620A4-19-203 Replace Fan Coil Units Add1 Drawings.pdf
PDF 3 MB Posted
- Solicitation number
- 36C24224B0022
About this file
This document is a set of drawings and specifications for a project to replace fan coil units in Building 15 at the Castle Point VA Medical Center in Wappingers Falls, New York. The project involves demolishing existing 4-pipe fan coil units and installing new fan coil units with chilled water and hot water connections. The drawings provide details on the mechanical, electrical, and control system work required. The project number is 620A4-19-203 and the solicitation number is 36C24224B0022. The project is being procured by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2. The required completion date for the work is August 25, 2023. The contractor will be responsible for coordinating the work to minimize disruption to the occupied facility, following infection control procedures, and integrating the new fan coil units into the existing building automation system.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT LOCATION:
BUILDING 15H
15H 15E
79 88
82A
75A
MP
N
Rive r R d
Newburgh Beacon
HU
D
S O
N
RI
VE
R
B alm v ille R d
Bridge
Fostertown Rd
84 Exit 11
Matte awan S
t. H osp
Rd
North Rd
Fish kill
A ve
Castle Point Rd
Chelsea Rd
VA HUDSON VALLEY
HEALTH CARE
SYSTEM
CASTLE POINT
CAMPUS
Holmes Rd La tti n t o w n R d
Stoneykill Rd
New Dr
Greenw ood Dr
Main St 84 Exit 12
Baxtertown Rd
Old Hopewell Rd
Smithtown Rd
Ketchamtown Rd
9d 9W
105063
ST
ATE
OF NEW YORK
MA
T TH
EW LLOYD
LICENSED PROFESSIONAL
EN
GI
NE
ER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTSOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Watson Engineering, P.C.
1112 State Rte. 434 Owego, NY 13827 (607)223-4334
REPLACE FAN COIL UNITS
CASTLE POINT VAMC, WAPPINGERS FALLS, NEW YORK
620A4-19-203
15H
08/25/2023 MPL AMR
10/5/2022
BI
M
VA
-2
R ep la ce
F an
C oi l U ni ts /R ep la ce F an C oi l U ni ts
.rv t
4/ 4/
:4
9:
P M
T-100
TITLE SHEET
REPLACE FAN COIL UNITS
BUILDING 15, VA MEDICAL CENTER, CASTLE POINT
41 CASTLE POINT RD, WAPPINGERS FALLS, NY 12590
PROJECT NO: 620A4-19-203
CAMPUS MAP SITE LOCATION
DRAWING INDEX
SHEET
NUMBER SHEET NAME
T-100 TITLE SHEET
G-001 ICRA, CODE NOTES, AND INTERIM LIFE SAFETY FLOOR PLAN
M-001 MECHANICAL NOTES, ABBREVIATIONS, AND SYMBOLS
MD101 MECHANICAL 1ST FLOOR DEMOLITION PLAN
M-101 MECHANICAL BASEMENT NEW WORK PLAN
M-102 MECHANICAL 1ST FLOOR NEW WORK PLAN
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-601 MECHANICAL SCHEDULES
M-701 MECHANICAL EQUIPMENT CONTROLS
E-001 ELECTRICAL NOTES, ABBREVIATIONS AND SYMBOLS
ED101 ELECTRICAL 1ST FLOOR DEMOLITION PLAN
E-101 ELECTRICAL 1ST FLOOR NEW WORK PLAN
E-601 ELECTRICAL SCHEDULES
E-602 ELECTRICAL RISER DIAGRAMS
Revisions: Date:
2 BEDROOM
H-130
DAYROOM
H-129
2 BEDROOM
H-128
TOILET
H-128A
WC STOR.
H-127
BATH
H-126ASINGLE
BEDROOM
H-126
SINGLE
BEDROOM
H-125
2 BEDROOM
H-124
BATH
H-125A
BATH
H-124A
2 BEDROOM
H-123
2 BEDROOM
H-120
BATH
H-123A
BATH
H-120A
2 BEDROOM
H-119
BATH
H-119A
EQPM. CLOSET
H-118
TOILET
H-117A
4 BEDROOM
H-117
CLEAN UTIL.
STORAGE
H-116
STORAGE
H-146
SINGLE
BEDROOM
H-132
SINGLE
BEDROOM
H-133
2 BEDROOM
H-135
2 BEDROOM
H-136
4 BEDROOM
H-138
TOILET
H-130A
BATH
H-132A
STOR.
H-131
BATH
H-133A
BATH
H-135A
BATH
H-136A
TOILET
H-138A
ELECT. CL.
H-137
DATA CLOSET
H-139
LOUNGE
H-100
ELEVATOR
LOBBY
C1-01
CLEAN LINEN
H-101
ELEVATOR
ELEVATOR
MECH. EQUIP
ROOM
H-103
TOILET
H-105A
CONFERENCE
ROOM
H-105
FAMILY ROOM
H-107
TOILET
H-107A
FEMALE
LOCKERS
H-114
TOILET
H-114A SHOWER
H-114B
SHOWER
H-115
TOILET
H-115B
MALE LOCKERS
H-115A
STAFF LOUNGE
H-113
DIST SUPPLY
CL.
H-143
BATHROOM
H-142
OFFICE
H-111
STORAGE
H-109
NUTRITION
ROOM
H-110
TOILET
H-108
OFFICE
H-106
MED ROOM
H-112
OFFICE
H-106A
SOILED UTILITY
H-104
WHEEL CHAIR
STORAGE
H-102
STORAGE
H-140
E.M.S. CL
H-141
SOUTH STAIR
HALL
CENTER STAIR
HALL
150' TRAVEL
DISTANCE
1'
T R
AV
EL
D
IS
TA
N C
E
7' - 9 1/4"
7'
3/
4"
30-MINUTE SMOKE BARRIER
2-HR FIRE BARRIER
105063
ST
ATE
OF NEW YORK
MA
T TH
EW LLOYD
LICENSED PROFESSIONAL
EN
GI
NE
ER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTSOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Watson Engineering, P.C.
