36C24918R0223-005.xlsx
XLSX spreadsheet 34 KB Posted
- Attached to
- 621-16-144 - Replace AHU 3 for SPD, Bldg. 77 Federal contract opportunity
- Solicitation number
- 36C24918R0223
About this file
36C24918R0223 S02-Solicitation Attachment-Price Schedule Project 621-16-144.xlsx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24918R0223-A00002000.docx | DOCX document | |
| 36C24918R0223-A00002001.pdf | ||
| 36C24918R0223-A00001003.jpg | JPG image | |
| 36C24918R0223-A00001002.jpg | JPG image | |
| 36C24918R0223-A00001001.jpg | JPG image | |
| 36C24918R0223-A00001000.docx | DOCX document | |
| 36C24918R0223-004.pdf | ||
| 36C24918R0223-002.docx | DOCX document | |
| 36C24918R0223-007.pdf | ||
| 36C24918R0223-003.pdf | ||
| 36C24918R0223-006.pdf | ||
| 36C24918R0223-001.docx | DOCX document | |
| 36C24918R0223-000.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer-Breakdown
| JOB NAME: TBD LOCATION: TBD | Solicitation Number 36C24918R0223 | Project Title - Replace AHU in building 77 | Project Number - 621-16-144 | Proposal Date - April 5, 2018 at 3:00 PM CST | ||
| SPEC/COST CODE | DESCRIPTION | LABOR | MATERIAL | EQUIPMENT | LINE TOTALS | DIVISION TOTALS |
| DIVISION 1 | GENERAL REQUIREMENTS | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| DIVISION 2 | EXISTING CONDITIONS | $0.00 | ||||
| $0.00 | ||||||
| DIVISION 5 | METALS | $0.00 | ||||
| $0.00 | $0.00 | $ - 0 | $0.00 |
DIVISION 7 THERMAL AND MOISTURE PROTECTION $0.00
| DIVISION 8 | OPENINGS | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| DIVISION 9 | FINISHES | $100.00 | ||||
| $7.00 | $5.00 | 66.00 | $78.00 | |||
| $5.00 | $9.00 | 8.00 | $22.00 | |||
| DIVISION 13 | SPECIAL CONSTRUCTION | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| DIVISION 23 | HEATING, VENTILATING AND AIR CONDITIONING (HVAC) | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| DIVISION 26 | ELECTRICAL | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| DIVISION 28 | ELECTRONIC SAFETY AND SECURITY | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 |
$0.00
TOTALS
TOTAL LABOR
TOTAL MATERIALS
TAX FOR MATERIALS $0.00
TOTAL EQUIPMENT
TOTAL SUB
DIVISION GRAND TOTALS
| DIVISION GRAND TOTALS | $0 |
| TAX FOR MATERIALS | $0 |
SUBTOTAL $0
| OVERHEAD | 0% | $0 |
| PROFIT | 0% | $0 |
SUBTOTAL $0
| BOND/FEE | 0% | $0 |
| PERMITS/LICENSES | $0 |
GRAND TOTAL $0
| Base Offer Item 1 | INSTRUCTIONS |
| 1. It is the intent of this pricing schedule to provide all the divisions of work associated with this project per the original design. Alteration or changes made to this schedule must clearly highlight and identify the proposed additional work as perceived by the Offeror. | |
| The contractor shall provide all resources necessary to accomplish and furnish all labor, material, equipment, transportation and expert supervision necessary for Project #596-322, Construct Continuing Care Facilities-Phase 1 at the Lexington Rex VA Medical Center located at 2250 Leestown Road, Lexington, Kentucky 40511 in accordance with the Statement of Work, project specifications and drawings. Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction along with certain other items. |
The period of performance for the work in the base offer 480 calendar days from receipt of Notice to Proceed.
2. Lump sum price breakdowns will not be accepted. Lump sum price breakdowns are defined as a single price provided by the contractor for one division when each division has been broken down in price to a greater degree;
3. Divisions must still be listed even if not applicable to the construction requirement;
4. The information above does not propose to include all possible division or subdivisions needed for the requirement referenced above. Contractors shall provide all prices for each categorical column above and break down each specific division to the greatest degree possible, similar to what is referenced above. Utilizing this template in the contractor's proposal does not in any way require the Government to accept the price breakdown that is provided by the contractor or prevent the Government from requesting a further price breakdown.
