This solicitation requests proposals for a design-build renovation project at a Veterans Affairs medical center. Key details include renovation of an existing masonry building to abate lead paint and mold, replace structural elements, install new mechanical and electrical systems, and complete exterior repairs. Interested service-disabled veteran-owned small businesses must submit proposals for design and construction services with site investigations, submittals, and a 200-day completion schedule. The project value is between $250,000 to $500,000 and proposals are due in January 2020, with award subject to FY20 funding. Offerors must be registered in SAM and verified as SDVOSBs by CVE.
36C24420R0033 36C24420R0033_1.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24420R0033 0001.pdf | ||
| 36C24420R0033-005.pdf | ||
| 36C24420R0033-004.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24420R0033
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24420R0033 X 05-05-2020 542-20-101 00244 Department of Veterans Affairs Network Contracting Office 4 VA Medical Center 20 Montchanin Rd Greenville, DE 19807 Department of Veterans Affairs Benjamin Villasenor 20 Montchanin Road Greenville, DE 19807
Benjamin Villasenor 302-994-2511x7501 Design Build Renovate Building 40, Project No. 542-20-101
1. The scope of this project is to hire a Design/Build team that will provide architectural design, tools, labor, materials, and supervision to renovate building 40 at the Coatesville VAMC.
2. PHASING: Construction must allow for continuance of all hospital operations and services provided and coordinate with adjoin ing projects. After-business hours work may be necessary as dictated by the COR. All items must go through the submittal process prior to acceptance.
3. See full detailed statement of work contained herein.
Refer to FAR 52.236-27, Site Visit, for Contractor site visit information.
Prior to commencement of work, general contractor shall provide proof that an OSHA certified "competent person' (CP) will maintain a presence at the work site whenever the general or subcon tractors are present.
This project is 100% set-aside for Service-Disabled Veteran-Owned Small Business Concerns. Bidders must be verified as SDVOSB per the Center for Veterans Enterprise s (CVE) www.vetbiz.gov website.
The magnitude of construction is between $250,000.00 and $500,000.00
The small business size standard is $39.5 million. North American Industry Classification (NAICS) Code is 236220.
Contractor Personnel Security Requirements: All contractor personnel may be subject to fingerprinting and background security checks. Background security checks may be required prior to start of this project.
This solicitation is issued under the authority of 38 U.S.C. 8127, Total Service-Disabled Veteran-Owned Small Business Set-Aside.
x x 52.211-10 X 3:30 Pm 06-03-2020 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY
CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offe rs are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give numb er and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
00244 Department of Veterans Affairs Network Contracting Office 4
Austin Payment Center Department of Veterans Affairs PO Box 149971 Austin TX 78714-9971
(877) 353-9791
(512) 460-5429
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 19 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 20 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 20 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 20 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 20 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 21 |
| 2.5 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) | 22 |
| 2.6 52.228-1 BID GUARANTEE (SEP 1996) | 24 |
| 2.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 24 |
| 2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 25 |
| 2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 25 |
| 2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 26 |
| 2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 26 |
| 2.12 PARTNERING | 27 |
| REPRESENTATIONS AND CERTIFICATIONS | 28 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) | 28 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019) | 32 |
| 3.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 33 |
| GENERAL CONDITIONS | 36 |
| 4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 36 |
| 4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2020) | 36 |
| 4.3 52.223-20 AEROSOLS (JUN 2016) | 39 |
| 4.4 52.223-21 FOAMS (JUN 2016) | 40 |
| 4.5 SUPPLEMENTAL INSURANCE REQUIREMENTS | 40 |
| 4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 41 |
| 4.7 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 44 |
| 4.8 VAAR 852.219-9 VA SMALL BUSINESS SUBCONTRACTING PLAN MINIMUM REQUIREMENTS (DEC 2009) | 44 |
| 4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 44 |
| 4.10 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 47 |
| 4.11 VAAR 852.219-76 SUBCONTRACTING PLANS MONITORING AND COMPLIANCE (JUL 2018) | 47 |
| 4.12 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 48 |
