This document is a Standard Form 1449 Solicitation/Contract/Order for Commercial Products and Commercial Services issued by the Department of Veterans Affairs Veterans Health Administration Network Contracting Office. The solicitation (36C25625Q1473) is a total Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside for fire damper inspection and testing services at the John L. McClellan and North Little Rock VA Medical Centers.
The contract requires inspecting approximately 309 fire dampers across two facilities, with a 90-day performance period from November 3, 2025, to March 31, 2026. Key requirements include testing each fire damper to ensure operational compliance, making dampers accessible, repairing or replacing compromised components, and creating detailed inspection reports with before and after photographs. The inspection will be conducted in phases, with 103 dampers to be inspected at 30-day intervals. The contract type is Firm Fixed Price, and a site visit for interested parties is scheduled for October 10, 2025, at the North Little Rock Building Fire Station. All questions must be submitted to the contracting officer by October 14, 2025, at 10:00 AM CST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25625Q1473 0001.docx | DOCX document | |
| Wage Determination 15-5117.txt | TXT text file | |
| JLM Ground to 9th floor life safety drawings.pdf | ||
| NLR-Bldg--170---Dampers 6 year.xlsx | XLSX spreadsheet | |
| LRVA Medical-Center---Dampers 6 year.xlsx | XLSX spreadsheet | |
| North Little Rock ground to 4th floor life safety drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25625Q1473
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
36C25625Q1473 Andrew Misfeldt andrew.misfeldt@va.gov 10-24-2025 10:00
CDT
Department of Veterans Affairs Veterans Health Administration Network Contracting Office 16 2575 Keystone Crossing Fayetteville
AR
72703 X X 541350 $11.5 Million N/A X Department of Veterans Affairs John L McClellan Veterans Health 4300 West 7th Street Little Rock
AR
72205 Department of Veterans Affairs Veterans Healthcare System of the Ozarks Network Contracting Office 16 2575 Keystone Crossing Fayetteville
AR
72703
FSC e-Invoice Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 invoice must be submitted electronically
1-877-489-6135 See CONTINUATION Page Provide fire damper inspection as outlined in the SOW.
A site visit for interested parties will be held on 10OCT2025 at 900am. Meet at NLR Building Fire Station.
All questions must be submitted to andrew.misfeldt@va.gov no latter than 14OCT2025 10:00 AM (CST).
Contract type will be Firm Fixed Price (FFP).
See CONTINUATION Page X Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 3 |
| B.1 CONTRACT ADMINISTRATION DATA | 3 |
| B.2 IT CONTRACT SECURITY | 4 |
| B.3 PRICE/COST SCHEDULE | 18 |
| ITEM INFORMATION | 18 |
| SECTION C - CONTRACT CLAUSES | 19 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023) | 19 |
| C.2 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999) | 24 |
| C.3 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 25 |
| C.4 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) | 28 |
| C.5 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 29 |
| C.6 VAAR 852.237-75 KEY PERSONNEL (OCT 2019) | 31 |
| C.7 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 31 |
| C.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 31 |
| C.9 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (JAN 2025) (DEVIATION FEB 2025) | 32 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 41 |
| SECTION E - SOLICITATION PROVISIONS | 42 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (SEP 2023) | 42 |
| E.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 46 |
| E.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023) | 49 |
| E.4 52.216-1 TYPE OF CONTRACT (APR 1984) | 50 |
| E.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 50 |
| E.6 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024) (DEVIATION FEB 2025) | 51 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C256 Department of Veterans Affairs Veterans Health Administration Network Contracting Office 16 2575 Keystone Crossing Fayetteville AR 72703
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] Upon Completion and Report Acceptance with all deliverables |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
B.2 IT CONTRACT SECURITY
VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY
1. GENERAL
Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.
2. ACCESS TO VA INFORMATION AND VA INFORMATION SYSTEMS
a. A contractor/subcontractor shall request logical (technical) or physical access to VA information and VA information systems for their employees, subcontractors, and affiliates only to the extent necessary to perform the services specified in the contract, agreement, or task order.
b. All contractors, subcontractors, and third-party servicers and associates working with VA information are subject to the same investigative requirements as those of VA appointees or employees who have access to the same types of information. The level and process of background security investigations for contractors must be in accordance with VA Directive and Handbook 0710, Personnel Suitability and Security Program. The Office for Operations, Security, and Preparedness is responsible for these policies and procedures.
