discount associated with trade-in must be noted on the bid. Deinstallation and disposal of old lifts and unneeded rail and hardware is the contractor’s responsibility. All work must be coordinated with COR and Supply Chain Management Services in order to coordinate paperwork, and all new and decommissioned lifts must be taken to PPM in the Warehouse (Bldg 44 in Dallas; bldg.
10 in Bonham) for inventory record/sticker purposes. In large rooms to be specified below, new continuous-charge rail will be required and will need to attach to existing structural supports. Some of those rooms, as specified, will require a redesign to accommodate curtains and door widths (likely to mean the traveling rail is the longer rail). Locations are in Dallas VAMC and Sam Rayburn Memorial Veterans Center (Bonham). Installation/replacement will need to be timed according to availability of rooms. Details are provided in sections C and D below, Specific Mandatory Tasks and
Associated Deliverables. If proposed cost exceeds budget, VA will prioritize and specify final lift replacement locations.
3. Background: Ceiling lifts have been installed in many places throughout the VA North Texas Health Care System. The Arjo Maxi Sky lifts in SCI Outpatient Clinic are currently the oldest in the building, from 2006, and are breaking down often enough to warrant replacement. The GH2 lifts installed in 2008 and 2009 will be unsupported by the manufacturer as of 2020, so we are starting the process of replacing them. This first set of upgrades will include only systems that do not have continuous charge, so that we solve a problem of usability caused by the older charging stations. These systems integrate into an existing system in which mostly Guldmann ceiling lifts (with ceiling lifts from 3 other manufacturers and floor lifts from 7 manufacturers scattered throughout the facility) are used to lift, transfer, and reposition inpatients and outpatients. Patients may arrive at any of these locations on a sling or be sent on to another location on a sling applied at these locations. The systems being installed here are being installed in areas that already contain similar equipment. They may also receive patients wearing assorted brands of slings from home or may need to use slings from Barton/Humancare, Guldmann, and/or Alpha Modalities to lift patients and send them to other departments.
Staff from other parts of the facility participate in transfers in Radiology, so compatibility and similar operation are important.
4. Performance Period/Schedule: The contractor shall start the work required under this SOW by about October 2019 and coordinate installation with room availability unless otherwise directed by the Contracting Officer (CO). It is anticipated that this quantity of lift replacements may require up to a year to complete. If the contractor proposes an earlier completion date, and the Government accepts the contractor’s proposal, the contractor’s proposed completion date shall prevail. Installation dates and designs must be coordinated with Contracting Officer Representative (COR), and dates for installation in remodeling projects may be adjusted by the Government as required if engineering changes are required and delayed.
5. Type of Contract: Firm-Fixed-Price B. Contract Award Meeting
1. The contractor shall not commence performance on the tasks in this SOW until the CO has conducted a kick off meeting, or has advised the contractor that a kick off meeting is waived.
C. General Requirements
1. All installation must comply with requirements of Patient Safety Alert AL14-07, including the Checklist for Installation and Relocation. The installation checklist must be filled out for each installed lift, in addition to any checklist required by the manufacturer, and supplied to the COR.
AL14-07PSAChecklist forInstallationandRelo
2. Contractor will provide evaluation of existing structure where ceiling lifts are needed and submission of plans to VA North Texas Healthcare System Engineering service, to assure that workable systems are installed and comply with VA design requirements and relevant standards.
3. Contractor will coordinate with Engineering service to verify access to engineering mechanical, HVAC, and fire systems components within the mounting area of the lift units.
4. Contractor will coordinate with Contracting Officer Representative (COR) to schedule installations.
5. Contractor will provide information on minimum clearances for operation of each lift, to be presented with the bid.
6. Contractor will provide a list of all construction or modifications required to install these lifts, to be presented with the bid. The goal is to install around any obstructions without requiring VA to make construction modifications.
7. Contractor will provide all qualified personnel, materials, equipment and services necessary to install ceiling lifts for the rooms described below under Location, including lifts, tracks, spreader bars, attachment hardware, and all other equipment necessary for safe operation. Detailed requirements are described in the Standards and Special Requirements sections. Lift systems may be configured in any way that covers the rooms best and meets the requirements.