| 4.13 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS–CPM) (NOV 2018) (ALTERNATE I) | 48 |
| 4.14 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018) | 51 |
| 4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 55 |
| 4.16 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 56 |
| 4.17 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 57 |
| 4.18 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 57 |
| 4.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019) | 58 |
| 4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 58 |
| 4.21 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 60 |
| DESIGN BUILD SPECIFICATIONS | 74 |
| 4.22 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES | 74 |
| 4.23 OWNERSHIP OF ORIGINAL DOCUMENTS | 74 |
| 4.24 RETENTION OF REVIEW DOCUMENTS | 74 |
| 4.25 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION | 74 |
| 4.26 COORDINATION WITH MEDICAL CENTER | 75 |
| 4.27 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR | 75 |
| ATTACHMENTS | 76 |
| ATTACHMENT 1 - RELEASE OF CLAIMS | 76 |
Statement of Work for the Renovate Building 40 Coatesville VA Medical Center Coatesville, PA 19200
| Construction Documents Ready by: | 100 days after NTP issued | |
| Construction Complete by: | 200 days after NTP issued |
-- Services --
· Provide all inspection, design, supervision, labor, transportation, materials, tools and equipment, and design-build services necessary for design and construction of a project described here in other specific tasks as further defined by this request for proposal (RFP) renovation of Project No. 542-20-101, Renovate Building 40 Design-Build. The resultant contract of this procurement is to provide required design completion of the referenced project and perform construction of completed design work. Project shall be designed and completed in accordance with VA Criteria, EPA requirements, building codes life safety codes, and VA Specifications developed for the project.
Definitions:
· Design/Build (DB) Team (Offeror): The Team includes all Joint Venture (J/V) partners, consultants and sub-contractors to the one firm. The DB team shall provide all architectural and engineering disciplines for the preparation of construction documents, and all construction contractor capabilities for construction of the project.
· DB Architect/Engineer: The Design/Build A/E refers to the Architect-Engineer firm(s) that are a part of the DB team if a joint venture or other team
· This Request for Proposal (RFP) document is intended to generally define the scope and design parameters to be included in the project. It is the DB Team’s responsibility to provide a complete set of design documents in a manner consistent with VA guidelines, specifications, and design standards in order to complete construction within the 200-day schedule.
· If the DB A/E and prime contractor are a joint venture J/V (not one and the same firm) engineering and other technical consultants shall be subcontractors of the J/V architect – not the Design-Build construction contractor or sub-contractors. If the DB A/E and contractor is one and the same firm (not a J/V) those consultants shall be subcontractors of the DB firm not the construction subcontractors.
· The offer should reflect the Offer’s best terms, both from a cost and technical standpoint. See FAR 52.215-1, Instructions to Offerors – Competitive Acquisition (OCT 1997). Standard Form 1442 shall be used for submitting offers. Offerors shall submit separate prices for architect-engineer services, construction work and other activities. Under section 304 (b) of the Federal Property and Administrative Services Act, VA is not authorized to obligate funds or pay for architect-engineer services that exceed 6 percent of the estimated project cost, exclusive of fees.
· Offeror shall be prepared for a 200-day schedule as indicated below in the Project Schedule. Offeror may propose an alternate schedule, in addition to the 200-day schedule, which will be reviewed by the VA. Schedules shall indicate the following:
· The design period and provisions for VA reviews;
· Phasing plans for coordination of any site utility relocation work;
· Construction period services including:
· Interior Construction/exterior construction
· Procurement and installation of equipment
· Provisions for overtime or shift work shall be included for IT only.
· Equipment unloading, placing, repairing asphalt, and reports.
PROVIDE:
Professional Design/Build (DB) in compliance with healthcare planning services to include but not limited to:
· Contract drawings, specifications for construction, and cost estimate.
· Construction period services for DB A/E - review of shop drawing submissions, provide recommendations regarding contractor change proposals and RFI’s, DB A/E shall visit site per VA's request, add to drawings as-built conditions from contractor's record drawings; DB A/E will respond on site within a 3-day period when requested.
-- Project Scope --
GENERAL:
The objective of this project is to renovate building 40. This building is masonry with wood frame construction.