c. Contract personnel who require access to national security programs must have a valid security clearance. National Industrial Security Program (NISP) was established by Executive Order 12829 to ensure that cleared U.S. defense industry contract personnel safeguard the classified information in their possession while performing work on contracts, programs, bids, or research and development efforts. The Department of Veterans Affairs does not have a Memorandum of Agreement with Defense Security Service (DSS). Verification of a Security Clearance must be processed through the Special Security Officer located in the Planning and National Security Service within the Office of Operations, Security, and Preparedness.
d. Custom software development and outsourced operations must be located in the U.S. to the maximum extent practical. If such services are proposed to be performed abroad and are not disallowed by other VA policy or mandates, the contractor/subcontractor must state where all non-U.S. services are provided and detail a security plan, deemed to be acceptable by VA, specifically to address mitigation of the resulting problems of communication, control, data protection, and so forth. Location within the U.S. may be an evaluation factor.
e. The contractor or subcontractor must notify the Contracting Officer immediately when an employee working on a VA system or with access to VA information is reassigned or leaves the contractor or subcontractor's employ. The Contracting Officer must also be notified immediately by the contractor or subcontractor prior to an unfriendly termination.
3. VA INFORMATION CUSTODIAL LANGUAGE
a. Information made available to the contractor or subcontractor by VA for the performance or administration of this contract or information developed by the contractor/subcontractor in performance or administration of the contract shall be used only for those purposes and shall not be used in any other way without the prior written agreement of the VA. This clause expressly limits the contractor/subcontractor's rights to use data as described in Rights in Data - General, FAR 52.227-14(d) (1).
b. VA information should not be co-mingled, if possible, with any other data on the contractors/subcontractor's information systems or media storage systems in order to ensure VA requirements related to data protection and media sanitization can be met. If co-mingling must be allowed to meet the requirements of the business need, the contractor must ensure that VA's information is returned to the VA or destroyed in accordance with VA's sanitization requirements. VA reserves the right to conduct on site inspections of contractor and subcontractor IT resources to ensure data security controls, separation of data and job duties, and destruction/media sanitization procedures are in compliance with VA directive requirements.
c. Prior to termination or completion of this contract, contractor/ subcontractor must not destroy information received from VA, or gathered/ created by the contractor in the course of performing this contract without prior written approval by the VA. Any data destruction done on behalf of VA by a contractor/subcontractor must be done in accordance with National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management and its Handbook 6300.1 Records Management Procedures, applicable VA Records Control Schedules, and VA Handbook 6500.1, Electronic Media Sanitization. Self-certification by the contractor that the data destruction requirements above have been met must be sent to the VA Contracting Officer within 30 days of termination of the contract.
d. The contractor/subcontractor must receive, gather, store, back up, maintain, use, disclose and dispose of VA information only in compliance with the terms of the contract and applicable Federal and VA information confidentiality and security laws, regulations and policies. If Federal or VA information confidentiality and security laws, regulations and policies become applicable to the VA information or information systems after execution of the contract, or if NIST issues or updates applicable FIPS or Special Publications (SP) after execution of this contract, the parties agree to negotiate in good faith to implement the information confidentiality and security laws, regulations and policies in this contract.
e. The contractor/subcontractor shall not make copies of VA information except as authorized and necessary to perform the terms of the agreement or to preserve electronic information stored on contractor/subcontractor electronic storage media for restoration in case any electronic equipment or data used by the contractor/subcontractor needs to be restored to an operating state. If copies are made for restoration purposes, after the restoration is complete, the copies must be appropriately destroyed.
f. If VA determines that the contractor has violated any of the information confidentiality, privacy, and security provisions of the contract, it shall be sufficient grounds for VA to withhold payment to the contractor or third party or terminate the contract for default or terminate for cause under Federal Acquisition Regulation (FAR) part 12.
g. If a VHA contract is terminated for cause, the associated BAA must also be terminated and appropriate actions taken in accordance with VHA Handbook 1600.01, Business Associate Agreements. Absent an agreement to use or disclose protected health information, there is no business associate relationship.
h. The contractor/subcontractor must store, transport, or transmit VA sensitive information in an encrypted form, using VA-approved encryption tools that are, at a minimum, FIPS 140-2 validated.
i. The contractor/subcontractor's firewall and Web services security controls, if applicable, shall meet or exceed VA's minimum requirements. VA Configuration Guidelines are available upon request.
j. Except for uses and disclosures of VA information authorized by this contract for performance of the contract, the contractor/subcontractor may use and disclose VA information only in two other situations: (i) in response to a qualifying order of a court of competent jurisdiction, or (ii) with VA's prior written approval. The contractor/subcontractor must refer all requests for, demands for production of, or inquiries about, VA information and information systems to the VA contracting officer for response.