Project 621-16-144, Replace AHU in building 77
Deduct Alternate 1
| JOB NAME: TBD LOCATION: TBD | Solicitation Number | Project Title | Solicitation Number | Project Number | Proposal Date | |
| SPEC/COST CODE | DESCRIPTION | LABOR | MATERIAL | EQUIPMENT | LINE TOTALS | DIVISION TOTALS |
| DIVISION 1 | GENERAL REQUIREMENTS | $0.00 | ||||
| Infection Control Walls | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Submittal Process | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Supervision | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Demolition | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Dumpsters | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Job-site Office Equipment | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Safety & First Aid-ICRA | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Final Cleaning | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Punchlist/Closeout | $0.00 | $0.00 | $0.00 | $0.00 | ||
| DIVISION 2 | SITE WORK | $0.00 | ||||
| 02 41 00 | Demolition | $0.00 | ||||
| DIVISION 6 | WOOD, PLASTICS AND COMPOSITES | $0.00 | ||||
| 06 06 00 | Translucent Resin Panel System | $0.00 | $0.00 | $ - 0 | $0.00 | |
| 06 20 00 | Finish Carpentry | |||||
| DIVISION 7 | THERMAL AND MOISTURE PROTECTION | $0.00 | ||||
| 07 72 00 | Roof Accessories | |||||
| 07 84 00 | Firestopping | |||||
| 07 92 00 | Joint Sealants | |||||
| DIVISION 9 | FINISHES | $0.00 | ||||
| 09 06 00 | Schedule for Finishes | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 22 16 | Non Struct Metal Framing | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 29 00 | Gypsum Board | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 51 00 | Acoustical Ceilings | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 65 16 | Resilient Sheet Flooring | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 65 19 | Resilient Tile Flooring | $0.00 | $0.00 | $0.00 | ||
| 09 91 00 | Painting | $0.00 | $0.00 | $0.00 | $0.00 | |
| DIVISION 10 | ACCESSORIES | $100.00 | ||||
| 10 14 00 | Signage | $7.00 | $5.00 | 66.00 | $78.00 | |
| 10 26 00 | Wall and Door Protection | $5.00 | $9.00 | 8.00 | $22.00 | |
| DIVISION 14 | CONVEYING EQUIPMENT | $0.00 | ||||
| 14 21 00 | Electric Traction Passenger Elevators P1-P4 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 14 21 20 | Electric Traction Passenger Elevators P7-P9 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 14 21 30 | Electric Traction Service Elevators S5-S6 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 14 21 90 | Passenger Elevators Data Connection P10-P12 | $0.00 | $0.00 | $0.00 | $0.00 | |
| Division 21 | FIRE SUPPRESSION | $0.00 | ||||
| 21 13 13 | Wet-Pipe Sprinkler Systems | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 22 16 | Non Struct Metal Framing | $0.00 | $0.00 | $0.00 | $0.00 | |
| 09 29 00 | Gypsum Board | $0.00 | $0.00 | $0.00 | $0.00 | |
| DIVISION 23 | HEATING, VENTILATING AND AIR CONDITIONING (HVAC) | $75.00 | ||||
| 23 05 11 | Common Work Results for HVAC | $75.00 | $0.00 | $0.00 | $75.00 | |
| 23 05 12 | General Motor Requirements for HVAC and Steam Generation Equipment | $0.00 | $0.00 | $0.00 | $0.00 | |
| 23 07 11 | HVAC and Boiler Plant Insulation | $0.00 | $0.00 | $0.00 | $0.00 | |
| 23 23 00 | Refrigerant Piping | $0.00 | $0.00 | $0.00 | $0.00 | |
| 23 81 00 | Decentralized VRF Equipment | $0.00 | $0.00 | $0.00 | $0.00 | |
| DIVISION 26 | ELECTRICAL | $0.00 | ||||
| 26 05 11 | Requirements for Electrical Installations | $0.00 | $0.00 | $0.00 | $0.00 | |