WARRANTY: All services provided by the contractor, as well as parts replaced shall come with a one (1) year warranty (minimum). All labor, tools, supplies, transportation, and equipment associated with the replacement of warranty items shall be provided by the contractor at no additional cost to the Government.
SPECIFICS:
The scope of this project is to hire a Design/Build team that will provide architectural design, tools, labor, material, and supervision, to renovate building 40.
Evaluation of existing conditions.
Free and clear access to all work area.
Site analysis and design charrettes as required.
Restore condition of disturbed grasses/vegetation.
The scope of work includes but is not limited to the following:
Abate Lead Paint in the Building:
· Removal of lead-based paint in its entirety.
· Removal of mold in its entirety.
· All work will be completed in strict accordance with the project specification and EPA, OSHA, Federal, State and PA Department of the Environment regulation.
· Proper Disposal of lead-based paint.
Building Repairs
· Replace/repair building structures such as floor joists, sub floor, and floor.
· Insulate walls and roof.
· Replace/repair building structures such as roof trusses.
· Relocate basement access to exterior of building.
Exterior Repairs:
· Remove existing roof and replace with standing seamless metal roof.
· Replace/repair damaged soffit on exterior of building.
· Replace/repair gutters and downspouts.
· Repair any block foundation issues.
· Repair tuck pointing as needed.
Mechanical:
· Demolish existing water line and cap.
· Demolish and dispose of existing electric water heater.
· Demolish existing PVC drain line from sink and cap.
· Install government furnished gas fired heater.
· Provide and install AC/heat pump.
Electrical:
· Demolish and provide new conduit in its entirety.
· Provide and install new electrical circuit.
· Provide fire alarm and tie into main system.
· Provide and install fiber optic cable.
Other considerations:
· Subsurface/geological evaluations as required.
· Implementing value-engineering decisions to meet required construction budget.
· Involvement of a certified industrial hygienist (CIH) to incorporate the necessary guidance in the construction documents as applicable.
· Providing submittals and final documents as indicated below.
PHASING: Construction must allow for continuance of all hospital operations and services provided and coordinate with adjoining projects. After-business hours work may be necessary as dictated by the COR. All items must go through the submittal process prior to acceptance.
- Site Investigations -
EXPECTATION: The DB A/E will make site visits as necessary to survey existing conditions.
Survey existing to determine existing as-built conditions affecting this project. All additional references and specifications are available in VHA’s Technical Information Library at address http://www.cfm.va.gov/til/. AutoCAD 2019 background drawings will be provided by the VA upon request but shall not be considered all-inclusive. The DB A/E shall field verify all dimensions and specifications. The DB A/E shall field verify every aspect that relates to the project. Coordinate site visits with the COR as determined after award.
-- Project Schedule --
EXPECTATION: Submit review package so they are received on the noted day.
SUBMISSIONS:
Submit review packages so they are received on the noted day (calendar days after Notice to Proceed (NTP) or earlier):
| Initial NTP Meeting | 0 days | |
| Design Development Documents (50%) | 30 days | |
| (Meeting to review 50%) | 40 days | |
| Design Development Documents (100%) | 70 days | |
| (Meeting to review 100%) | 80 days | |
| Construction Documents | 100 days | |
| (3 Sets of Drawings and Specifications CAD and PDF) |
Begin Construction ON-SITE on or before 110 days
Complete Construction on or before 200 days
Note: The issuance of the Notice to Proceed (NTP) for design will be at the first Project Design Team (PDT) Meeting. The Design-Build Team (Contractor and the DB A/E) will be required to attend and take minutes of each PDT meeting. Minutes will be submitted electronically to the COR and Contracting Officer within three calendar days of each meeting for an approval.
--Design Requirements and Submissions--
EXPECTATIONS: Submit complete review package in accordance with the following requirements and guidelines outlined in http://www.cfm.va.gov/contract/aeDesSubReq.asp. As appropriate and depending upon the complexity of the design, the DB A/E may elect to delete individual submissions where not required (i.e. Do not address Site Development, Landscaping for interior renovation projects, etc.)
DELIVER:
All design packages will be submitted directly to the Project Engineer/COR on the established dates to allow the VA to review. A transmittal letter is required to go to the Contracting Officer on the same day as delivery along with a copy of the drawings and CD’s.