k. Notwithstanding the provision above, the contractor/subcontractor shall not release VA records protected by Title 38 U.S.C. 5705, confidentiality of medical quality assurance records and/or Title 38 U.S.C. 7332, confidentiality of certain health records pertaining to drug addiction, sickle cell anemia, alcoholism or alcohol abuse, or infection with human immunodeficiency virus. If the contractor/subcontractor is in receipt of a court order or other requests for the above mentioned information, that contractor/subcontractor shall immediately refer such court orders or other requests to the VA contracting officer for response.
l. For service that involves the storage, generating, transmitting, or exchanging of VA sensitive information but does not require C&A or an MOU-ISA for system interconnection, the contractor/subcontractor must complete a Contractor Security Control Assessment (CSCA) on a yearly basis and provide it to the COR.
4. INFORMATION SYSTEM DESIGN AND DEVELOPMENT
a. Information systems that are designed or developed for or on behalf of VA at non-VA facilities shall comply with all VA directives developed in accordance with FISMA, HIPAA, NIST, and related VA security and privacy control requirements for Federal information systems. This includes standards for the protection of electronic PHI, outlined in 45 C.F.R. Part 164, Subpart C, information and system security categorization level designations in accordance with FIPS 199 and FIPS 200 with implementation of all baseline security controls commensurate with the FIPS 199 system security categorization (reference Appendix D of VA Handbook 6500, VA Information Security Program). During the development cycle a Privacy Impact Assessment (PIA) must be completed, provided to the COR, and approved by the VA Privacy Service in accordance with Directive 6507, VA Privacy Impact Assessment.
b. The contractor/subcontractor shall certify to the COR that applications are fully functional and operate correctly as intended on systems using the VA Federal Desktop Core Configuration (FDCC), and the common security configuration guidelines provided by NIST or the VA. This includes Internet Explorer 7 configured to operate on Windows XP and Vista (in Protected Mode on Vista) and future versions, as required.
c. The standard installation, operation, maintenance, updating, and patching of software shall not alter the configuration settings from the VA approved and FDCC configuration. Information technology staff must also use the Windows Installer Service for installation to the default "program files" directory and silently install and uninstall.
d. Applications designed for normal end users shall run in the standard user context without elevated system administration privileges.
e. The security controls must be designed, developed, approved by VA, and implemented in accordance with the provisions of VA security system development life cycle as outlined in NIST Special Publication 800-37, Guide for Applying the Risk Management Framework to Federal Information Systems, VA Handbook 6500, Information Security Program and VA Handbook 6500.5, Incorporating Security and Privacy in System Development Lifecycle.
f. The contractor/subcontractor is required to design, develop, or operate a System of Records Notice (SOR) on individuals to accomplish an agency function subject to the Privacy Act of 1974, (as amended), Public Law 93-579, December 31, 1974 (5 U.S.C. 552a) and applicable agency regulations. Violation of the Privacy Act may involve the imposition of criminal and civil penalties.
g. The contractor/subcontractor agrees to:
(1) Comply with the Privacy Act of 1974 (the Act) and the agency rules and regulations issued under the Act in the design, development, or operation of any system of records on individuals to accomplish an agency function when the contract specifically identifies:
(a) The Systems of Records (SOR); and
(b) The design, development, or operation work that the contractor/ subcontractor is to perform;
(1) Include the Privacy Act notification contained in this contract in every solicitation and resulting subcontract and in every subcontract awarded without a solicitation, when the work statement in the proposed subcontract requires the redesign, development, or operation of a SOR on individuals that is subject to the Privacy Act; and
(2) Include this Privacy Act clause, including this subparagraph (3), in all subcontracts awarded under this contract which requires the design, development, or operation of such a SOR.
h. In the event of violations of the Act, a civil action may be brought against the agency involved when the violation concerns the design, development, or operation of a SOR on individuals to accomplish an agency function, and criminal penalties may be imposed upon the officers or employees of the agency when the violation concerns the operation of a SOR on individuals to accomplish an agency function. For purposes of the Act, when the contract is for the operation of a SOR on individuals to accomplish an agency function, the contractor/subcontractor is considered to be an employee of the agency.
(1) "Operation of a System of Records" means performance of any of the activities associated with maintaining the SOR, including the collection, use, maintenance, and dissemination of records.
(2) "Record" means any item, collection, or grouping of information about an individual that is maintained by an agency, including, but not limited to, education, financial transactions, medical history, and criminal or employment history and contains the person's name, or identifying number, symbol, or any other identifying particular assigned to the individual, such as a fingerprint or voiceprint, or a photograph.
