This solicitation notice is for a construction project to renovate an existing laboratory space on the second floor of Building 109 at the Michael E. DeBakey Veterans Affairs Medical Center in Houston, Texas. The project involves renovating approximately 2,600 square feet to create a new Intravital Microscopy Research Lab, including offices, research work space, a tissue culture lab, and a FACS/confocal microscopy room. Interested service-disabled veteran-owned small businesses are invited to submit fixed-price proposals for specialized construction work including demolition, structural, architectural, mechanical, electrical, plumbing, communications, fire protection, and interior finishes. The performance period is 270 calendar days from notice to proceed. The estimated value is between $1 million and $2 million. The solicitation and specifications will be available on July 30, 2019. Proposals are due 90 days later. Bid and performance/payment bonds are required. The work is set aside for service-disabled veteran-owned small businesses, and at least 15% of labor costs must be spent on SDVOSB or veteran employees.

36C25619R0117 Statement of Work 7.22.2019.docx

View the file

Other files

File Type Posted
36C25619C0157-000.docx DOCX document
36C25619R0117-0002000.docx DOCX document
36C25619R0117-0002001.docx DOCX document
36C25619R0117-0001006.pdf PDF
36C25619R0117-0001007.pdf PDF
36C25619R0117-0001004.pdf PDF
36C25619R0117-0001008.pdf PDF
36C25619R0117-0001000.docx DOCX document
36C25619R0117-0001001.pdf PDF
36C25619R0117-0001002.pdf PDF
36C25619R0117-0001009.pdf PDF
36C25619R0117-0001003.pdf PDF
36C25619R0117-0001005.pdf PDF
36C25619R0117-0001010.pdf PDF
36C25619R0117-001.docx DOCX document
36C25619R0117-006.pdf PDF
36C25619R0117-010.pdf PDF
36C25619R0117-008.docx DOCX document
36C25619R0117-007.pdf PDF
36C25619R0117-004.pdf PDF
36C25619R0117-003.pdf PDF
36C25619R0117-009.doc DOC document
36C25619R0117-005.pdf PDF
36C25619R0117-000.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate B-109 Lab 2nd Floor Project No: 580-18-105 Scope of Work 1 Foreword

1.1 Contractor shall provide all labor, materials, tools, equipment, expertise, administration, supervision and transportation as necessary to perform all work in accordance with provided construction specifications, drawings, all documents attached to this contract, all terms and conditions of this contract, and this statement of work.

1.2 This document does not relieve the contractor of their professional responsibility to comply with all local and federal construction and environmental codes and to perform and complete a fully coordinated job.

2 General Project Description

2.1 The project will renovate approximately 2,600 S.F. of the 2nd floor in building 109 to create a new Intravital Microscopy Research Lab. The existing space is research and will be combined into 1 larger lab. The new space will include Offices, Research Work Space, Tissue Culture Lab, FACS/Confocal Microscopy Room.

2.2 Work includes specialized construction labor & supervision for architectural, mechanical, structural, electrical, plumbing, medical gas, fire protection, asbestos abatement and demolition work as required by provided construction documents. This Scope of Work is not considered to be a comprehensive description of work details for this project. All work shall be completed per the plans/drawings and specifications.

2.3 Bid Items include: See construction specification general requirements.

2.4 The construction period shall be identified and scheduled for approximately two hundred and seventy (270) calendar days after NTP.

3 General Construction Requirements

3.1 Prior to any mobilization and construction, the contractor shall request and have an approved Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety Measures Certification from the VAMC. Also project/construction schedule, schedule of values/prices and construction phases have to be provided and approved by VA’s COR/Project Engineer and/or Contracting Officer.

3.2 Contractor shall completely prepare site, prior to the installation of the equipment, and furnish labor, equipment and materials to perform work for this specific project as required by construction documents.

3.3 The entire project’s associated construction and temporary works shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and regulations.

3.4 Project Record Drawings: The Contractor will maintain a set of Record Drawings. The Contractor will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process. The project record drawings will be available for review by the VA Project Manager at all times.

3.5 The following milestone dates shall be incorporated into the contractor’s schedule.

3.5.1 Submittal Schedule and log shall be provided within ten (10) calendar days after Notice to Proceed. The contractor shall provide it to the Contracting Officer’s Representative (COR) for approval, and shall include the dates for submission of Shop Drawings, Product Data, and Samples.

3.5.2 All Shop Drawings, Product Data and Samples shall be submitted and approved by the VA within sixty (60) calendar days after Notice to Proceed. The VA will provide the Contractor with written comments within 15 business days after receiving each submittal.

3.5.3 The Contractor shall submit a construction schedule within ten (10) calendar days after Notice to Proceed. The construction schedule shall be prepared in terms of calendar days (not working days). Once the construction schedule is submitted by the Contractor and approved by the CO, no lateness in the schedule shall be tolerated without the CO’s approval.

3.5.4 A pre-construction meeting shall be held within ten (10) calendar days after award of Contract. During the construction, the Contractor shall attend all weekly construction progress meetings. The meeting schedule and place will be discussed in the pre-construction meeting.

4 General Contract Requirement

4.1 The MEDVAMC expects that contractors who submit bids will have experience with at least three (3) or more projects similar in size and scope that have been completed within the last 5 years that was self-coordinated and/or self-performed within a hospital setting or other medical facility.

4.2 Work as described under this contract shall be accomplished during Normal Working Hours, which are defined as 7:00 am to 4:30 p.m., Monday through Friday, unless otherwise specifically authorized by the Contracting Officer. Contractor can work earlier or later in the day and on weekends with prior approval.

4.3 Pursuant to clause 52.236-8 Other Contracts incorporated by reference under section 4.33 52.252-2 Clauses Incorporated by Reference, Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. If required by the Contracting Officer, Contractor shall, at no additional cost to the VA, coordinate with other VA’s activities including but not limited to construction activities near the job site to ensure the construction work under this project will be in harmony with those activities. This coordination shall include but not limited to the careful scheduling of work commencement, equipment mobilization etc.

4.4 The following legal holidays are observed by this Government Agency:

New Year's Day January 1st Martin Luther King's Birthday Third Monday in January Presidents Day Third Monday in February Memorial Day Last Monday in May Independence Day July 4th Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th and any day declared by the federal government as holiday.

5 Project Meetings

5.1 Each week the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government. Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.

5.2 Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer (CO). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and telephone numbers; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision. Copies of updated minutes shall be distributed to the all attendees within 48 hours after change notice.

6 ID Badge Requirement

6.1 Contract workers under this project will require a flash badge from the VA before the start of construction work at the Houston VAMC. There is no charge for flash badges.

--- End---