S06_-_A00002_-_Att1_Addendum__2_-_585-16-116.docx
DOCX document 22 KB Posted
- Attached to
- 585-16-116 Replace Fire Doors and Frames at Oscar G. Johnson VAMC at Iron Mountain, MI Federal contract opportunity
- Solicitation number
- 36C25219B0013
About this file
36C25219B0013 0002 S06 - A00002 - Att1 Addendum #2 - 585-16-116.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25219C0061-000.docx | DOCX document | |
| 36C25219B0013_0004.docx | DOCX document | |
| 36C25219B0013_0003.docx | DOCX document | |
| S06_-_A00002_-_Att2_BidForm_-_585-16-116.docx | DOCX document | |
| S06_-_A00002_-_Att3_-_Signage_Spec_-_585-16-116.pdf | ||
| 36C25219B0013_0002.docx | DOCX document | |
| 36C25219B0013-0001006.pdf | ||
| 36C25219B0013-0001005.docx | DOCX document | |
| 36C25219B0013-0001002.pdf | ||
| 36C25219B0013-0001000.docx | DOCX document | |
| 36C25219B0013-0001004.pdf | ||
| 36C25219B0013-0001001.docx | DOCX document | |
| 36C25219B0013-0001003.pdf | ||
| 36C25219B0013-003.pdf | ||
| 36C25219B0013-001.docx | DOCX document | |
| 36C25219B0013-002.pdf | ||
| 36C25219B0013-004.docx | DOCX document | |
| 36C25219B0013-000.docx | DOCX document |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: 36C25219B0013
Addendum #2 Project #: 585-16-116 Project: Replace Fire Doors and Frames Date: 10DEC18
Drawings, specifications, and / or proposals are herein amended, expanded, and / or modified, and become a part of the Contract Documents with the same effect as if incorporated in the original documents. Any contrary provisions contained, or referred to, in Drawings and / or Specifications, shall remain applicable unless overridden by this Addendum. Revised provisions herein shall include all labor, materials, methods, modifications, etc. required for the completion of the Work.
Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may disqualify Bidder.
GENERAL INFORMATION
BID FORM – (Change in Period of Performance)
“All work shall be completed within 180 calendar days after receiving Notice to Proceed.”
CHANGES TO SPECIFICATIONS
Section 02 41 00 – Demolition
The interiors of all fire doors are assumed to be Asbestos Containing Materials (ACM). Contractor shall not cut doors during demolition and shall dispose of doors in accordance with applicable regulations.
Signage – Add Specification Section 10 14 00 SIGNAGE
Section 28 31 00 - FIRE DETECTION AND ALARM
- Delete Paragraph 3.3 INSTRUCTION (Training is not required)
ATTACHMENTS
BID FORM
10 14 00 SIGNAGE
END OF ADDENDUM