(3) "System of Records" means a group of any records under the control of any agency from which information is retrieved by the name of the individual or by some identifying number, symbol, or other identifying particular assigned to the individual.
i. The vendor shall ensure the security of all procured or developed systems and technologies, including their subcomponents (hereinafter referred to as "Systems"), throughout the life of this contract and any extension, warranty, or maintenance periods. This includes, but is not limited to workarounds, patches, hotfixes, upgrades, and any physical components (hereafter referred to as Security Fixes) which may be necessary to fix all security vulnerabilities published or known to the vendor anywhere in the Systems, including Operating Systems and firmware. The vendor shall ensure that Security Fixes shall not negatively impact the Systems.
j. The vendor shall notify VA within 24 hours of the discovery or disclosure of successful exploits of the vulnerability which can compromise the security of the Systems (including the confidentiality or integrity of its data and operations, or the availability of the system). Such issues shall be remediated as quickly as is practical, but in no event longer than days.
k. When the Security Fixes involve installing third party patches (such as Microsoft OS patches or Adobe Acrobat), the vendor will provide written notice to the VA that the patch has been validated as not affecting the Systems within 10 working days. When the vendor is responsible for operations or maintenance of the Systems, they shall apply the Security Fixes within days.
l. All other vulnerabilities shall be remediated as specified in this paragraph in a timely manner based on risk, but within 60 days of discovery or disclosure. Exceptions to this paragraph (e.g. for the convenience of VA) shall only be granted with approval of the contracting officer and the VA Assistant Secretary for Office of Information and Technology.
5. INFORMATION SYSTEM HOSTING, OPERATION, MAINTENANCE, OR USE
a. For information systems that are hosted, operated, maintained, or used on behalf of VA at non-VA facilities, contractors/subcontractors are fully responsible and accountable for ensuring compliance with all HIPAA, Privacy Act, FISMA, NIST, FIPS, and VA security and privacy directives and handbooks. This includes conducting compliant risk assessments, routine vulnerablity scanning, system patching and change management procedures, and the completion of an acceptable contingency plan for each system. The contractor's security control procedures must be equivalent, to those procedures used to secure VA systems. A Privacy Impact Assessment (PIA) must also be provided to the COR and approved by VA Privacy Service prior to operational approval. All external Internet connections to VA's network involving VA information must be reviewed and approved by VA prior to implementation.
b. Adequate security controls for collecting, processing, transmitting, and storing of Personally Identifiable Information (PII), as determined by the VA Privacy Service, must be in place, tested, and approved by VA prior to hosting, operation, maintenance, or use of the information system, or systems by or on behalf of VA. These security controls are to be assessed and stated within the PIA and if these controls are determined not to be in place, or inadequate, a Plan of Action and Milestones (POA&M) must be submitted and approved prior to the collection of PII.
c. Outsourcing (contractor facility, contractor equipment or contractor staff) of systems or network operations, telecommunications services, or other managed services requires certification and accreditation (authorization) (C&A) of the contractor's systems in accordance with VA Handbook 6500.3, Certification and Accreditation and/or the VA OCS Certification Program Office. Government- owned (government facility or government equipment) contractor-operated systems, third party or business partner networks require memorandums of understanding and interconnection agreements (MOU-ISA) which detail what data types are shared, who has access, and the appropriate level of security controls for all systems connected to VA networks.
d. The contractor/subcontractor's system must adhere to all FISMA, FIPS, and NIST standards related to the annual FISMA security controls assessment and review and update the PIA. Any deficiencies noted during this assessment must be provided to the VA contracting officer and the ISO for entry into VA's POA&M management process. The contractor/subcontractor must use VA's POA&M process to document planned remedial actions to address any deficiencies in information security policies, procedures, and practices, and the completion of those activities. Security deficiencies must be corrected within the timeframes approved by the government. Contractor/subcontractor procedures are subject to periodic, unannounced assessments by VA officials, including the VA Office of Inspector General. The physical security aspects associated with contractor/ subcontractor activities must also be subject to such assessments. If major changes to the system occur that may affect the privacy or security of the data or the system, the C&A of the system may need to be reviewed, retested and re- authorized per VA Handbook 6500.3. This may require reviewing and updating all of the documentation (PIA, System Security Plan, Contingency Plan). The Certification Program Office can provide guidance on whether a new C&A would be necessary.
e. The contractor/subcontractor must conduct an annual self assessment on all systems and outsourced services as required. Both hard copy and electronic copies of the assessment must be provided to the COR. The government reserves the right to conduct such an assessment using government personnel or another contractor/subcontractor. The contractor/subcontractor must take appropriate and timely action (this can be specified in the contract) to correct or mitigate any weaknesses discovered during such testing, generally at no additional cost.
