36C25219B0022-0007005.pdf
PDF 175 KB Posted
- Attached to
- Material Management Building, 537-321 Federal contract opportunity
- Solicitation number
- 36C25219B0022
About this file
36C25219B0022 0007 0 Table of Contents_Specifications.pdf
View the file
Other files for this federal contract opportunity
Show all 50
Material Management Building, 537-321 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
05-01-17
PROJECT NO: 537-321 00 01 10R - 1
CONTRACT NO: VA69D-P-1558
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10R
This list has been extracted from the VHA Master
Specifications for use on the:
Material Management Services Area
Jesse Brown VA Medical Center
Project No. 537-321
Contract No. VA69D-P-1558
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10R Table of Contents 12-12
00 01 15 List of Drawing Sheets 07-15
00 01 20 Construction Statement of Work
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.15 Project Schedules 02-15
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 29R Testing Laboratory Services 11-18
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 81 13R Sustainable Design Requirements 10-17
01 81 13.21 Sustainability Certification Requirements- Green
Globes
09-15
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 08-16
02 41 00R Demolition 08-17
02 83 33.13 Lead Based Paint Removal and Disposal 08-16
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 12-15
DIVISION 04 – MASONRY
04 05 13R Masonry Mortaring 10-17
04 05 16 Masonry Grouting 02-16
04 20 00R Unit Masonry 08-17
04 72 00 Cast Stone Masonry 02-15
DIVISION 05 – METALS
05 36 00 Composite Metal Decking 10-15
05 50 00R Metal Fabrications 08-18
05 51 00 Metal Stairs 10-15
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00R Rough Carpentry 10-17
PROJECT NO: 537-321 00 01 10R - 2
CONTRACT NO: VA69D-P-1558
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 08 00 Facility Exterior Closure Commissioning 11-16
07 13 52 Modified Bituminous Sheet Waterproofing 08-16
07 21 13R Thermal Insulation 10-17
07 22 00 Roof and Deck Insulation 02-16
07 52 16.11 Cold Adhesive Styrene-Butadiene-Styrene Modified
Bituminous Membrane Roofing
08-16
07 60 00R Flashing and Sheet Metal 09-18
07 72 00 Roof Accessories 10-15
07 81 00R Applied Fireproofing 10-17
07 84 00 Firestopping 02-16
07 92 00R Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 02-16
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16
08 14 00 Interior Wood Doors 02-16
08 31 13 Access Doors and Frames 02-16
08 51 13R Aluminum Windows 02-16
08 71 00 Door Hardware 01-16
08 71 13 Automatic Door Operators 02-16
08 71 13.11 Low Energy Power Assist Door Operators 08-16
08 80 00 Glazing 10-15
08 90 00 Louvers and Vents 05-15
DIVISION 09 – FINISHES
09 06 00 Schedule For Finishes 04-15
09 22 16R Non-Structural Metal Framing 06-18
09 29 00R Gypsum Board 09-18
09 30 13 Ceramic/Porcelain Tiling 10-15
09 51 00R Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 67 23.60R Resinous (Urethane and Epoxy Mortar) Flooring (RES-6) 09-18
09 68 00 Carpeting 10-15
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10-15
10 21 13 Toilet Compartments 12-15
10 22 13 Wire Mesh Partitions 10-15
10 26 00 Wall and Door Protection 10-15
10 28 00 Toilet, Bath, and Laundry Accessories 02-16
10 44 13R Fire Extinguisher Cabinets 08-18
10 51 13 Metal Lockers 5-10
DIVISION 11 – EQUIPMENT
None
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 14– CONVEYING EQUIPMENT
None
PROJECT NO: 537-321 00 01 10R - 3
CONTRACT NO: VA69D-P-1558
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression Systems 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
22 14 00 Facility Storm Drainage 12-09
22 14 29 Sump Pumps 09-15
22 14 36 Packaged, Submersible, Drainage Pump Units 01-11
22 40 00 Plumbing Fixtures 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-15
23 05 12 General Motor Requirements for HVAC And Steam
Generation Equipment
11-10
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC and Plumbing Insulation 02-15
23 08 00 Commissioning of HVAC Systems 11-16
23 09 23R Direct-Digital Control System for HVAC 09-11
23 21 13R Hydronic Piping 09-12
23 22 23 Steam Condensate Pumps 02-15
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 02-15
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 40 00 HVAC Air Cleaning Devices 02-12
23 73 00 Indoor Central Station Air Handling Units 04-11
23 82 00 Convection Heating and Cooling Units 04-11
23 82 16 Air Coils 04-11
DIVISION 25 – INTEGRATED AUTOMATION
None
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33R Raceway and Boxes for Electrical Systems 05-14
26 08 00 Commissioning of Electrical Systems 11-16
26 24 16R Panelboards 05-14
26 27 26R Wiring Devices 01-16
26 29 11R Motor Starters 08-14
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 41 00 Facility Lightning Protection 01-17
26 51 00R Interior Lighting 08-14
DIVISION 27 – COMMUNICATIONS
PROJECT NO: 537-321 00 01 10R - 4
CONTRACT NO: VA69D-P-1558
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33R Raceways and Boxes for Communications Systems 10-18
27 10 00 Control, Communication, And Signal Wiring 06-15
27 51 16R Public Address and Mass Notification Systems 10-18
27 52 23 Nurse Call And Code Blue Systems 10-18
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 13R Conductors and Cables For Electronic Safety And
Security
10-18
28 05 28 Conduits And Backboxes For Electronic Safety and
Security
09-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
31 23 19 Dewatering 10-12
31 63 26 Drilled Caissons 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement & Concrete for Exterior Improvements 08-16
DIVISION 33 – UTILITIES
33 08 00 Commissioning of Site Utilities 11-16
33 40 00R Storm Sewer Utilities 12-17
33 46 13 Foundation Drainage 10-11
DIVISION 34 – TRANSPORTATION
None
DIVISION 48 – Electrical Power Generation
None
EXHIBITS
Exhibit 1 Soils Report: This contains an independent table of contents reading:
Introduction
Subsurface Investigation Procedures
Testing Program
Soil Conditions
Water Table Conditions
Analysis and Recommendations
General Qualifications
Appendix A – General Notes and Location Diagram
Appendix B – Boring Logs
Appendix C – Vane Shear Results
Exhibit 2 Hazardous Materials/GEMS Construction Safety manual
Exhibit 3 VA Statement of Conditions
Exhibit 4 VA Asbestos Report
Exhibit 5 Soils Investigation and Analytical Testing Report