36C24718B0637-0005001.pdf

PDF 57 KB Posted

Attached to
Renovate Wing 6A Amend release date of solicitation Federal contract opportunity
Solicitation number
36C24718B0637
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7

About this file

36C24718B0637 0005 Question 6A Electrical Panels 1 and Response.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Wing 6A Amend release date of solicitation, newest first.
File Type Posted
36C24718B0637-0007001.pdf PDF
36C24718B0637-0007000.docx DOCX document
36C24718B0637-0006001.pdf PDF
36C24718B0637-0006000.docx DOCX document
36C24718B0637-0005000.docx DOCX document
36C24718B0637-0004000.docx DOCX document
36C24718B0637-0004001.pdf PDF
36C24718B0637-0004002.pdf PDF
36C24718B0637-0003001.pdf PDF
36C24718B0637-0003000.docx DOCX document
36C24718B0637-0003002.pdf PDF
36C24718B0637-0003003.pdf PDF
36C24718B0637-0002000.docx DOCX document
36C24718B0637-0001004.pdf PDF
36C24718B0637-0001009.pdf PDF
36C24718B0637-0001005.pdf PDF
36C24718B0637-0001003.pdf PDF
36C24718B0637-0001006.pdf PDF
36C24718B0637-0001008.pdf PDF
36C24718B0637-0001007.pdf PDF
36C24718B0637-0001002.docx DOCX document
36C24718B0637-010.docx DOCX document
36C24718B0637-001.docx DOCX document
36C24718B0637-000.docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question: Please provide further clarification on what panels are to be demolished under the One Line Demo plan. Some of the same panels are shown under the new work diagram but according to the panel schedules none are listed as existing. Are all panels to be replaced?

Answer:

On drawing E001 in the Electrical Legend there are two sections for line types that show how we shown equipment for demolition and new work items. In the demolition riser diagram panel shown in solid (6ELA, GNHA, 6NLA and MCC) are to be removed and dashed equipment is to remain. On New work riser diagram panels shown in solid (6ELA, 6HNA, 6NLA, 6CLAA and 6EHB) are new and dashed equipment is to remain.