f. VA prohibits the installation and use of personally-owned or contractor/ subcontractor-owned equipment or software on VA's network. If non-VA owned equipment must be used to fulfill the requirements of a contract, it must be stated in the service agreement, SOW or contract. All of the security controls required for government furnished equipment (GFE) must be utilized in approved other equipment (OE) and must be funded by the owner of the equipment. All remote systems must be equipped with, and use, a VA-approved antivirus (AV) software and a personal (host-based or enclave based) firewall that is configured with a VA-approved configuration. Software must be kept current, including all critical updates and patches. Owners of approved OE are responsible for providing and maintaining the anti-viral software and the firewall on the non-VA owned OE.
g. All electronic storage media used on non-VA leased or non-VA owned IT equipment that is used to store, process, or access VA information must be handled in adherence with VA Handbook 6500.1, Electronic Media Sanitization upon: (i) completion or termination of the contract or (ii) disposal or return of the IT equipment by the contractor/subcontractor or any person acting on behalf of the contractor/subcontractor, whichever is earlier. Media (hard drives, optical disks, CDs, back-up tapes, etc.) used by the contractors/ subcontractors that contain VA information must be returned to the VA for sanitization or destruction or the contractor/subcontractor must self-certify that the media has been disposed of per 6500.1 requirements. This must be completed within 30 days of termination of the contract.
h. Bio-Medical devices and other equipment or systems containing media (hard drives, optical disks, etc.) with VA sensitive information must not be returned to the vendor at the end of lease, for trade-in, or other purposes. The options are:
(1) Vendor must accept the system without the drive;
(2) VA's initial medical device purchase includes a spare drive which must be installed in place of the original drive at time of turn-in; or
(3) VA must reimburse the company for media at a reasonable open market replacement cost at time of purchase.
(4) Due to the highly specialized and sometimes proprietary hardware and software associated with medical equipment/systems, if it is not possible for the VA to retain the hard drive, then;
(a) The equipment vendor must have an existing BAA if the device being traded in has sensitive information stored on it and hard drive(s) from the system are being returned physically intact; and
(b) Any fixed hard drive on the device must be non-destructively sanitized to the greatest extent possible without negatively impacting system operation. Selective clearing down to patient data folder level is recommended using VA approved and validated overwriting technologies/methods/tools. Applicable media sanitization specifications need to be pre-approved and described in the purchase order or contract.
(c) A statement needs to be signed by the Director (System Owner) that states that the drive could not be removed and that (a) and (b) controls above are in place and completed. The ISO needs to maintain the documentation.
6. SECURITY INCIDENT INVESTIGATION
a. The term "security incident" means an event that has, or could have, resulted in unauthorized access to, loss or damage to VA assets, or sensitive information, or an action that breaches VA security procedures. The contractor/ subcontractor shall immediately notify the COR and simultaneously, the designated ISO and Privacy Officer for the contract of any known or suspected security/privacy incidents, or any unauthorized disclosure of sensitive information, including that contained in system(s) to which the contractor/ subcontractor has access.
b. To the extent known by the contractor/subcontractor, the contractor/ subcontractor's notice to VA shall identify the information involved, the circumstances surrounding the incident (including to whom, how, when, and where the VA information or assets were placed at risk or compromised), and any other information that the contractor/subcontractor considers relevant.
c. With respect to unsecured protected health information, the business associate is deemed to have discovered a data breach when the business associate knew or should have known of a breach of such information. Upon discovery, the business associate must notify the covered entity of the breach. Notifications need to be made in accordance with the executed business associate agreement.
d. In instances of theft or break-in or other criminal activity, the contractor/subcontractor must concurrently report the incident to the appropriate law enforcement entity (or entities) of jurisdiction, including the VA OIG and Security and Law Enforcement. The contractor, its employees, and its subcontractors and their employees shall cooperate with VA and any law enforcement authority responsible for the investigation and prosecution of any possible criminal law violation(s) associated with any incident. The contractor/subcontractor shall cooperate with VA in any civil litigation to recover VA information, obtain monetary or other compensation from a third party for damages arising from any incident, or obtain injunctive relief against any third party arising from, or related to, the incident.