Include all information as follows and as outlined in the attachments for each submission. Information required for each submittal is outlined in Program Guide PG-18-15 Volume C November 2008. The manual is available at the following address: http://www.cfm.va.gov/contract/aeDesSubReq.asp.
Design Development 50%: 50% Submission Requirements
· Define the design elements based on the presented option and submit all information required by the PG-18-15 (50% Design Development).
· Identify Working Drawings scope within the construction budget.
· Develop plans and marked up specifications to meet all applicable federal and state codes/requirements, including but not limited to PENDOT, OSHA, DER, EPA, NEC, NFPA 101 Life Safety Code.
· Identify all design calculations.
· Identify all existing utilities and utilities requirements.
· Develop initial cost estimate with thorough breakdown of values.
· Identify all phasing requirements for construction.
· Develop Infection Control Risk Assessment (VA EC-43)
Design Development 100%: 100% Submission Requirements
· Requirements for the 100% Design Development Documents Submission.
· Address all comments from the 50% review.
· Consolidate all necessary submittals by specification section on an Excel spreadsheet. Checklist to be utilized to track/monitor submittal process.
· Revise and update cost estimate.
· Finalize all design calculations.
· Finalize all phasing requirements for construction.
· Finalize impact of existing asbestos.
· Finalize Infection Control Risk Assessment (VA EC-43)
· Address all comments from the VISN Safety & Fire Protection Review.
Construction Documents:
· Provide construction documents after completion of design development.
Contract Documents (CD): Contract Documents Submission Requirements
· Submit a complete set of documents of all contract requirements. The Cover Page shall be submitted for approval signatures. If necessary, update and submit until approved by the VA. All pages are to have engineer stamp.
-- Construction Period Services --
Expectations: Respond to submittals within 14 days and other requests within 5 days.
PROVIDE:
· If a joint venture, assist the VA to determine whether the contractor or subcontractor meets qualification requirements, supported by written recommendations of any problems or litigation encountered in past based on first-hand knowledge.
· Review all shop drawing submissions and provide recommendations to the VA within five calendar days upon request.
· Review and provide replies to contractor generated RFI’s when required by the project manager or COR within five days.
· If a Joint Venture, review contractor's cost estimates and provide recommendations to the VA.
· Make site visits on requests of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design will be at no cost to the VA.
· Participate in partial and/or final acceptance inspections as scheduled and generate punch-list items for completion. The punch-list shall reference the contract documents for specific deficiencies (i.e. specification section, drawing detail, etc.)
· Prepare as-built drawings on original set with DB A/E’s stamp, based on record drawings that the contractor kept during construction. Transpose contractor’s as-built’s to AutoCAD 2019 and provide a set of updated as-built’s on CD within 30 days to the COR. Drawings shall be prepared as separate CAD and PDF documents, and full set of CAD and PDF documents. Specifications shall be in Word and PDF.
Design Development 50% Submission Requirements
Deliver the following (labeled with 50% submission) and include this attachment as a checklist with your submission:
· 2 copies of a narrative report forwarding the design develop 50% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager, and any design calculations or analysis.
· 1 half-size and 1 full size of all drawings updating all previous comments required by project and produced on Auto CAD 2019 software and PDF, binding XREF.
· 2 copies of updated itemized cost estimate by specification section or trade (labor, material and equipment).
· 1 copy of custom edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.
· 1 half size set of all drawings and electronic specifications, updating all previous comments required by project to send to the Fire Protection Engineer (TBD).
· 1 half size set of all drawings and specifications, updating all previous comments required by project to send for 3rd party Life Safety Review.
· 3 copies of CD’s of drawings in PDF and AutoCAD (versions 2019 acceptable) and specifications in PDF and Microsoft Word 2007 (or newer) on (CD). All documents on the CD are to be individual files and as a full-set file. 2 copies will be sent to the COR at Coatesville VAMC Building 70 1400 Black Horse Hill Road Coatesville, PA 19320. 1 copy will be sent to CO in Coatesville VAMC Building 16 1400 Black Horse Hill Road Coatesville, PA 19320.
