36C24718B0637-0003001.pdf
PDF 88 KB Posted
- Attached to
- Renovate Wing 6A Amend release date of solicitation Federal contract opportunity
- Solicitation number
- 36C24718B0637
About this file
36C24718B0637 0003 6A QUESTIONS-TMM Responses.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24718B0637-0007001.pdf | ||
| 36C24718B0637-0007000.docx | DOCX document | |
| 36C24718B0637-0006001.pdf | ||
| 36C24718B0637-0006000.docx | DOCX document | |
| 36C24718B0637-0005000.docx | DOCX document | |
| 36C24718B0637-0005001.pdf | ||
| 36C24718B0637-0004002.pdf | ||
| 36C24718B0637-0004000.docx | DOCX document | |
| 36C24718B0637-0004001.pdf | ||
| 36C24718B0637-0003003.pdf | ||
| 36C24718B0637-0003000.docx | DOCX document | |
| 36C24718B0637-0003002.pdf | ||
| 36C24718B0637-0002000.docx | DOCX document | |
| 36C24718B0637-0001007.pdf | ||
| 36C24718B0637-0001002.docx | DOCX document | |
| 36C24718B0637-0001004.pdf | ||
| 36C24718B0637-0001009.pdf | ||
| 36C24718B0637-0001005.pdf | ||
| 36C24718B0637-0001003.pdf | ||
| 36C24718B0637-0001006.pdf | ||
| 36C24718B0637-0001008.pdf | ||
| 36C24718B0637-010.docx | DOCX document | |
| 36C24718B0637-001.docx | DOCX document | |
| 36C24718B0637-000.docx | DOCX document |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION # 36C-247-18-B-0637
6A - QUESTIONS
COMPANY SUBMITTING QUESTIONS
Company Name: Nacci Construction Services, INC.
QUESTIONS
Question #1: The area of work is 14,773 SF and the asbestos flooring scope area in 13,000 SF. Can we identify the areas of Floor 6A that do not have asbestos flooring?
TMM Response-Drawings indicate you should anticipate all areas are hot. Specs allow for 10% variance from listed quantity. Note that we cannot test every space so all spaces are potentially suspect. You should anticipate any and all spaces are hot. Negligible cost issue.
Added quantity must be justified by contractor
Question #2: Do we know if there’s any sheet vinyl flooring associated with the asbestos scope?
TMM Response-see response to 1
Question #3: Will the entire floor be isolated from the active hospital as a single-phase project?
TMM Response-wing will be isolated
Question #4: Do you intend to provide a buckhoist? If not, provide “load-out” route.
VA Response – NO buckhoist. Load out route will be the Research Elevators in to the back dock.
Question #5: We need to know location of dumpster staging to determine the waste load-out effort.
VA Response: The dumpsters will be located on the back dock.
Question #6: We will need to remove a few windows to exhaust the filtered air.
Will this be allowed by the general contractor?
VA Response: Yes
2 | P a g e
Question #7: Will the flooring abatement occur before or after demolition?
TMM Response-Documents define requirements
Question #8: Has the VA given consideration for removal of contaminated leveling compound beneath the flooring?
TMM Response-Documents define requirements. Provide clean to conc slab