7. LIQUIDATED DAMAGES FOR DATA BREACH
a. Consistent with the requirements of 38 U.S.C. 5725, a contract may require access to sensitive personal information. If so, the contractor is liable to VA for liquidated damages in the event of a data breach or privacy incident involving any SPI the contractor/subcontractor processes or maintains under this contract.
b. The contractor/subcontractor shall provide notice to VA of a "security incident" as set forth in the Security Incident Investigation section above. Upon such notification, VA must secure from a non-Department entity or the VA Office of Inspector General an independent risk analysis of the data breach to determine the level of risk associated with the data breach for the potential misuse of any sensitive personal information involved in the data breach. The term 'data breach' means the loss, theft, or other unauthorized access, or any access other than that incidental to the scope of employment, to data containing sensitive personal information, in electronic or printed form, that results in the potential compromise of the confidentiality or integrity of the data. Contractor shall fully cooperate with the entity performing the risk analysis. Failure to cooperate may be deemed a material breach and grounds for contract termination.
c. Each risk analysis shall address all relevant information concerning the data breach, including the following:
(1) Nature of the event (loss, theft, unauthorized access);
(2) Description of the event, including:
(a) date of occurrence;
(b) data elements involved, including any PII, such as full name, social security number, date of birth, home address, account number, disability code;
(3) Number of individuals affected or potentially affected;
(4) Names of individuals or groups affected or potentially affected;
(5) Ease of logical data access to the lost, stolen or improperly accessed data in light of the degree of protection for the data, e.g., unencrypted, plain text;
(6) Amount of time the data has been out of VA control;
(7) The likelihood that the sensitive personal information will or has been compromised (made accessible to and usable by unauthorized persons);
(8) Known misuses of data containing sensitive personal information, if any;
(9) Assessment of the potential harm to the affected individuals;
(10) Data breach analysis as outlined in 6500.2 Handbook, Management of Security and Privacy Incidents, as appropriate; and
(11) Whether credit protection services may assist record subjects in avoiding or mitigating the results of identity theft based on the sensitive personal information that may have been compromised.
d. Based on the determinations of the independent risk analysis, the contractor shall be responsible for paying to the VA liquidated damages in the amount of per affected individual to cover the cost of providing credit protection services to affected individuals consisting of the following:
(1) Notification;
(2) One year of credit monitoring services consisting of automatic daily monitoring of at least 3 relevant credit bureau reports;
(3) Data breach analysis;
(4) Fraud resolution services, including writing dispute letters, initiating fraud alerts and credit freezes, to assist affected individuals to bring matters to resolution;
(5) One year of identity theft insurance with $20,000.00 coverage at $0 deductible; and
(6) Necessary legal expenses the subjects may incur to repair falsified or damaged credit records, histories, or financial affairs.
8. SECURITY CONTROLS COMPLIANCE TESTING
On a periodic basis, VA, including the Office of Inspector General, reserves the right to evaluate any or all of the security controls and privacy practices implemented by the contractor under the clauses contained within the contract. With 10 working-day's notice, at the request of the government, the contractor must fully cooperate and assist in a government-sponsored security controls assessment at each location wherein VA information is processed or stored, or information systems are developed, operated, maintained, or used on behalf of VA, including those initiated by the Office of Inspector General. The government may conduct a security control assessment on shorter notice (to include unannounced assessments) as determined by VA in the event of a security incident or at any other time.
9. TRAINING
a. All contractor employees and subcontractor employees requiring access to VA information and VA information systems shall complete the following before being granted access to VA information and its systems:
(1) Sign and acknowledge (either manually or electronically) understanding of and responsibilities for compliance with the Contractor Rules of Behavior, Appendix E relating to access to VA information and information systems;
(2) Successfully complete the VA Cyber Security Awareness and Rules of Behavior training and annually complete required security training;
(3) Successfully complete the appropriate VA privacy training and annually complete required privacy training; and
(4) Successfully complete any additional cyber security or privacy training, as required for VA personnel with equivalent information system access [to be defined by the VA program official and provided to the contracting officer for inclusion in the solicitation document - e.g., any role-based information security training required in accordance with NIST Special Publication 800-16, Information Technology Security Training Requirements.]
b. The contractor shall provide to the contracting officer and/or the COR a copy of the training certificates and certification of signing the Contractor Rules of Behavior for each applicable employee within 1 week of the initiation of the contract and annually thereafter, as required.
c. Failure to complete the mandatory annual training and sign the Rules of Behavior annually, within the timeframe required, is grounds for suspension or termination of all physical or electronic access privileges and removal from work on the contract until such time as the training and documents are complete.