Design Development 100% Submission Requirements
Deliver the following (labeled with 100% submission) and include this attachment as a checklist with your submission:
· 2 copies of a narrative report forwarding the design develop 100% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager and any design calculations or analysis.
· 2 sets of half size and one set of full size of all drawings updating all previous comments required by project produced on AutoCAD (2019 acceptable) software.
· 2 copies of the proposed construction schedule.
· 2 copies of final itemized cost estimate by spec section or trade (labor, material and equipment) and also by VA criteria, NRM, Minor, BSER and BSEA.
· 2 copies of final edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.
· 3 CD containing
· All drawings in PDF and AutoCAD (2019 acceptable) individually and as a full set
· All specifications in PDF and Microsoft Word 2007 (or newer) individually and as a full set
· Cost estimates, schedules, narratives, recommendations, phasing, and deducts shall be included in Word and PDF.
Expectation: Submit complete contract documents for final review prior to Notice to Proceed for Construction. Continue to submit contract documents until all changes are incorporated by the DB A/E for final signature prior to Notice to Proceed for Construction. Upon approval duplicate copies as required.
Deliver the following (labeled with Contract Documents Submission) and include this attachment as a checklist with your submission:
Contract Document Submission Requirements
· 1 copy of the Cover Sheet (AutoCAD) with signature blocks for final VA signatures with engineer stamps.
· 2 sets of half size and one set of full size of all drawings updating all previous comments required by project, produced on AutoCAD (2019 acceptable) software – for final VA review. Must include engineers stamp. If approved final sets to be submitted with signed off cover sheet.
· 2 copies of final project specification (bound) prepared in Microsoft Word 2007 (or newer) software. Include a master submittal list in the specifications.
· 3 CD containing
· All drawings in AutoCAD (2019 acceptable) and in a .pdf file as individual files and a complete file in each format
· All specifications in PDF and Microsoft Word 2007 individually and complete file
· Submittal Spreadsheet – identifying all the submittals required to be submitted by the contractor for review. The list shall be organized by division and specification.
· Upon signature approval, provide three (3) sets of final Contract Documents (complete with VA signed Cover Sheet). Provide two (2), half (½) size sets of final drawings.
Page 1 of
Page 1 of
EVALUATION CRITERIA FOR AWARD
This section of the solicitation outlines the competitive source selection process which will result in one (1) award to an eligible Service-Disabled Veteran Owned Small Business (SDVOSB) concern. The selection process is structured based on a two-phase Design-Build selection process in accordance with FAR Subpart 36.3. In addition, the evaluation incorporates the procedures in FAR Subpart 15.1 utilizing a “Best Value” source selection process with the option of a trade-off strategy for all non-cost/non-price evaluation factors. The Government intends to award, without discussions to the offeror deemed responsible in accordance with the Federal Acquisition Regulation (FAR) Subpart 9.1 and FAR 52.215-1. The offeror’s proposal must conform to the solicitation requirements and be judged to represent a “Best Value” to the Government. The “Best Value” is the most advantageous offer, design concepts, proposed technical solutions, key personnel, construction management and price considered and consistent with the Government's stated importance of evaluation criteria.
THE GOVERNMENT RESERVES THE RIGHT TO AWARD TO OTHER THAN THE LOW- PRICED OFFERORS. This may result in award being made to a higher-rated, higher-priced offeror(s) where the Contracting Officer determines that an offeror's proposal offers a “Best Value” that outweighs the price difference. To arrive at a best value decision, an integrated assessment between all non-cost/non-price evaluation factors and price will be conducted.
Phase 1 of the selection process includes the receipt of offers from all interested firms eligible to receive an award set-aside exclusively for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns. NO PRICING INFORMATION SHALL BE SUBMITTED DURING THIS PHASE 1 PROCESS. NO BONDS SHALL BE SUBMITTED DURING PHASE 1 PROCESS. The Phase 1 evaluation will consist of a review and evaluation of each offer against the Phase 1 evaluation factors. Thereafter, proposals shall be ranked and the three (3) most highly rated offers shall be selected to participate in the Phase 2 of this process. All offers not selected to participate in Phase 2 shall be notified that no further consideration of their proposal will be given.
