36C25218B1081-0001003.pdf

PDF 70 KB Posted

Attached to
Demolition CLC Ward-3C Bldg-134 556-14-011
Solicitation number
36C25218B1081
Issued by

About this file

36C25218B1081 0001 RFI Questions and Government Responses.pdf

View the file

Other files

File Type Posted
36C25218B1081-0003000.docx DOCX document
36C25218B1081-0002002.pdf PDF
36C25218B1081-0002003.pdf PDF
36C25218B1081-0002001.pdf PDF
36C25218B1081-0002004.pdf PDF
36C25218B1081-0002000.docx DOCX document
36C25218B1081-0001004.pdf PDF
36C25218B1081-0001001.pdf PDF
36C25218B1081-0001000.docx DOCX document
36C25218B1081-0001002.pdf PDF
36C25218B1081-002.pdf PDF
36C25218B1081-003.pdf PDF
36C25218B1081-001.docx DOCX document
36C25218B1081-000.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Questions and Government Responses.

Solicitation # 36C25218B1081

556-14-011 Demolition CLC Ward-3C Bldg-134

1) Is the 3rd floor the top floor of the building

The third floor is the top floor of the building.

2) Can we acquire the weight limit for the elevator that we can use and size?

Building 134 Service Elevator –

Capacity 5000 pounds

7’-5” deep

6’-5” wide

3) What is the total height of the building from the back?

The specific height is not known. The third floor is three full floors (Ground, 1st, 2nd, 3rd) above ground level.

4) Is the space below the work area vacant during the enter construction?

The second floor area immediately below the project area, will not be occupied throughout the project timeframe.