(End of Clause)
SCOPE OF WORK TO PERFORM "TEST FIRE DAMPER"
BUILDING 170 (North Little Rock) and John L. McClellan (Little Rock) VA MEDICAL CENTERS ProjectTitle: Test Fire Dampers Service and Testing A. General Scope of Work:
1. Contractor will provide all labor, materials, equipment, etc. necessary to inspect and test approximately 309 fire dampers and complete all work in accordance with Contracting Documents, Scope of Work {SOW), NFPA, local building codes, VA facility standards, and other applicable requirements.
B. Project Conditions
1. Period of Performance will be 90 days.
2. Make repairs or corrections as necessary within scope of work. Corrections and repairs shall not void UL or similar rating or the fire damper itself will be replaced.
3. Work shall include, but shall not be limited to, test each fire damper to ensure they are operational and code compliant, make the fire damper accessible and test them to ensure they are operational, as well as repairing fire dampers that are determined to need repair and testing them to ensure they are operational. Additional, work shall involve, but shall not be limited to, cleaning, lubricating fire dampers to ensure they are operational, creating access hatches or make recommendations for further actions necessary outside the scope of this project to make them operational and code compliant.
4. Work shall also include the removal or disabling fire dampers identified on the provided drawings or given written instructions from the onsite contracting officer representative. Where identified to disable existing fire damper, contractor will mechanically disable per NFPA code requirements, so they are considered decommissioned from that point. New materials shall match existing material type, size, thickness, or other characteristics. Insulation shall be patched back to match around the entire duct, sealed with appropriate material. Approved 2-hour firestop materials will be used where applicable to fill necessary voids or openings and acoustical caulk will be used around fire dampers and ductwork that is subject to being deformed by intumescent fireproofing materials.
5. Removal of unnecessary fire dampers from the inspection/testing list will be provided to the COR prior to removal for approval.
6. Anniversary Date Service Requirements: A total of approximately 309 Fire Dampers (JLM 251 and North Little Rock 58) must be inspected/tested. Of the total, the following quantities must be inspected by the accompanying dates: (103) units inspected within first 30 days of NTP, (103) within 60 days of NTP, (103) within 90 days of NTP. These fire dampers may be indicated as preferred and a priority depending on the time of NTP to make sure (6) year timelines are accomplished. Upon completion of any preferred fire damper inspections the contractor may phase remaining construction at their discretion and will coordinate schedule and remaining phasing with VA COR. The remaining fire damper inspection and removals will be completed by the end of the contract.
C. ICRA/PRCA
1. Prior to the contractor starting work, VA Staff will complete a Pre-Construction Risk Assessment/Infection Control Risk Assessment (PCRA/ICRA) with the infection control officer. Contractor is responsible for providing and installing (PCRA/ICRA) barriers and complying with all required ICRA actions. Interim Life Safety Measures (ILSM) requirements and paperwork shall be completed at this time as well and the contractor shall follow these requirements. Hot works and above ceiling permits will be obtained per Central Arkansas Veterans Healthcare System (CAVHS) VA policy when doing task that fall within the guidelines of this type of work.
D. Post award Conference
1. Pre-Installation fire damper testing Conference: Convene a conference approximately 10 days prior to scheduled commencement and issuance of notice to proceed of fire damper testing and demo/installation and any associated work.
E. Schedule
1. The offeror shall workdays and times agreed to with the CAVHS VA. Normal operating times will be between 7:00am - 5:00pm Monday-Friday. It is expected that most operations will occur during those hours but will not always be able. Work schedules may have to be altered for work which may create noise or vibration with the VA Medical Center that is disruptive to staff, patients, and the VA Medical Center procedures, or must result in equipment shutdown for demolition and reinstallation of utility system components. The contractor should expect to have to work on weekends or times outside of the normal workday of 7:00 am-5:00pm Monday - Friday.
2. The Offerer shall describe in a written narrative its plans for phasing the work so that the Medical Center and the associated utility systems remain operational during construction. All utility system outages shall be scheduled with the VA COR and the HVAC Shop staff. Utility system outages will be scheduled typically after normal VA business hours for the area, nights, and weekends at no additional cost to the Government.
3. Contractor will provide the COR at least a 21-day notice of all proposed shutdowns of air handlers and other equipment. Work shall be done on premium time (at no additional cost to the Government) where necessary to minimize impact to critical care and patient operations.
4. Work shall be grouped so that only one air handling system is shut down at a time, unless approved otherwise by the VA COR and HVAC staff is required to assist with the system shutdowns and start-ups. Work shall be completed and the system operational two hours prior to the start of the next business day when VA staff will be occupying the space. The system needs to be running to provide adequate temperature and humidity control as well as general ventilation.