| 26 05 19 | Low-Voltage Electrical Power Conductors and Cables | $0.00 | $0.00 | $0.00 | $0.00 | |
| 26 05 26 | Grounding and Bonding for Electrical Systems | $0.00 | $0.00 | $0.00 | $0.00 | |
| 26 05 33 | Raceways and Boxes for Electrical Systems | $0.00 | $0.00 | $0.00 | $0.00 | |
| 26 24 16 | Panelboards | $0.00 | $0.00 | $0.00 | $0.00 | |
| 26 27 26 | Wiring Devices | $0.00 | $0.00 | $0.00 | $0.00 | |
| 26 29 21 | Enclosed Switches and Circuit Breakers | $0.00 | $0.00 | $0.00 | $0.00 | |
| DIVISION 27 | COMMUNICATIONS | $0.00 | ||||
| 27 05 11 | Requirements for Communications Installations | $0.00 | $0.00 | $0.00 | $0.00 | |
| 27 05 26 | Grounding and Bonding for Communications Systems | $0.00 | $0.00 | $0.00 | $0.00 | |
| 27 05 33 | Raceways and Boxes for Communications Systems | $0.00 | $0.00 | $0.00 | $0.00 | |
| DIVISION 28 | ELECTRONIC SAFETY AND SECURITY | $0.00 | ||||
| 28 31 00 | Fire Detection and Alarm | $0.00 | $0.00 | $0.00 | $0.00 |
TOTALS
TOTAL LABOR $87.00
TOTAL MATERIALS $14.00
TAX FOR MATERIALS 6% $0.84
| TOTAL EQUIPMENT | $74.00 | |
| $175.00 | ||
| TOTAL SUB |
DIVISION GRAND TOTALS
| DIVISION GRAND TOTALS | $175 |
| TAX FOR MATERIALS | $1 |
SUBTOTAL $176
| OVERHEAD | 0% | $0 |
| PROFIT | 0% | $0 |
SUBTOTAL $176
| BOND/FEE | 0% | $0 |
| PERMITS/LICENSES | $0 |
GRAND TOTAL $176
| Deduct Alternate 1 | INSTRUCTIONS |
| 1. It is the intent of this pricing schedule to provide all the divisions of work associated with this project per the original design. Alteration or changes made to this schedule must clearly highlight and identify the proposed additional work as perceived by the Offeror. |
2. Lump sum price breakdowns will not be accepted. Lump sum price breakdowns are defined as a single price provided by the contractor for one division when each division has been broken down in price to a greater degree;
3. Divisions must still be listed even if not applicable to the construction requirement;
4. The information above does not propose to include all possible division or subdivisions needed for the requirement referenced above. Contractors shall provide all prices for each categorical column above and break down each specific division to the greatest degree possible, similar to what is referenced above. Utilizing this template in the contractor's proposal does not in any way require the Government to accept the price breakdown that is provided by the contractor or prevent the Government from requesting a further price breakdown.
| &"-,Bold"MINOR PROJECT 596-322 | &"-,Bold"CONSTRUCT CONTINUING CARE FACILITIES-PHASE 1 |
| &"-,Bold"LEXINGTON VA MEDICAL CENTER |
FFP Per Item
| Base Bid Item 1 | Description | Firm Fixed Price |
| A. Bid Item No. 1: All work as required by drawings and specifications, including general construction, demolition and alteration of existing construction, structural, mechanical, electrical, plumbing, fire protection, utility systems, necessary alteration of existing structure and construction and certain other items. Work includes all labor, material, equipment and supervision to perform the required construction work on this project. | $0.00 |
Alt Ded 1 B. Deduct Alternate No. 1: All work in Bid Item 1, Base Bid above minus all work associated with the installation of the new AHU 3 and associated exhaust fan system, as destribed on the drawings, in order to provide for the refurbishing (and rearranging) of the existing AHU 3 located in the building 204 mechanical room. The new air cooled chiller will be installed on the exsiting steel dunnage. $0.00