Phase 2 evaluation process will exist amongst the three (3) most highly rated offers selected from Phase 1. The Phase 2 proposals shall be submitted in two parts: Volume 1-Technical Proposal and Volume 2-Price Proposal. Bonds are required in Phase 2, Volume 2-Price Proposal. The Phase 2 evaluation process will consist of an in- depth review of an offeror’s technical approach, as well as an examination of the offeror’s response to each evaluation criteria as compared to the solicitation requirements. In the final selection, proposals will be ranked based on an offeror’s demonstration of technical understanding by the thoroughness, soundness, comprehensiveness and price reasonableness of its technical approach.
EVALUATION FACTORS
Design Build Solicitation This project will be solicited as a firm fixed price best value contract. The solicitation will be conducted as a two-phase design / build in accordance with FAR 36.3. The A/E and construction contractor team shall be required to submit information in two phases.
Under Phase I of the solicitation the contractor Design-Build Team shall be required to submit detailed information on the following as explained later in the solicitation:
1. Technical approach
2. Technical qualifications
a. Specialized Experience and Technical Competence
b. Capability to Perform
c. Past Performance
The factors are of equal weight of importance, and an overall rating shall be assigned.
The following information/documentation is required as part of the offeror’s Phase I proposal:
SUBMISSION REQUIREMENTS for Phase I: Interested firms having the capabilities to perform this work shall submit one (1) hard copy along with one (1) electronic (CD) copy. Submissions by electronic means i.e. e-mail are NOT permitted. Additionally, the submission shall include an insert detailing the following information:
1. Dun & Bradstreet Number
2. Tax ID Number
3. The e-mail address and phone number of the Primary Point of Contact
4. A printed copy of the firm’s VIPS Registry
5. A printed copy of the firm’s SAM Registry
6. Certification of OSHA and EPA violations
7. EMR Rating
8. VETS 4212 filing
9. Contractor shall provide detailed information for each of the following factors that the Government will evaluate. Information shall be presented in a manner that highlights your firm’s capabilities in meeting the specific areas that are listed under each evaluation factor. Detailed information of Phase I:
a) Technical Approach – provide design and construction approach; roles and responsibilities; quality control policies and standards; scheduling methodology; and considerations for fast tracking.
b) Specialized Experience and Technical Competence to include general renovations; number and duties of proposed staff: addressing function, responsibilities and authorities of key personnel designing and constructing to signage and wayfinding design and installation.
c) Past Performance of at least three but no more than five projects similar in size and scope.
This information will then be evaluated, and the Government shall select the three most highly qualified offerors. The Contracting Officer will then issue a Request For Proposal to the three most highly qualified offerors to provide the information per Phase II of the solicitation. All questions are to be sent to the attention of Benjamin.Villasenor@va.gov .
Phase I Rating Guidance:
There are two (2) non-priced evaluation factors for Phase I. Included in the second factor are three (3) sub-factors. Each factor will receive a rating with an overall total rating established for Phase I. The factors are of equal weight of importance
1. Technical Approach:
This factor evaluates how the individual offeror will approach the design and construction of this project. The offeror shall provide detailed information addressing the organization and the roles and responsibilities of the various sub-contractors for both the design and construction.
Offeror shall also provide adequate detail on the offeror’s policy regarding Quality Control (QC) and how the offeror intends to achieve this standard on the project. The offeror is to provide the scheduling methodology and demonstrate an understanding of its limitation and success. The offeror shall also include considerations of “Fast Track” construction whereby preliminary site construction activities can begin prior to the completion of the accepted 100% design documents
2. Technical Qualifications:
a) Specialized Experience and Technical Competence:
1. This factor evaluates the experience of the construction firm and design team in completing projects requiring skills like those anticipated for this contract. This includes experience in working on demolition, lead paint abatement, excavation, framing, electrical systems, telecommunications, and standing seamless roofs.
2. This factor also evaluates offeror’s number of personnel and the duties of proposed technical staff to determine if offeror can manage project within the area of consideration without significant difficulty.
3. Offeror should adequately address functions, responsibilities and authorities for performing such duties as overall project management, site superintendence, quality control, safety, administration and in-house trade capabilities.