F. Damper Inspection
1. Contractor is to provide qualified staff to inspect and test fire dampers. All tests shall be completed in a safe manner by personnel wearing proper personal protective equipment. Inspections shall meet NFPA code requirements.
2. The fire damper location drawings are available see attachment 1 (NLR) and attachment 2 (JLM). There may be differences discovered in the field. The contractor shall notify Contracting Officers Representative (COR), in writing, of any discrepancies.
3. Tasks to be performed included during inspection, but shall not be limited to:
a. Locate and operate (i.e. actuate) all fire dampers in the Medical Center.
b. Remove and reset the fusible link, to verify the damper fully closes.
c. Ensure no interference due to rusted, bent, misaligned, or damaged frame or blades, or defective hinges or other moving parts. Repair or replace if the condition(s) are found.
d. Check for penetrations by foreign objects and correct if found.
e. Check for anything blocking the closure in any way and remove if found.
f. Lubricate all moving parts of the fire damper.
g. If damper is provided with a latch, check operation of the latch.
h. Replace all fusible links that are compromised (per NFPA Code).
4. Supply a Master Inspection Report. At a minimum offeror will provide completed Inspection logs, and a formal Inspection Report, which must include but shall not limited to, the following information for each damper:
a. Location of fire damper.
b. Was the damper tested successfully (Y /N).
b. If the fire damper failed the inspection, provide a detailed reason why.
d. Note corrective actions taken and if retesting was successful or not.
e. Date of testing.
f. Name of inspector.
5. Provide proper documentation of completed inspection sheet that includes pictures of every damper "Before" and "After" Inspection as directed by the inspection sheet. A digital copy of this form will be provided to you and be required to be submitted per As-built section of SOW. A hard copy set of the inspection log sheets will be submitted by floor in alphabetical order in a spiral bound document.
6. Provide a list of all inaccessible damper locations and recommended actions for access. Recommendations will include descriptions of work to correct the access issue and cost estimate for corrections to make them accessible.
7. Contractor shall schedule maintenance and inspections; and coordinate access to all HVAC mechanical spaces and equipment and shut down of equipment or systems with the VA COR or HVAC personnel. Some dampers may be difficult to access and require air handling unit system shutdowns as well as additional life safety and infection control measures. Contractor is responsible for arranging all access, providing all required construction barriers, and coordinating shutdowns with VA COR or other assigned Engineering Service staff to not interfere with continuity of Medical Center operations. Contractor shall follow all OSHA and VA safety requirements when accessing dampers.
8. Contractor shall follow all VA policies and procedures.
G. As-Built and Other Documentation Requirements
1. Drawings: The Offerer shall submit a redline copy of the facility maps provided with the project identifying any changes or notes made in the field. This shall include fire damper removal, fire damper disabling, fire damper installation, differing site conditions, ductwork modifications, ductwork size issues, rerouted utilities, etc.
2. Fire Damper Inspection Report - the contractor shall provide both hard copy and electronic copies of the completed Fire Damper Inspection Report to the VA COR.
3. Electronic documents shall be submitted on DVD-ROM/CD-ROM or thumb drive disks as well as email and approved by the VA COR of all submittals, meeting minutes, payroll requirements, RFl's, daily logs, warranties, deliverable attachments filled out for the project.
H. Access Doors
1. Provide and install ducts and access doors as approved by the COR on site.
2. See the attached VA Standard Detail for the proper installation of a fire damper to use for comparison and any that may have to be installed.
I: Security Information (Information systems Security Requirements) A. Information Systems Officer, Information Protection:
a. The Firm will not have access to VA Desktop computers and nor will they have access to online resources belonging to the government while conducting services.
B. Privacy Officer:
a. The A/E Firm will not have access to protected Patient Health Information (PHI) and nor will they have the capability of accessing patient information during the services provided.
C. Records Manager:
a. Citations to pertinent laws, codes, and regulations such as 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.
b. The Government Agency owns the rights to all data/records produced as part of this contract.
c. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. A/E Firm must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
-----END----
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Inspect/test 309 fire dampers CAVHS/JLM and Bldg 170 Contract Period: Base POP Begin: 11-03-2025 POP End: 03-31-2026
| 5.00 |
| ea |
| __________________ |
| __________________ |
Provide and install access panel to gain access to noted or unidentified fire damper
| 5.00 |
| ea |
| __________________ |
| __________________ |
Identify, test, label and report unidentified fire dampers Contract Period: Option 1
| 5.00 |
| ea |
| __________________ |
| __________________ |
Replace damaged/inoperable fusible link
| GRAND TOTAL |
| __________________ |
36C25625Q1473
Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should…