S06_COMMISSIONING_PROCESS_ROLES_AND_RESPONSIBILITIES_019100.pdf
PDF 78 KB Posted
- Attached to
- Project 646-16-109 UD Replace Kitchen Federal contract opportunity
- Solicitation number
- 36C24419B0005
About this file
36C24419B0005 0002 S06 COMMISSIONING PROCESS ROLES AND RESPONSIBILITIES 019100.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24419B0005_0004.docx | DOCX document | |
| 36C24419B0005_0003.docx | DOCX document | |
| S06_SUBMITTAL_REGISTER_013323.A.pdf | ||
| 36C24419B0005_0002.docx | DOCX document | |
| S04_PRE-CON_SIGN_IN_SHEET.pdf | ||
| S06_REFR_CONTAINER_SPECS.pdf | ||
| S06_IMIGRATION_COMPLIANCE_FORM.pdf | ||
| S06_SCHEDULE_FOR_FINISHES_090600.pdf | ||
| S06_NOISE_AND_VIBRATION_GUIDE__230541.pdf | ||
| 36C24419B0005_0001.docx | DOCX document | |
| S02_SPECIFICATIONS_VOL_1.pdf | ||
| S02_DRAWINGS_02.pdf | ||
| S02_SPECIFICATIONS_VOL_2.pdf | ||
| S02_DRAWINGS_01.pdf | ||
| S02_DRAWINGS_03.pdf | ||
| 36C24419B0005_1.docx | DOCX document | |
| 36C24419B0005-000.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dept. of Veterans Affairs VA Project #646-16-109 VA Pittsburgh Healthcare System UD Replace Kitchen AHU (AC-6) Pittsburgh, PA Construction Bid Documents: 06/15/18
01 91 00 - 35
PART 3 - EXECUTION
3.1 COMMISSIONING PROCESS ROLES AND RESPONSIBILITIES
A. The following table outlines the roles and responsibilities for the Commissioning Team members during the Construction Phase:
Construction Phase CxA = Commissioning Agent
RE = COR
A/E = Design Arch/Engineer
PC = Prime Contractor
O&M = Gov’t Facility O&M
L = Lead
P = Participate
A = Approve
R = Review
O = Optional
Commissioning Roles & Responsibilities
Category Task Description CxA RE A/E PC O&M Notes
Meetings Construction Commissioning Kick Off meeting
L A P P O
Commissioning Meetings L A P P O
Project Progress Meetings P A P L O
Controls Meeting L A P P O
Coordination Coordinate with [OGC's, AHJ, Vendors, etc.] to ensure that Cx interacts properly with other systems as needed to support the OPR and BOD.
L A P P N/A
Cx Plan & Spec Final Commissioning Plan L A R R O
Schedules Duration Schedule for Commissioning Activities
L A R R N/A
OPR and BOD Maintain OPR on behalf of Owner L A R R O
Maintain BOD/DID on behalf of Owner L A R R O
01 91 00 - 36
Construction Phase CxA = Commissioning Agent
RE = COR
A/E = Design Arch/Engineer
PC = Prime Contractor
O&M = Gov’t Facility O&M
L = Lead
P = Participate
A = Approve
R = Review
O = Optional
Commissioning Roles & Responsibilities
Category Task Description CxA RE A/E PC O&M Notes
Document Reviews
TAB Plan Review L A R R O
Submittal and Shop Drawing Review R A R L O
Review Contractor Equipment Startup Checklists
L A R R N/A
Review Change Orders, ASI, and RFI L A R R N/A
Site Observations
Witness Factory Testing P A P L O
Construction Observation Site Visits L A R R O
Functional Test Protocols
Final Pre-Functional Checklists L A R R O
Final Functional Performance Test Protocols
L A R R O
Technical
Issues Resolution Meetings P A P L O
Reports and Logs
Status Reports L A R R O
Maintain Commissioning Issues Log L A R R O
01 91 00 - 37
B. The following table outlines the roles and responsibilities for the Commissioning Team members during the Acceptance Phase:
Acceptance Phase CxA = Commissioning Agent
RE = COR
A/E = Design Arch/Engineer
PC = Prime Contractor
O&M = Gov’t Facility O&M
L = Lead
P = Participate
A = Approve
R = Review
O = Optional
Commissioning Roles & Responsibilities
Category Task Description CxA RE A/E PC O&M Notes
Meetings Commissioning Meetings L A P P O Project Progress Meetings P A P L O Pre-Test Coordination Meeting L A P P O Lessons Learned and Commissioning Report Review Meeting L A P P O
Coordination Coordinate with [OGC's, AHJ, Vendors, etc.] to ensure that Cx interacts properly with other systems as needed to support OPR and BOD
L P P P O
Cx Plan & Spec Maintain/Update Commissioning Plan L A R R O
Schedules Prepare Functional Test Schedule L A R R O
OPR and BOD Maintain OPR on behalf of Owner L A R R O
Maintain BOD/DID on behalf of Owner L A R R O
Document Reviews
Review Completed Pre-Functional Checklists L A R R O
Pre-Functional Checklist Verification L A R R O Review Operations & Maintenance Manuals L A R R R
01 91 00 - 38
Acceptance Phase CxA = Commissioning Agent
RE = COR
A/E = Design Arch/Engineer
PC = Prime Contractor
O&M = Gov’t Facility O&M
L = Lead
P = Participate
A = Approve
R = Review
O = Optional
Commissioning Roles & Responsibilities
Category Task Description CxA RE A/E PC O&M Notes
Training Plan Review L A R R R Warranty Review L A R R O Review TAB Report L A R R O
Construction Observation Site Visits L A R R O Witness Selected Equipment Startup L A R R O
Functional
TAB Verification L A R R O Systems Functional Performance Testing L A P P P Retesting L A P P P
Issues Resolution Meetings P A P L O Systems Training L S R P P
Reports and Logs
Status Reports L A R R O Maintain Commissioning Issues Log L A R R O Final Commissioning Report L A R R R Prepare Systems Manuals L A R R R
C. The following table outlines the roles and responsibilities for the Commissioning Team members during the Warranty Phase:
01 91 00 - 39
Warranty Phase CxA = Commissioning Agent
RE = COR
A/E = Design Arch/Engineer
PC = Prime Contractor
O&M = Gov’t Facility O&M
L = Lead
P = Participate
A = Approve
R = Review
O = Optional
Commissioning Roles & Responsibilities
Category Task Description CxA RE A/E PC O&M Notes
Meetings Post-Occupancy User Review Meeting L A O P P
Periodic Site Visits L A O O P
Functional
Deferred and/or seasonal Testing L A O P P
Issues Resolution Meetings L S O O P
Post-Occupancy Warranty Checkup and review of Significant Outstanding Issues
L A R P
Reports and Logs
Final Commissioning Report Amendment L A R R Status Reports L A R R