4. Offeror shall provide a minimum of three (3) project examples like the one proposed at the Coatesville VA Medical Center
b) Capability to Perform:
1. This factor evaluates the ability of the Construction firm to perform given their current projected workload and the availability of their key personnel, to accomplish the project in the required time.
c) Previous Experience/Past Performance:
The Past Performance proposal evaluation will consider such things as an offeror's business practices, quality, customer relationship, and ability to successfully perform as proposed and other considerations considering currency, relevancy, sources, context, and trends. Past Performance includes current on-going (present) performance.
To conduct the performance risk assessment, the Government may use data provided by the offeror, and data obtained from other sources. An offeror with no Past Performance may receive a rating based on the evaluation of its predecessor companies, key personnel, and/or subcontractors. These ratings may have the same weight as the ratings of the proposing company. If such information is not applicable (i.e., the offeror does not have a predecessor company, key personnel or subcontractors with relevant experience), the offeror shall be evaluated as "Neutral”. However, the proposal of an offeror with no relevant Past Performance history, while rated” Neutral” in Past Performance, may not represent the most advantageous proposal to the Government. For this solicitation, currency is performance occurring within the last five years through the solicitation release date. Within this period, performance occurring later in the period may have greater significance than work occurring earlier in the period. For example, performance information for work occurring during 2015 may have greater importance than performance information for work occurring during 2010.
In assessing relevancy, the Government may evaluate an offeror's references for similarity of the construction methods to the scope of this solicitation, (multi-discipline or specialized area), scope/type of contracts/projects, cost magnitude of projects as it relates to price. Performance on managing multiple multi-disciplined projects at one time may also be considered.
PHASE 1 EVALUATION FACTORS
Offerors shall be evaluated according to the following evaluation factors for Phase 1:
1. Technical Approach: Technical approach to performing the work as outlined in the Statement of Work.
2. Technical Qualifications
a. Specialized Experience and Technical Competence: Specialized experience of the A/E in designing similarly scoped projects.
b. Capability to Perform
c. Previous Experience/Past Performance: Experience of contractor team in renovation of small structures.
Phase 1-The Phase 1 evaluation will result in the selection of the three (3) most highly rated offers for participation and proposal submission in the Phase 2 process. During the Phase 1 evaluation process, only technical evaluation factors will be considered. No consideration of pricing will occur during this phase. The evaluation factors under consideration for Phase 1 are listed below, and will be evaluated as Excellent, Good, Satisfactory, Marginal and Unsatisfactory.
Factor 1: Technical Approach
· Offerors shall provide a written narrative approach proposed to accomplish the statement of work. Discussion of the technical approach shall contain explanations of proposed approaches to performing and accomplishing the work. \
· Include as part of the narrative a statement of any problems anticipated in accomplishing the work and an evaluation of the various methods considered for resolving the problems/difficulties.
· Include a proposed project plan which outlines the work to be accomplished to include a start/completion schedule.
· Offeror shall include the extent of anticipated subcontracting together with a list of work to be subcontracted.
Factor 2: Technical Qualifications
a. Specialized Experience and Technical Competence
· Offeror shall describe their specialized experience and technical competence of key personnel proposed for this project to include both Design and Construction Period services. Offerors shall also describe the resources that will be applied to this project and describe the unique capability they offer to the VA. Offer shall describe the areas of work that will be subcontracted to specialty contractors.
b. Capability to Perform:
· Demonstrates in detail their current projected workload and the availability of their key personnel that shall ensure all contractual requirements will be completed on time.