8. Contractor will provide installation and testing of all equipment for ceiling lifts, according to VA checklist requirements, resulting in a turnkey system.
9. Contractor will provide training on equipment use for all new types of equipment included in this contract, one session per shift for up to 2 shifts of personnel in each affected area and for onsite trainers (up to 10 sessions scheduled after installation and before use), in coordination with COR.
10. Contractor will provide evidence of testing of all lift systems provided and schedule testing when it can be overseen by COR.
11. Contractor will mitigate any new hazards created by installation, such as ramps over interstitial support beams that create trip hazards.
12. Contractor will meet construction safety requirements, including construction orientation, safety training requirements, dust control requirements from the Infection Control Risk Assessment, TB testing, electrical safety requirements, and Above Ceiling Permit requirements including re-sealing any penetrations of fire barriers.
D. NARA Records Management Language Clause
1. Citations to pertinent laws, codes and regulations such as 44 U.S.C Chapter 21 , 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.
2. Contractor shall treat all deliverables under the contract as the property of the U.S.
Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government ‘IT’ equipment and/or Government records.
4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.
5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
6. The Government Agency owns the rights to all data/records produced as part of this contract.
7. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
8. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].
9. No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.
10. Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under or relating to this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.
E. Specific Mandatory Tasks and Associated Deliverables
1. Location of Ceiling Lift Installations: VA North Texas Healthcare System, Dallas VA
Medical Center (4500 S Lancaster Rd, Dallas, TX 75216), and Sam Rayburn Memorial Veterans Center (1201 E 9th St., Bonham, TX 75418). Rooms are listed below, along with the required capacity and whether scale is required, and drawings are posted with the announcement:
Item # Bldg Area Room # Lbs. Scal e
Design Timing
1 60 CLC PT
(center)
124 550 Y New continuous-charge XY rail, using existing supports if possible, in very large room. Can change orientation of lift rails, but existing structure is preferred.
Coordinated with COR and
CLC PM&R
staff
2 60 CLC PT
(center)
124 550 Y New continuous-charge XY rail, using existing supports if possible, in very large room. Can change orientation of lift rails, but existing structure is preferred.
Coordinated with COR and
CLC PM&R
staff
3 74 SCI 1D-127 "E" 550 Yes New continuous-charge XY system, mounted to steel above
Coordinated with COR and SCI managers ceiling or wall mounted (replacing ARJO system)
4 74 SCI 1D-131 "F" 550 Yes New continuous-charge XY system, mounted to steel above ceiling or wall mounted (replacing ARJO system)
Coordinated with COR and SCI managers
5 74 SCI 1D-133 "D" 550 Yes New continuous-charge XY system, mounted to steel above ceiling or wall mounted (replacing ARJO system)
Coordinated with COR and SCI managers
6 74 SCI 1D-134 "C" 550 Yes New continuous-charge XY system, mounted to steel above ceiling or wall mounted (replacing ARJO system)
Coordinated with COR and SCI managers
7 74 SCI 1D-138 "B" 550 Yes New continuous-charge XY system, mounted to steel above ceiling or wall mounted (replacing ARJO system)
Coordinated with COR and SCI managers
8 74 SCI 1D-140 "A" 550 Yes New continuous-charge XY system, mounted to steel above ceiling or wall mounted (replacing ARJO system)
Coordinated with COR and SCI managers
9 60 Dallas
CLC-B
B112 770 Yes New continuous-charge rails on redesigned supports to accommodate curtains and door opening (specify and test rail only for 1000 pound capacity)
Coordinated with COR and CLC managers
10 2J 5A 5A-280 825 Yes New continuous-charge rails on existing supports (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and 5A managers
11 2J TICU 2 5B-252P 825 Yes New continuous-charge rails on existing supports (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and
SICU/TICU
managers
12 2J CCU 9 5A-124L 825 Yes Existing continuous-charge rail (specify and
Coordinated with COR, Bed test rail only for 1000 pound capacity)
Control, and
MICU/CCU
managers
13 2J MICU 2 5A-109K 825 Yes Existing continuous-charge rail (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and
MICU/CCU
managers
14 2J MICU 9 5A-109S 825 Yes Existing continuous-charge rail (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and
MICU/CCU
managers
15 2J SICU 12 5B-202T 825 Yes Existing continuous-charge rail (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and
SICU/TICU
managers
16 2J SICU 7 5B-202N 825 Yes Existing continuous-charge rail (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and
SICU/TICU
managers
17 2J CCU 4 5A-124F 825 Yes Existing continuous-charge rail (specify and test rail only for 1000 pound capacity)
Coordinated with COR, Bed Control, and
MICU/CCU
managers
18 60 Dallas
CLC-A
A156A Shower
550 No New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
19 60 Dallas
CLC-A
A156 Shower
550 No New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
20 60 Dallas
CLC-A
B156 550 No New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
21 60 Dallas Hospice
C-108 left 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
22 74 Dallas SCI
PT
1B-208 PT
clinic (Combi lock)
550 Yes Rail redesign with PT input for wider traverse covering areas adjoining mat and up to the edge of the switch track; double positioning lock to stop movement in either/both directions.
Sever connection to straight track. Attached to steel.
Coordinated with COR and
SCI PT
management
23 74 Dallas SCI
PT
PT clinic (Switch track)
550 Yes Keep existing switch track system; allow continuous charge.
Attached to steel.
Coordinated with COR and
SCI PT
management
24 29 Bonham
CLC-B
C3402 550 Yes New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
25 29 Bonham
CLC-C
B2402A 550 Yes New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
26 60 Dallas
CLC-A
107 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
27 60 Dallas
CLC-A
106 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
28 60 Dallas
CLC-A
105 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
29 60 Dallas
CLC-B
119 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
30 60 Dallas
CLC-B
120 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
31 60 Dallas
CLC-B
103 BATH 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
32 60 Dallas
CLC-B
103 Left 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
33 60 Dallas
CLC-B
103 Right 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
34 60 Dallas
CLC-B
104 BATH 550 No New continuous-charge rails on existing supports; shower area
Coordinated
CLC managers means water protection is required
35 60 Dallas
CLC-B
104 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
36 60 Dallas
CLC-A
103 BATH 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
37 60 Dallas
CLC-A
103 right 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
38 60 Dallas
CLC-A
103 left 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
39 60 Dallas
CLC-A
133 BATH 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
40 60 Dallas
CLC-A
133 left 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
41 60 Dallas
CLC-A
133 right 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
42 60 Dallas
CLC-B
105 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
43 60 Dallas
CLC-B
106 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
44 60 Dallas
CLC-B
107 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
45 60 Dallas
CLC-B
108 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
46 60 Dallas
CLC-B
109 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
47 60 Dallas
CLC-B
110 550 Yes New continuous-charge rails on existing supports
Coordinated
48 60 Dallas
CLC-A
104 BATH 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
49 60 Dallas
CLC-A
104 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
50 60 Dallas
CLC-A
108 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
51 60 Dallas
CLC-A
109 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
52 60 Dallas
CLC-A
110 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
53 60 Dallas
CLC-A
118 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
54 60 Dallas
CLC-A
119 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
55 60 Dallas
CLC-A
120 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
56 60 Dallas
CLC-A
121 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
57 60 Dallas
CLC-A
122 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
58 60 Dallas
CLC-A
123 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
59 60 Dallas
CLC-A
124 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated
60 60 Dallas
CLC-A
125 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
61 60 Dallas
CLC-A
126 770 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
62 60 Dallas
CLC-A
127 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
63 60 Dallas
CLC-A
128 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
64 60 Dallas
CLC-A
129 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
65 60 Dallas
CLC-A
130 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
66 60 Dallas
CLC-A
131 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
67 60 Dallas
CLC-A
132 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
68 60 Dallas
CLC-A
132 bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
69 60 Dallas
CLC-A
112 bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
70 60 Dallas
CLC-A
125 bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
71 60 Dallas
CLC-B
113 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
72 60 Dallas
CLC-B
114 550 Yes New continuous-charge rails; new room design to
Coordinated accommodate curtains and door opening
73 60 Dallas
CLC-B
115 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
74 60 Dallas
CLC-B
116 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
75 2 4C 221 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
76 60 Dallas
CLC-B
118 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
77 60 Dallas
CLC-B
121 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
78 60 Dallas
CLC-B
122 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
79 60 Dallas
CLC-B
123 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
80 60 Dallas
CLC-B
124 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
81 60 Dallas
CLC-B
125 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
82 60 Dallas
CLC-B
126 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
83 60 Dallas
CLC-B
127 550 Yes New continuous-charge rails on existing supports
Coordinated
84 60 Dallas
CLC-B
128 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
85 60 Dallas
CLC-B
129 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
86 60 Dallas
CLC-B
130 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
87 60 Dallas
CLC-B
131 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
88 60 Dallas
CLC-B
132 550 Yes New continuous-charge rails; new room design to accommodate curtains and door opening
Coordinated with COR and CLC managers
89 60 Dallas
CLC-B
113 Bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
90 60 Dallas
CLC-B
125 Bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
91 60 Dallas
CLC-B
130 Bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
92 60 Dallas
CLC-B
132 Bath 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
93 60 Dallas Hospice
C-108 right 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
94 60 Dallas Hospice
C-116 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
95 Bonha m
NHCU
C 3201 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
96 Bonha m
NHCU
C 3202 550 Yes New continuous-charge rails on existing supports
Coordinated
97 Bonha m
NHCU
C 3203 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
98 Bonha m
NHCU
C 3204 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
99 Bonha m
NHCU
C 3205 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
100 Bonha m
NHCU
C 3206 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
101 Bonha m
NHCU
C 3207 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
102 Bonha m
NHCU
C 3208 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
103 Bonha m
NHCU
C 3306 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
104 Bonha m
NHCU
C 3308 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
105 Bonha m
NHCU
C 3401 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
106 Bonha m
NHCU
C 3403 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
107 Bonha m
NHCU
C 3404 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
108 Bonha m
NHCU
C 3405 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
109 Bonha m
NHCU
C 3406 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
110 Bonha m
NHCU
C 3407 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
111 Bonha m
NHCU
C 3408 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
112 Bonha m
NHCU
C 3201-2BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
113 Bonha m
NHCU
C 3203BR 550 No New continuous-charge rails on existing supports; shower area
Coordinated means water protection is required
114 Bonha m
NHCU
C 3205-7BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
115 Bonha m
NHCU
C 3206-8BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
116 Bonha m
NHCU
C 3401-3BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
117 Bonha m
NHCU
C 3404BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
118 Bonha m
NHCU
C 3405-7BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
119 Bonha m
NHCU
C 3406-8BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
120 Bonha m
NHCU
C C3208-
10BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
121 Bonha m
NHCU
C C3209-11 bath
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
122 Bonha m
NHCU
C C3209-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
123 Bonha m
NHCU
C C3210 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
124 Bonha m
NHCU
C C3211 550 Yes New continuous-charge rails on existing supports
Coordinated
125 Bonha m
NHCU
C C3409-
11BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
126 Bonha m
NHCU
C C3409-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
127 Bonha m
NHCU
C C3410-
12BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
128 Bonha m
NHCU
C C3410-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
129 Bonha m
NHCU
C C3411 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
130 Bonha m
NHCU
C C3412 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
131 Bonha m
NHCU
B 2201 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
132 Bonha m
NHCU
B 2202 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
133 Bonha m
NHCU
B 2203 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
134 Bonha m
NHCU
B 2204 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
135 Bonha m
NHCU
B 2205 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
136 Bonha m
NHCU
B 2206 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
137 Bonha m
NHCU
B 2207 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
138 Bonha m
NHCU
B 2301 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
139 Bonha m
NHCU
B 2303 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
140 Bonha m
NHCU
B 2304 550 Yes New continuous-charge rails on existing supports
Coordinated
141 Bonha m
NHCU
B 2305 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
142 Bonha m
NHCU
B 2306 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
143 Bonha m
NHCU
B 2307 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
144 Bonha m
NHCU
B 2308 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
145 Bonha m
NHCU
B 2401 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
146 Bonha m
NHCU
B 2403 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
147 Bonha m
NHCU
B 2404 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
148 Bonha m
NHCU
B 2405 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
149 Bonha m
NHCU
B 2406 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
150 Bonha m
NHCU
B 2407 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
151 Bonha m
NHCU
B 2408 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
152 Bonha m
NHCU
B 2201-02BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
153 Bonha m
NHCU
B 2203BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
154 Bonha m
NHCU
B 2204BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
155 Bonha m
NHCU
B 2205-7BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated
156 Bonha m
NHCU
B 2301-3BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
157 Bonha m
NHCU
B 2304BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
158 Bonha m
NHCU
B 2305-7BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
159 Bonha m
NHCU
B 2401-3BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
160 Bonha m
NHCU
B 2404BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
161 Bonha m
NHCU
B 2405-7BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
162 Bonha m
NHCU
B 2406-8BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
163 Bonha m
NHCU
B B2208-
10BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
164 Bonha m
NHCU
B B2209-
11BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
165 Bonha m
NHCU
B B2208-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
166 Bonha m
NHCU
B B2209-A 550 Yes New continuous-charge rails on existing supports
Coordinated
167 Bonha m
NHCU
B B2210 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
168 Bonha m
NHCU
B B2211 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
169 Bonha m
NHCU
B B2306-8BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
170 Bonha m
NHCU
B B2309-
11BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
171 Bonha m
NHCU
B B2309-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
172 Bonha m
NHCU
B B2310-
12BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
173 Bonha m
NHCU
B B2310-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
174 Bonha m
NHCU
B B2311 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
175 Bonha m
NHCU
B B2312 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
176 Bonha m
NHCU
B B2409-
11BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
177 Bonha m
NHCU
B B2409-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
178 Bonha m
NHCU
B B2410-
12BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
179 Bonha m
NHCU
B B2410-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
180 Bonha m
NHCU
B B2411 550 Yes New continuous-charge rails on existing supports
Coordinated
181 Bonha m
NHCU
B B2412 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
182 Bonha m
NHCU
C C3301-3BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
183 Bonha m
NHCU
C C3303 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
184 Bonha m
NHCU
C C3305 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
185 Bonha m
NHCU
C C3305-7BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
186 Bonha m
NHCU
C C3306-8BR 550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
187 Bonha m
NHCU
C C3307 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
188 Bonha m
NHCU
C C3309-
11BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
189 Bonha m
NHCU
C C3309-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
190 Bonha m
NHCU
C C3310-
12BR
550 No New continuous-charge rails on existing supports; shower area means water protection is required
Coordinated with COR and CLC managers
191 Bonha m
NHCU
C C3310-A 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
192 Bonha m
NHCU
C C3312 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and CLC managers
193 Bonha m/1
OPC Bldg
403 (Moving to Bldg 2 room 303)
550 Yes NEW LOCATION: new continuous-charge rail and support in Bldg 2 room 303 (with concrete deck above old non-needed plaster
Coordinated with COR and
OPC
managers ceiling, lift size ~4x4 meters)
194 Bonha m/1
OPC Bldg
320 (Moving to Bldg 1 room 132)
550 Yes NEW LOCATION: new continuous-charge rail and support in room 132 (with concrete deck and steel to attach to, lift size ~3x3 meters)
Coordinated with COR and
OPC
managers
195 2J 5A 5A-224 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
196 2J 5A 5A-228 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
197 2J 5A 5A-230 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
198 2J 5A 5A-248 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
199 2J 5A 5A-250 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
200 2J 5A 5A-262 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
201 2J 5A 5A-264 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
202 2J 5A 5A-284 550 Yes New continuous-charge rails on existing supports
Coordinated with COR and unit managers
203 2J 5A 5A-286 550 Yes New continuous-charge rails on existing…