Attachment_2_-_Addendum_01.pdf
PDF 33 KB Posted
- Attached to
- Replace SICU Curtainwall (VA-18-00160141) 541-19-501 Federal contract opportunity
- Solicitation number
- 36C25019B0002
About this file
36C25019B0002 0002 Attachment 2 - Addendum 01.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 2019_01_03_-_responses.pdf | ||
| 36C25019B0002_0003.docx | DOCX document | |
| Photo_2110.jpg | JPG image | |
| Attachment_1_-_VA_responses_-_bidding_RFIs.pdf | ||
| Photo_2115.jpg | JPG image | |
| 36C25019B0002_0002.docx | DOCX document | |
| 2nd_Floor_SICU_Stone_Sill_IMG_0142.jpg | JPG image | |
| 2nd_Floor_SICU_Stone_Sill_3_IMG_0143.jpg | JPG image | |
| Site_Visit_Sign_In_Sheet.pdf | ||
| 2nd_Floor_SICU_Stone_Sill_2_IMG_0144.jpg | JPG image | |
| 36C25019B0002_0001.docx | DOCX document | |
| 36C25019B0002-002.pdf | ||
| 36C25019B0002-003.pdf | ||
| 36C25019B0002-004.pdf | ||
| 36C25019B0002-005.pdf | ||
| 36C25019B0002-001.docx | DOCX document | |
| 36C25019B0002-006.docx | DOCX document | |
| 36C25019B0002-000.docx | DOCX document |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 01
Date: December 17, 2018
Project: Replace Surgery Curtainwall, Project No. 541-19-501
Location: VAMC Wade Park, 10701 East Blvd., Cleveland, OH 44106
Documents: September 24, 2018
This Addendum hereby modifies, supplements, and amends the bidding documents, as prepared by Perspectus Architecture, for all labor, material, and equipment of every nature and required for the execution of the entire work for the above referenced project. Wherein this Addendum varies or is in conflict with the Bidding Documents, the requirements of this Addendum shall govern. In all other particulars, the requirements of the original Specifications and Bidding Documents, including any previous Addenda, shall govern.
This Addendum includes the following Item:
Item 1 Project Duration
Revise Drawing A0.1 to indicate that Project Duration during construction is to be 150 calendar days. Total project duration for pre-construction and construction shall remain at 270 days.
END OF ADDENDUM NO. 01