c. Previous Experience/Past Performance
· Offerors shall describe a minimum of three (3) and a maximum of five (5) completed Design/Build projects within the past 5 years. The projects listed under this factor shall be similar in scope and complexity as the subject project. Information listed under this factor must be completed projects. Projects listed under this factor that are not completed will seriously affect the rating of the offer. The following format must be followed in providing Previous Experience/Past Performance information: Government Agency/Company which awarded contract to offeror
a. Contract Number
b. Complete Description of Contract Scope
c. Total Dollar Value
d. Performance Period
e. Place of Performance
f. Contracting Officer/Procurement Official
a. Name
b. Email
c. Phone Number
d. Address
PHASE 2 EVALUATION FACTORS
Technical proposals for Phase 2 shall be evaluated according to the following evaluation factors:
1. Technical Design Schematic.
2. Management Plan.
3. Scheduling.
4. Price.
Phase 2- The Phase II proposals shall be submitted in two parts: Volume 1-Technical Proposal and Volume 2-Price Proposal. Evaluators will initially be provided for only the technical proposal of the offerors selected for participation in Phase 2. Following completion of the technical evaluation, the SSEB will be provided pricing information for further consideration. An integrated assessment of design concept/proposed technical solution, construction management, key personnel, capability to perform and price will be conducted, and the results ranked. A trade-off may occur, if the Contracting Officer determines that an offeror's proposal offers a “Best Value” that outweighs a higher price.
The “Best Value” is the most advantageous offer, design concept/proposed technical solutions, construction management, key personnel, capability to perform and price considered and consistent with the Government's stated importance of evaluation criteria. The evaluation factors under consideration for Phase 2 are listed below, and will be evaluated as Excellent, Good, Satisfactory, Marginal and Unsatisfactory.
The Phase 2 evaluation factors are:
Phase 2 There are three (3) non-priced evaluation factors and one (1) price evaluation factor for Phase II of the solicitation. The following factors are equal in importance, and when combined are significantly more important than price. The factors are of equal weight of importance.
1. Technical Design Schematic
· Offerors shall provide a detailed approach proposed to accomplish the statement of work. Discussion of the technical approach shall contain explanations of proposed approaches to performing and accomplishing the work including communications, quality control, cost controls, review/oversights, inspections, safety, and infection control.
· Discuss in detail problems anticipated in accomplishing the work and an evaluation of the various methods considered for resolving the problems/difficulties
· Offeror shall include the extent of anticipated subcontracting together with a list of work to be subcontracted.
· The offeror shall submit conceptual drawings, renderings, product data sheets, one-line diagrams, etc.
2. Management Plan
a. Subfactor 1: Project Personnel:
· A resume or information provided for each proposed personnel which includes, Project Management, site superintendence, quality control manager, infection and safety, as well as a list of major subcontractors and A-E design personnel who will be utilized throughout the life of the contract, should be included with detailed background, education, current certifications, and indicative of acceptable experience and listing of projects where personnel worked together as a team.
b. Sub-factor 2: Quality Control & Risk Assessment:
· Offeror must submit a written plan which demonstrates the ability to Complete the project and all requirements within the contract terms and conditions.
· Demonstrates techniques for maintain quality control for workmanship, material, and work progress.
· Demonstrates in detail office procedures that ensure all contractual requirements will be completed on time and all written documents and records (e.g., payrolls, daily logs, submittals, insurance certificates, payments, change orders, supplemental agreements, correspondence, etc.) are easily accessible.
· Demonstrates techniques for work coordination with Subcontractors. Describe what is in place to monitor performance of Subcontractors and guarantee performance. Describe how contract requirements flow down to the lowest level of Subcontractor.
· Demonstrates in detail a written Risk Assessment on this project to include an understanding of the site conditions and plans to deal with varying elements and factors affecting the work (e.g, weather, local obstacles, public access and other conditions, inflation, cost of fuel, length of contract performance as it relates to offering a firm-fixed-price without the ability to make inflationary adjustments). The Risk Assessment shall include what contingencies are being anticipated and what plans are proposed to address them.
3. Scheduling:
· Must demonstrate the ability to meet the completion of construction of 200 days from NTP, including all milestones throughout this project.
· Describe objectives to be completed at each of the design milestones.
· Breakdown the time needed demo and renovate of project.
· Phasing for all stages of proposed project.
4. Price Evaluation:
· Provide pricing to include all work to be completed for the entire design and construction of the project. Must follow guidelines according to FAR 15.404-1(b)(2)(i)
When combined all non-cost/non-price evaluation factors are significantly more important than price and may be used as a tradeoff for a higher rated higher priced technical proposal.
Coatesville Veterans Affairs Medical Center (CVAMC) Design / Build Renovate Building 40
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 2.5 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .