36C25219B0013-0001001.docx
DOCX document 26 KB Posted
- Attached to
- 585-16-116 Replace Fire Doors and Frames at Oscar G. Johnson VAMC at Iron Mountain, MI Federal contract opportunity
- Solicitation number
- 36C25219B0013
About this file
36C25219B0013 0001 S06 - A00001 - Att 1 - Addendum #1 - 585-16-116.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25219C0061-000.docx | DOCX document | |
| 36C25219B0013_0004.docx | DOCX document | |
| 36C25219B0013_0003.docx | DOCX document | |
| S06_-_A00002_-_Att2_BidForm_-_585-16-116.docx | DOCX document | |
| S06_-_A00002_-_Att1_Addendum__2_-_585-16-116.docx | DOCX document | |
| S06_-_A00002_-_Att3_-_Signage_Spec_-_585-16-116.pdf | ||
| 36C25219B0013_0002.docx | DOCX document | |
| 36C25219B0013-0001006.pdf | ||
| 36C25219B0013-0001000.docx | DOCX document | |
| 36C25219B0013-0001004.pdf | ||
| 36C25219B0013-0001003.pdf | ||
| 36C25219B0013-0001005.docx | DOCX document | |
| 36C25219B0013-0001002.pdf | ||
| 36C25219B0013-003.pdf | ||
| 36C25219B0013-004.docx | DOCX document | |
| 36C25219B0013-001.docx | DOCX document | |
| 36C25219B0013-002.pdf | ||
| 36C25219B0013-000.docx | DOCX document |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: 36C25219B0013
Addendum #1 Project #: 585-16-116 Project: Replace Fire Doors and Frames Date: 03DEC18
Drawings, specifications, and / or proposals are herein amended, expanded, and / or modified, and become a part of the Contract Documents with the same effect as if incorporated in the original documents. Any contrary provisions contained, or referred to, in Drawings and / or Specifications, shall remain applicable unless overridden by this Addendum. Revised provisions herein shall include all labor, materials, methods, modifications, etc. required for the completion of the Work.
Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may disqualify Bidder.
GENERAL INFORMATION
During the walkthrough on 27NOV18, COR did not include exterior Door B-S5.1 in the Facility Tour. An interior and Exterior photograph is attached.
CHANGES TO SPECIFICATIONS
1. SPECIFICATION SECTION 01 00 00 – GENERAL REQUIREMENTS
A. Bidders attention is directed to paragraph 1.24 INSTRUCTION “E. An on-site face to face training session consisting of a full 8-hourday detailing Medeco 3 Mechanical Hardware and Factory Certification course to include key cutting, pinning, preventive maintenance, master keying, etc. Training to occur within 45 days of NTP and to be scheduled through COR.”
2. SPECIFICATION SECTIO 08 71 00 – DOOR HARDWARE
A. HW-2 Passage Stairwell Door – One-Way Access Only Each Door to Have: RATED Hinges QUANTITY & TYPE AS REQUIRED 1 Closer C02011/C02021 1 Exit Device TYPE 1 F14 LEVER (PASSAGE FUNCTION) 1 Kick Plate J102 1 Sets Self-Adhesive Seals R0Y154 1 Wall Stop (@ Inswing Doors) L02101 CONVEX
CHANGES TO THE DRAWINGS:
Revisions have been made to the following drawings and are issued in the form of full-size plans. Edits are indicated by a revision delta and a cloud surrounding the affected portion of the drawing.
1. G001 – Cover Sheet – DOOR SCHEDULE & KEYED NOTES
SEE ATTACHED SPREADSHEET – “G001 – Addendum #1”
A. Eliminated Door 1-S4.2 from Project
B. Corrections made to KEYED NOTES, added NOTES regarding additional information regarding installation, and ALLOWABLE INSTALLATION TIMES to clarify acceptable working hours for each door/frame assembly.
C. Clarification on Required Weekend Work on Subbasement Elevator Access Room Doors.
ATTACHMENTS
BID FORM
PHOTOS: Door B-S5.1 (Two Photos)
SPREADSHEET: “G001- Addendum #1”
END OF ADDENDUM