1112 State Rte. 434 Owego, NY 13827 (607)223-4334
REPLACE FAN COIL UNITS
CASTLE POINT VAMC, WAPPINGERS FALLS, NEW YORK
620A4-19-203
15H
08/25/2023 MPL AMR
10/5/2022
BI
M
VA
-2
R ep la ce
F an
C oi l U ni ts /R ep la ce F an C oi l U ni ts
.rv t
4/ 4/
:4
8:
P M
G-001
ICRA, CODE NOTES, AND INTERIM
LIFE SAFETY FLOOR PLAN
INFECTION CONTROL NOTES
THE PURPOSE OF INFECTION CONTROL PROCEDURES IS TO MINIMIZE THE POTENTIAL FOR THE SPREAD OF INFECTIONS DUE TO DEGRADED AIR QUALITY, ENVIRONMENTAL CONTAMINATION, OR CONTAMINATION OF WATER. IT IS THE POLICY OF THIS MEDICAL CENTER THAT A SYSTEMATIC APPROACH BASED ON ASSESSMENT AND PLANNING WILL EFFECTIVELY MANAGE THE ISSUE OF TRANSMISSION OF INFECTIOUS DISEASES AND THE AGGRAVATION OF ALLERGIES.
THE OVERALL APPROACH RELIES ON PRE-CONSTRUCTION ASSESSMENT, MANAGEMENT OF HVAC SYSTEMS, AND AGGRESSIVE USE OF A VARIETY OF BARRIERS. CONTRACTOR IS TO WORK CLOSELY WITH THE VA FACILITY MANAGEMENT SERVICE. THE INFECTION CONTROL PROGRAM STAFF AND THE SAFETY AND OCCUPATION HEALTH MANAGER TO HAVE IN PLACE A MONITORING PROGRAM TO ASSURE RIGOROUS IMPLEMENTATION OF THE REQUIRED MEASURES.
REFER TO PROJECT SPECIFICATIONS.
A. THE CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE FIELD AND COORDINATE ALL INFECTION CONTROL REQUIREMENTS WITH THE DEMOLITION AND NEW CONSTRUCTION. THE CONTRACTOR SHALL REPORT ALL DISCOVERIES TO THE OWNER'S REPRESENTATIVE FOR RESOLUTION
PRIOR TO BEGINNING.
B. CONTRACTOR TO INSTALL BARRIERS AND OTHER MEASURES. CONSTRUCTION BARRIER DOOR(S) MUST BE SELF-CLOSING. PROVIDE DUST CONTROL AND CONTAINMENT STICKY MATS ON ALL ACCESS DOORS INTO CONSTRUCTION AREA. ANTE-ROOM REQUIRED AT CONSTRUCTION ENTRY. PROVIDE
MANOMETER MONITORS FOR ALL CONSTRUCTION BARRIERS.
C. CONTRACTOR TO DISPOSE OF MATERIALS BEFORE 8:00AM OR AFTER 4:00PM UNLESS ARRANGED WITH THE VA TO DISPOSE OF DURING NORMAL HOURS. USE ROUTE AGREED UPON BY ICRA TEAM AND COTR FOR TRANSPORT OF TRANSPORT CONTAINERS THROUGH THE FACILITY. CONTRACTORS CAN ONLY DEVIATE TO NORMAL HOURS WITH THE APPROVAL OF THE INFECTION CONTROL NURSE AND COR DUE TO PARTICULAR CIRCUMSTANCES THAT MAY OBSTRUCT PROGRESS. A CLEAR PLAN WILL HAVE TO BE SUBMITTED AND PRECAUTIONARY INFECTION CONTROL MEASURES IMPLEMENTED.
D. CONTRACTOR TO COVER CARTS AND WEAR BOOTIES WHEN DISPOSING MATERIALS.
E. CONTRACTOR TO CHANGE MATS MULTIPLE TIMES A DAY AS NEEDED AND MOP FLOORS BEHIND THEM MULTIPLE TIMES A DAY.
F. CONTRACTOR TO MAINTAIN CONTINUOUS NEGATIVE AIR PRESSURE WITHIN THE WORK SITE UTILIZING WINDOW EXHAUST FANS STRATEGICALLY LOCATED OR PROVIDE NEGATIVE PRESSURE AIR HEPA UNITS AND EXHAUST TO EXTERIOR OF THE BUILDING. CONTRACTOR TO INCLUDE MONITORING
MANOMETER AT ANTEROOM SO THE NEGATIVE PRESSURE CAN BE INSPECTED.
CODE NOTES
A. 1. PRIMARY APPLICABLE CODES AND STANDARDS - EXISTING BUILDING / RECONSTRUCTION
THE DEPARTMENT OF VETERANS AFFAIRS HAS ADOPTED THE LATEST EDITION OF THE FOLLOWING CODES AND STANDARDS AS A MINIMUM FOR ALL PROJECTS PERFORMED IN THE MODERNIZATION, ALTERATION, ADDITION OR IMPROVEMENT OF ITS REAL PROPERTY AND THE CONSTRUCTION OF NEW
STRUCTURE.
a. NFPA 101 LIFE SAFETY CODE, 2021 EDITION
b. NFPA NATIONAL FIRE CODES (WITH THE EXCEPTION OF NFPA 5000 AND NFPA 900)
c. NATIONAL ELECTRIC CODE (NEC)
d. INTERNATIONAL PLUMBING CODE (IPC)
e. ASME BOILER AND PRESSURE VESSEL CODE
f. ASME CODE FOR PRESSURE PIPING
g. ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN GUIDE (PG-18-13)
h. ENERGY POLICY ACT (EPAct)
i. VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON
THE TECHNICAL INFORMATION LIBRARY (TIL)
j. VA MENTAL HEALTH DESIGN GUIDE
k. INTERNATIONAL BUILDING CODE (IBC) - ONLY WHEN SPECIFICALLY REFERENCE IN VA DESIGN DOCUMENTS
l. OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS
m. PHYSICAL SECURITY DESIGN MANUAL (PSDM)
2. THE CONSTRUCTION CLASSIFICATION IS TYPE II (222). THE MINIMUM FIRE RATING FOR ALL LOAD BEARING STRUCTURAL ELEMENTS IS 2 HOURS. IF DURING CONSTRUCTION, ANY DAMAGE TO EXISTING FIREPROOFING IS OBSERVED OR IF DISCOVERED THAT ANY FIRE PROTECTION IS MISSING, THE
CONTRACTOR SHALL REPAIR TO MAINTAIN FULL PROTECTION.
NFPA 101 REVIEW
B. CHAPTER 19 EXISTING HEALTH CARE OCCUPANCIES
1. (19.1.1.1) THE REQUIREMENTS OF THIS CHAPTER SHALL APPLY TO EXISTING BUILDINGS OR PORTIONS THEREOF CURRENTLY OCCUPIED AS HEALTH
CARE OCCUPANCIES.
2. (19.1.5) THE CLASSIFICATION OF HAZARD OF CONTENTS SHALL BE AS DEFINED IN SECTION 6.2.
C. MEANS OF EGRESS - CHAPTER 19 AND CHAPTER 7
1. (19.2.1) ALL MEANS OF EGRESS SHALL BE IN ACCORDANCE WITH CHAPTER 7 & THIS CHAPTER.
2. (19.2.3.1) THE CAPACITY OF MEANS OF EGRESS SHALL BE IN ACCORDANCE WITH SECTION 7.3:
A. TABLE 7.3.1.2 OCCUPANT LOAD FACTOR FOR HEALTH CARE (INPATIENT TREATMENT DEPARTMENTS) = 240 SF PER PERSON.
16,000 SF / 240 = 66 OCCUPANTS
3. (19.2.3.4) ANY REQUIRED AISLE, CORRIDOR, OR RAMP REQUIRED FOR EXIT ACCESS SHALL BE NOT LESS THAN 48 IN. IN CLEAR WIDTH WHERE SERVING
AS MEANS OF EGRESS FROM PATIENT SLEEPING ROOMS.
4. (19.2.6.2.1) THE TRAVEL DISTANCE BETWEEN ANY POINT IN A ROOM AND AN EXIT SHALL NOT EXCEED 150 FT, UNLESS OTHERWISE PERMITTED BY 19.2.6.2.2.
A. (19.2.6.2.2) THE MAXIMUM TRAVEL DISTANCE SPECIFIED IN 19.2.6.2.1 SHALL BE PERMITTED TO BE INCREASED BY 50 FT IN BUILDINGS
PROTECTED THROUGHOUT BY AN APPROVED, SUPERVISED, AUTOMATIC SPRINKLER SYSTEM.
5. (7.1.3.1) EXIT ACCESS CORRIDORS. CORRIDORS USED AS EXIT ACCESS AND SERVING AN AREA HAVING AN OCCUPANT LOAD EXCEEDING 30 SHALL BE SEPARATED FROM OTHER PARTS OF THE BUILDING BY WALLS HAVING NOT LESS THAN A 1-HOUR FIRE RESISTANCE RATING IN ACCORDANCE
WITH SECTION 8.3, UNLESS OTHERWISE PERMITTED BY ONE OF THE FOLLOWING:
A. THIS REQUIREMENT SHALL NOT APPLY TO EXISTING BUILDINGS, PROVIDED THAT THE OCCUPANCY CLASSIFICATION DOES NOT CHANGE.
6. (7.1.5.1) MEANS OF EGRESS SHALL BE DESIGNED AND MAINTAINED TO PROVIDE HEADROOM NOT LESS THAN 7 FT 6 IN, UNLESS OTHERWISE SPECIFIED
BY ANY OF THE FOLLOWING:
A. IN EXISTING BUILDINGS, THE CEILING HEIGHT SHALL NOT BE LESS THAN 7 FT FROM THE FLOOR, WITH PROJECTIONS FROM THE CEILING
NOT LESS THAN 6 FT 8 IN NOMINAL ABOVE THE FLOOR.
7. (7.2.1.2.3.2) DOOR OPENINGS IN MEANS OF EGRESS SHALL NOT BE LESS THAN 32 IN. IN CLEAR WIDTH.
8. (7.2.1.4.3.2) WHEN FULLY OPEN, ANY DOOR LEAF IN A MEANS OF EGRESS SHALL NOT PROJECT MORE THAN 7 IN. INTO THE REQUIRED WIDTH OF AN AISLE, A CORRIDOR, A PASSAGEWAY OR A LANDING, UNLESS THE DOOR LEAF IS EQUIPPED WITH AN APPROVED SELF-CLOSING DEVICE AND IS NOT REQUIRED BY THE PROVISIONS OF 7.2.1.4.2 TO SWING IN THE DIRECTION OF EGRESS TRAVEL..
E. FIRE PROTECTION EQUIPMENT - CHAPTER 19 AND CHAPTER 9
1. THE EXISTING BUILDING IS FULLY PROTECTED WITH AN AUTOMATIC SPRINKLER SYSTEM.
TYPE C
HIGH RISK
CLASS IV
1/16" = 1'-0"1 INTERIM LIFE SAFETY PLAN
PROJECT PHASING NOTES
1. DURING THE EXECUTION OF THIS CONTRACT, THE PROJECT AREA WILL BE OCCUPIED AND IN USE. WORK DONE UNDER THIS CONTRACT SHALL BE PERFORMED WITHOUT INCONVENIENCE TO THE OWNER, STAFF, OR OTHER BUILDING OCCUPANTS. ALL WORK SHALL BE COORDINATED WITH THE
CONTRACTING OFFICER'S REPRESENTATIVE AND IS SUBJECT TO HIS CONTINUOUS APPROVAL.
2. "NORMAL" WORKING HOURS ON THE POST ARE FROM 8:00 AM TO 4:30 PM, MONDAY THROUGH FRIDAY; HOURS OUTSIDE OF "NORMAL" WORKING HOURS ARE DEFINED AS "OFF HOURS". THE CONTRACTOR SHALL DEVELOP A SCHEDULE OF DEMOLITION, NEW INSTALLATION, AND CHANGEOVER OF THE
MECHANICAL, PLUMBING, AND UTILITY SYSTEMS THAT WILL ALLOW FOR MINIMUM DOWNTIME.
3. THE CONTRACTOR SHALL DEVELOP AND PRESENT A CONSTRUCTION PLAN AND WORK SCHEDULE WITH ALL PHASING, STAGING, AND SEQUENCING OF WORK FOR APPROVAL PRIOR TO THE COMMENCEMENT AND BEGINNING IMPLEMENTATION OF HIS WORK. THE CONTRACTOR SHALL DETERMINE PRIOR TO SUBMITTING HIS WORK SCHEDULE, THE SPECIFIC TIME AVAILABILITY OF ALL AREAS AND SPACES AND DETERMINE WHAT WORK MUST BE DONE
DURING "OFF HOURS".
4. ALL WORK IN OCCUPIED SPACES SHALL BE DONE DURING "OFF HOURS". ALL WORK AS REQUIRED TO RETURN EXISTING SYSTEMS TO FUNCTIONALITY, REPLACE CEILING TILES, AND CONSTRUCTION CLEANUP SHALL BE FULLY COMPLETE AND APPROVED BY THE COR PRIOR TO THE END-OF-SHIFT AND
BEFORE THE OPENING OF THE AREA TO STAFF AND OTHER BUILDING OCCUPANTS.
5. WITH THE EXCEPTION OF SIGNIFICANT NOISE GENERATING ACTIVITIES SUCH AS CORE DRILLING, ETC., WORK OUTSIDE OF THE OCCUPIED SPACES, SUCH AS ON THE ROOF, ETC., MAY BE PERFORMED DURING NORMAL WORKING HOURS.
6. EACH ROOM WITHIN THE PROJECT AREA SHALL BE ISOLATED AS A SINGLE PHASE OF THE PROJECT. THE SEQUENCING OF PHASES SHALL BE DETERMINED BY THE COR BASED ON OCCUPANCY AT THE TIME OF CONSTRUCTION. DURING CONSTRUCTION OF EACH PHASE, THE CONTRACTOR SHALL FOLLOW THE INFECTION CONTROL MEASURES INDICATED ON THIS SHEET FOR CLASS III RENOVATION WORK.
CONTROLS SYMBOLS
MOTOR STARTER
T ROOM THERMOSTAT/TRANSMITTER - WALL MOUNT
TT TEMPERATURE TRANSMITTER
HS HAND SWITCH (HAND-OFF-AUTO SWITCH)
H4
H7
A
DRAWING SYMBOLS
26-SF-3
DETAIL NUMBER
DRAWING NUMBER WHERE SHOWN
SECTION LETTER
TYPICAL UNIT NO.
BUILDING NO. WHERE EQUIPMENT IS LOCATED.
SUPPLY FAN NO. 3 IN BUILDING NO. 26
EQUIPMENT ABBREVIATION (SUPPLY FAN)
DRAWING NUMBER WHERE DRAWN
TERMINAL UNIT SYMBOLS
FLOOR MOUNTED VERTICAL CABINET FAN COIL UNIT. LETTER OR
NUMBER INDICATES UNIT SIZE.
FCU
A
GATE VALVE WITH GLOBE-VALVED BYPASS
PLUG VALVE
CONTROL VALVE (CV) - FLOAT-OPERATED
PRESSURE REDUCING VALVE (PRV)
WYE STRAINER WITH VALVED DRAIN AND QUICK-COUPLE HOSE
CONNECTOR
WATER LEVEL CONTROLLER
FLOW METER
LC
M
VALVE SYMBOLS
BALL VALVE
GATE VALVE WITH 3/4" HOSE ADAPTER
CHECK VALVE
ANGLE GLOBE VALVE
BUTTERFLY VALVE
MODULATING CONTROL VALVE
TWO POSITION CONTROL VALVE
THREE-WAY MODULATING CONTROL VALVE
AUTOMATIC BALANCING CONTROL VALVE
PRESSURE SAFETY VALVE
GATE VALVE - THREADED/FLANGED
GLOBE VALVE - THREADED/FLANGED
PRESSURE REGULATING VALVE
THREE-WAY TWO POSITION CONTROL VALVE
WYE STRAINER (WITH BALL VALVE & HOSE CONNECTION)
FLEXIBLE CONNECTION
WATER BALANCE DEVICE
MODULATING CONTROL BUTTERFLY VALVE
CIRCUIT SETTER VALVE
QUICK-COUPLE HOSE CONNECTOR
GENERAL PIPING SYMBOLS
ANCHOR
REDUCER OR INCREASER
DIRECTION OF FLOW
SIDE CONNECTION
ECCENTRIC REDUCER
BOTTOM CONNECTION, 45° OR 90°
TOP CONNECTION, 45° OR 90°
DIRECTION OF PIPE PITCH (DOWN)
UNION
RISE OR DROP IN PIPE
CAPPED OUTLET
PRESSURE GAGE
THERMOMETER
FLOW ELEMENT
FLOAT & THERMOSTATIC TRAP SET INCLUDING PIPING ACCESSORIES
SEE DETAIL
INVERTED BUCKET TRAP SET INCLUDING PIPING ACCESSORIES SEE
DETAIL
PIPE UP
PIPE DOWN
REFRIGERANT SIGHT GLASS
TEST PLUG (PRESSURE/TEMPERATURE)
AUTOMATIC AIR VENT
AV
MANUAL AIR VENTMV
THERMOSTATIC TRAP SET INCLUDING PIPING ACCESSORIES SEE
DETAIL
FE
CHILLED WATER SUPPLY
CHILLED WATER RETURN
HOT WATER RETURN
HOT WATER SUPPLY
CHR
CHS
HWR
HWS
CONDENSATE DRAIND
PC TERMINAL UNIT CONTROLLER
SC SPEED CONTROLLER
YR YEAR
W WATTS
Wb WET-BULB (TEMPERATURE)
V VALVE
VAF VANE-AXIAL FAN
VAV VARIABLE AIR VOLUME
VD VOLUME DAMPER (MAN. OPPOSED BLADE)
VFD VARIABLE FREQUENCY DRIVE
VI VIBRATION ISOLATOR
UL UNDERWRITERS LABORATORY
D DAMPER - AUTOMATIC
DB DECIBELS
Db DRY-BULB TEMPERATURE
DD-1 DESIGN DEVELOPMENT (SUBMISSION1)
DD-2 DESIGN DEVELOPMENT (SUBMISSION2)
DDC DIRECT DIGITAL CONTROLS
DEG DEGREE
DHW DOMESTIC HOT WATER
DHWR DOMESTIC HOT WATER RETURN
DIA DIAMETER
CD-2 CONSTRUCTION
DOCUMENTS (SUBMISSION2)
CFH CUBIC FEET PER HOUR
CFM CUBIC FEET PER MINUTE
CFT CUBIC FEET
CHP CHILLED WATER PUMP
CHW CHILLER WATER
CHR CHILLED WATER RETURN
CHS CHILLED WATER SUPPLY
CO CLEAN OUT
CO2 CARBON DIOXODE
COMP COMPRESSOR UNIT
COP COEFFICIENT OF PERFORMANCE
CR CEILING REGISTER
CS CONDENSATE STORAGE TANK
CSG CLEAN STEAM GENERATOR
CT COOLING TOWER
CU CONDENSING UNIT
CUH CABINET UNIT HEATER
CV CONSTANT VOLUME
CW COLD WATER (POTABLE)
CWCC CHILLED WATER COOLING
COIL
CWP CONDENSER WATER PUMP
CWR CONDENSER WATER RETURN (TO
COOLING TOWER)
CWS CONDENSER WATER SUPPLY
(FROM COOLING TOWER)
BTC BLOWOFF TANK CONTROL VALVE
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNIT PER HOUR
A/E ARCHITECT / ENGINEER
AD ACCESS DOOR
AFF ABOVE FINISHED FLOOR
AHU AIR-HANDLING UNIT
AMP AMPERGE
AP ACCESS PANEL
APD AIR PRESSURE DROP
ARI AIR CONDITIONING AND
REFRIGERATION INSTITUTE
AS AIR SEPARATOR
ASME AMERICAN SOCIETY OF
MECHANICAL ENGINEERS
AW AIR WASHER
AXF AXIAL FLOW
CAV CONSTANT AIR VOLUME
CC COOLING COIL
CCD COOLING COIL CONDENSATE
DRAIN
CD-1 CONSTRUCTION
DOCUMENTS (SUBMISSION1)
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE
ECC ENGINEERING CONTROL CENTER
ENT ENTERING
ESP EXTERNAL STATIC PRESSURE
EWT ENTERING WATER TEMPERATURE
EX EXISTING
F FAHRENHEIT
FCU FAN COIL UNIT (4 PIPE)
FAN COIL UNIT HEATING ONLY
FCW FORWARD CURVED WHEEL (FAN)
FD FIRE DAMPER
FPM FEET PER MINUTE
FPS FEET PER SECOND
FPTU FAN POWERED TERMINAL UNIT
FR FLOOR REGISTER
FRP FIBER REINFORCED POLYESTER
FS FLOW SWITCH
FREEZESTAT
GA GAUGE
GAL GALLONS
GPD GALLONS PER DAY
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
HAC HOUSEKEEPING AID CLOSET
HC HEATING COIL
HP HORSEPOWER
HW HOT WATER
HWC HOT WATER COIL
HWHC HOT WATER HEATING COIL
HWP HEATING HOT WATER PUMP
HWR HEATING HOT WATER RETURN
HWS HEATING HOT WATER SUPPLY
HWUH HOT WATER UNIT HEATER
HVD HOISTWAY VENT DAMPER
HX HEAT EXCHANGER
HZ HERTZ
FT FEET
FT WC FEET OF WATER COLUMN
OD OUTSIDE DIAMETER
NA NOT APPLICABLE
NC NOISE CRITERIA
NC NORMALLY CLOSED
NO NORMALLY OPEN
NOM NOMINAL
NTS NOT TO SCALE
MAU MAKE-UP AIR UNIT
MAV MANUAL AIR VENT
MAX MAXIMUM
MB MIXING BOX
MBH 1000 BTUH
MCA MINIMUM BRANCH CIRCUIT AMPACITY
MER MECHANICAL EQUIPMENT ROOM
MERV MINIMUM EFFICIENCY REPORTING
VALUE
MHP MOTOR HORSEPOWER
MIN MINIMUM
MOV MOTOR OPERATED VALVE
LAT LEAVING AIR TEMPERATURE
LBS/HR POUNDS PER HOUR
LF LINEAR FOOT (FEET)
LVG LEAVING
LWT LEAVING WATER TEMPERATURE
kW KILOWATT kWh KILOWATT HOUR
J INTENTIALLY LEFT BLANK
I/O INPUT/OUTPUT
ID INSIDE DIAMETER
IN INCHES
IN HG INCHES OF MERCURY
IN WC INCH WATER COLUMN
IN WG INCH WATER GAUGE
IN-LB INCH-POUND
TAB TESTING, ADJUSTING, BALANCE
TD TEMPERATURE DIFFERENCE
TSP TOTAL STATIC PRESSURE
TSTAT THERMOSTAT
TU TERMINAL UNIT
SA SUPPLY AIR
SAT SUPPLY AIR TEMPERATURE
SD SMOKE DETECTOR
SD-1 SCHEMATIC DESIGN (SUBMISSION1)
SD-2 SCHEMATIC DESIGN (SUBMISSION2)
SEN SENSIBLE HEAT
SF SUPPLY FAN
SI SQUARE INCHES
SP STATIC PRESSURE
SQ FT SQUARE FOOT (FEET)
SS STAINLESS STEEL
R/E RETURN OR EXHAUST
RA RETURN AIR
RAT RETURN AIR TEMPERATURE
RDS ROOM DATA SHEETS
RH RELATIVE HUMIDITY
RHC REHEAT COIL
RHG REFRIGERANT HOT GAS
RL REFRIGERANT LIQUID LINE
RLA RUN LOAD AMPERE
RPM REVOLUTIONS PER MINUTE
RV RELIEF VALVE
P PUMP
PD PRESSURE DROP
PG PRESSURE GAGE
PSI POUNDS PER SQUARE INCH
PSIA POUNDS PER SQUARE INCH – ABSOLUTE
PSIG POUNDS PER SQUARE INCH – GAGE
FCUH
FSTAT
ASHRAE AMERICAN SOCIETY OF HEATING
REFRIGERATION AIR
CODE REQUIRED MECHANICAL PIPE SIZING AND INSULATION
PIPE
SIZE
MAX FLOW
(GPM)
MINIMUM PIPE INSULATION THICKNESS (IN)
TEMP RANGE (F) / CONDUCTIVITY (BTU-IN/HR-SQFT-F)
105F - 140F 141F - 200F 201F - 250F 251F - 350F > 350F 40F - 60F < 40F NOTES
0.22 - 0.28 0.25 - 0.29 0.27 - 0.3 0.29 - 0.32 0.32 - 0.34 0.21 - 0.27 0.2 - 0.26 1-4
0.50 1.5 1 1.5 2.5 3 4.5 0.5 0.5 1-4
0.75 3 1 1.5 2.5 3 4.5 0.5 0.5 1-4
1.00 5.5 1 1.5 2.5 4 5 0.5 1 1-4
1.25 12 1 1.5 2.5 4 5 0.5 1 1-4
1.50 18 1.5 2 2.5 4.5 5 1 1 1-4
2.00 35 1.5 2 2.5 4.5 5 1 1 1-4
2.50 55 1.5 2 2.5 4.5 5 1 1 1-4
3.00 100 1.5 2 2.5 4.5 5 1 1 1-4
4.00 202 1.5 2 3 4.5 5 1 1 1-4
5.00 250 1.5 2 3 4.5 5 1 1 1-4
6.00 440 1.5 2 3 4.5 5 1 1 1-4
8.00 700 1.5 2 3 4.5 5 1 1.5 1-4
10.00 1000 1.5 2 3 4.5 5 1 1.5 1-4
12.00 1500 1.5 2 3 4.5 5 1 1.5 1-4
14-24 MAX VEL
5 FT/S 1.5 2 3 4.5 5 1 1.5 1-4
1. ADAPTED FROM ASHAE 90.1, TABLES 6.5.4.6, 6.8.3-1 AND 6.8.3-2
2. MAX FLOW RATES APPLY TO HYDRONIC PIPING ONLY
3. PIPING INSULATION THICKNESS APPLIES TO STEAM, STEAM CONDENSATE, HOT WATER HEATING, DOMESTIC HOT WATER, CHILLED WATER, BRINE, AND REFRIGERANT PIPING AT RESPECTIVE TEMP RANGES
4. SEE SPECIFICATIONS FOR FURTHER DETAILS ON PIPE MATERIALS, INSULATION MATERIALS, ETC.
105063
ST
ATE
OF NEW YORK
MA
T TH
EW LLOYD
LICENSED PROFESSIONAL
EN
GI
NE
ER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTSOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Watson Engineering, P.C.
1112 State Rte. 434 Owego, NY 13827 (607)223-4334
REPLACE FAN COIL UNITS
CASTLE POINT VAMC, WAPPINGERS FALLS, NEW YORK
620A4-19-203
15H
08/25/2023 MPL AMR
10/5/2022
BI
M
VA
-2
R ep la ce
F an
C oi l U ni ts /R ep la ce F an C oi l U ni ts
.rv t
4/ 4/
:4
8:
P M
M-001
MECHANICAL NOTES,
ABBREVIATIONS, AND SYMBOLS
GENERAL MECHANICAL NOTES:
1. THE GENERAL MECHANICAL NOTES ON THIS SHEET APPLY TO ALL THE MECHANICAL DRAWINGS.
2. IT IS THE MECHANICAL CONTRACTOR'S RESPONSIBILITY TO FIELD VERIFY ALL ASPECTS OF THE DESIGN, TO
INCLUDE THE WORK OF SUB-TRADES, PRIOR TO SUBMITTING A BID.
3. THE MECHANICAL DRAWINGS SHALL BE FOLLOWED AS CLOSELY AS POSSIBLE, ALTHOUGH NO ATTEMPT WAS
MADE TO SHOW EVERY OFFSET, FITTING, BEAM, PIPE SUPPORT, CLEARANCE, ETC. IT IS THE MECHANICAL CONTRACTOR’S RESPONSIBILITY TO SURVEY ALL WORK AREAS AND SUBMIT FINAL, DETAILED COORDINATED SHOP DRAWINGS FOR REVIEW BY THE DESIGNER OF RECORD TO ENSURE THAT THE DESIGN INTENT WILL BE MET AND THAT ALL TRADES ARE PROPERLY COORDINATED. CHANGES REQUIRED TO FIT EQUIPMENT, PIPING, AND DUCTWORK SHALL BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER. ANY MAJOR DISCREPANCIES
SHALL BE CLARIFIED PRIOR TO SUBMITTAL OF BID.
4. BECAUSE OF THE SMALL SCALE OF THE DRAWINGS, IT IS NOT POSSIBLE TO INDICATE ALL OFFSETS, TRANSITIONS, FITTINGS, CLEARANCES, POSSIBLES CLASHES, AND ACCESSORIES THAT MAY BE REQUIRED.
COORDINATE ALL THE WORK OF ALL THE TRADES TO ENSURE ALL DUCTS, PIPES, CONDUITS, ETC. DO NOT CONFLICT AND CLEAR STRUCTURAL AND ARCHITECTURAL MEMBERS. THE MECHANICAL CONTRACTOR IS RESPONSIBLE FOR DEVELOPING COORDINATED SHOP DRAWINGS FOR REVIEW PRIOR TO STARTING
INSTALLATION.
5. THE MECHANICAL CONTRACTOR SHALL VISIT THE SITE AND BE FULLY COGNIZANT OF ALL CONDITIONS PRIOR TO SUBMITTING BID. REPORT ANY DISCREPANCIES TO THE ENGINEER PRIOR TO SUBMITTAL OF BID.
6. IF A JOB REQUIRES TYING INTO ANY EXISTING MECHANICAL SYSTEM, THE MECHANICAL CONTRACTOR SHALL CONDUCT NECESSARY PRE TEST, ADJUST, AND BALANCING (TAB) ACTIVITIES TO VERIFY BASELINE SOURCE CAPACITY FROM THE FACILITY, UNLESS THE OWNER CAN PROVIDE SUFFICIENT FACILITY MECHANICAL TREND LOGS TO ESTABLISH THAT SUFFICIENT SOURCE CAPACITY EXISTS. UPON DETERMINING INSUFFICIENT SOURCE CAPACITY, THE MECHANICAL CONTRACTOR SHALL IMMEDIATELY REPORT FINDINGS TO THE OWNER
AND ENGINEER FOR RECORD FOR ADDITIONAL GUIDANCE BEFORE PROCEEDING.
7. THE WORK INCLUDES ALL ITEMS OF THE MECHANICAL SPECIFICATIONS THAT ARE EITHER WRITTEN ON THE
DRAWINGS OR SEPARATELY IN A SPECIFICATIONS BOOK.
8. WHERE THERE IS A CONFLICT ON THE PLANS, SPECIFICATIONS, NOTES, GENERAL NOTES, REFERENCES, PUBLICATIONS, CODES, ETC. WITH RESPECT TO CONSTRUCTION, MATERIALS, PRODUCTS, METHODS, WORKMANSHIP, PROCEDURE, EXECUTION, ETC. THE MOST STRINGENT SHALL BE UTILIZED OR INSTALLED. THE MOST STRINGENT SHALL BE DEFINED AS THE SPECIFICATION OR REQUIREMENT THAT ALLOWS ALL SPECIFICATIONS OR REQUIREMENTS THAT ARE IN CONFLICT TO BE SATISFIED. NO RELIEF OR EXTRA PAYMENT
SHALL BE MADE TO THE CONTRACTOR BECAUSE OF THIS INTERPRETATION.
9. THE MECHANICAL CONTRACTOR SHALL NOT BEGIN FABRICATION, CUT ANY MEMBERS, OR BEGIN INSTALLATION
UNTIL THE SUBMITTALS AND COORDINATED SHOP DRAWINGS HAVE BEEN APPROVED. ANY WORK
CONSTRUCTED OR INSTALLED PRIOR TO THE APPROVAL OF SUBMITTALS AND COORDINATED SHOP DRAWINGS SHALL BE AT THE MECHANICAL CONTRACTOR'S RISK AND SHALL BE REMOVED AND REINSTALLED OR RECONSTRUCTED AT THE MECHANICAL CONTRACTOR'S EXPENSE AT THE REQUEST OF THE OWNER'S
REPRESENTATIVE TO THE COMPLETE SATISFACTION OF THE OWNER'S REPRESENTATIVE.
10. ALL WORK SHALL BE DONE WITH COMPLETE COMPLIANCE WITH THE PUBLISHED EDITIONS OF THE APPLICABLE CODES AND STANDARDS WHETHER STATUTORY OR NOT. ALL WORK SHALL BE INSTALLED TO COMPLY WITH THE INTERNATIONAL BUILDING MECHANICAL CODE, UNDERWRITER'S LABORATORY, INC., AMERICAN NATIONAL STANDARD INSTITUTE, INC. IF ANY PART OF THE INSTALLATION DOES NOT MEET CODE, NOTIFY THE OWNER'S REPRESENTATIVE PRIOR TO BEGINNING THE INSTALLATION. IF ANY PART OF THE PROJECT CANNOT BE INSTALLED TO CONFORM WITH THE PLANS AND/OR SPECIFICATIONS, NOTIFY THE OWNER'S REPRESENTATIVE
PRIOR TO BEGINNING THE INSTALLATION.
11. UNLESS STATED OTHERWISE, ALL EXISTING MATERIAL AND EQUIPMENT SHALL REMAIN THE PROPERTY OF THE
PROJECT OWNER.
12. THE MECHANICAL CONTRACTOR SHALL DEVELOP AND PRESENT A CONSTRUCTION PLAN AND WORK SCHEDULE WITH ALL PHASING, STAGING, AND SEQUENCING OF WORK FOR APPROVAL PRIOR TO THE COMMENCEMENT AND BEGINNING IMPLEMENTATION OF HIS WORK. THE MECHANICAL CONTRACTOR SHALL DETERMINE PRIOR TO SUBMITTING HIS WORK SCHEDULE, THE SPECIFIC TIME AVAILABILITY OF ALL AREAS AND
SPACES AND DETERMINE WHAT WORK MUST BE DONE DURING "OFF HOURS".
13. WITH THE EXCEPTION OF SIGNIFICANT NOISE GENERATING ACTIVITIES SUCH AS CORE DRILLING, ETC., WORK OUTSIDE OF THE OCCUPIED SPACES, SUCH AS ON THE ROOF, ETC., MAY BE PERFORMED DURING NORMAL
WORKING HOURS.
14. UNLESS SPECIFICALLY NOTED AS EXISTING, ALL ITEMS, EQUIPMENT, AND WORK SHOWN IS NEW AND SHALL BE
FURNISHED AND INSTALLED BY THE MECHANICAL CONTRACTOR.
15. DURING THE EXECUTION OF THIS CONTRACT, THE SITE AND BUILDINGS WILL BE OCCUPIED AND IN USE. WORK DONE UNDER THIS CONTRACT SHALL BE PERFORMED WITHOUT INCONVENIENCE TO THE OWNER INSOFAR AS POSSIBLE. ALL WORK SHALL BE COORDINATED WITH THE OWNER'S REPRESENTATIVE AND IS SUBJECT TO
THEIR CONTINUOUS APPROVAL.
16. THE MECHANICAL CONTRACTOR IS COMPLETELY RESPONSIBLE FOR ALL CHARACTERISTICS OF THE EQUIPMENT THAT HE INTENDS TO INSTALL AND MUST FOLLOW MANUFACTURER RECOMMENDATIONS FOR PROPER INSTALLATION. IF THERE ARE ANY DIFFERENCES IN THE EQUIPMENT SHOWN ON THE DESIGN DRAWINGS AND THE EQUIPMENT TO BE INSTALLED, THE MECHANICAL CONTRACTOR SHALL MAKE ALL CHANGES AND ADJUSTMENTS TO ACCOMMODATE THE PROPOSED EQUIPMENT AT NO ADDITIONAL COST TO THE OWNER. THIS APPLIES TO ALL SUPPORT SERVICES AND FACILITIES NECESSARY TO PROPERLY INSTALL THE EQUIPMENT TO FUNCTION ADEQUATELY AS PART OF THE SYSTEMS FOR WHICH THEY WERE DESIGNED AND SELECTED. THESE CHARACTERISTICS INCLUDE SUCH THINGS AS WEIGHT, CLEARANCE, DIMENSIONS, ELECTRICAL, MECHANICAL, PLUMBING, AND UTILITY SERVICES, ETC. ACCOMMODATING SERVICES INCLUDE SUCH THINGS AS DIMENSIONS, LOCATIONS, AND SIZES OF SUPPORTING MEMBERS, PIPE, CONNECTION SIZES, ELECTRICAL SERVICE SIZE AND PROTECTION, ELECTRICAL CONNECTION LOCATION, UTILITY AND PLUMBING CONNECTION SIZES AND LOCATIONS, ETC. ALL REQUIRED CHANGES TO THE CONTRACT DRAWINGS AND SPECIFICATIONS SHALL BE DESIGNED AND STAMPED BY REGISTERED ENGINEERS IN THE APPROPRIATE DISCIPLINE EMPLOYED BY THE MECHANICAL CONTRACTOR AND SHALL BE INCLUDED AS PART OF THE EQUIPMENT SUBMITTALS. ALL CHANGES SHALL BE SUBJECT TO THE APPROVAL OF THE PROJECT A/E AND THE
OWNER'S REPRESENTATIVE.
17. BEFORE ANY DEMOLITION OR CONSTRUCTION WORK IS BEGUN, THE MECHANICAL CONTRACTOR AND THE OWNER'S REPRESENTATIVE SHALL SURVEY THE EXISTING BUILDING AREA TO BE MODIFIED AND/OR REPLACED TO ACCURATELY DOCUMENT EXISTING CONDITIONS. THIS SURVEY WILL BE USED BY THE OWNER'S REPRESENTATIVE AT JOB COMPLETION TO DETERMINE WHICH BUILDING/SITE COMPONENTS MUST BE
REPLACED WITH NEW.
18. UNLESS STATED OTHERWISE, REQUEST APPROVAL FROM THE OWNER'S REPRESENTATIVE SEVEN DAYS IN
ADVANCE FOR THE SHUTDOWN OF ANY EXISTING SYSTEM.
19. UNLESS STATED OTHERWISE, FINAL ADVANCE NOTICE OF 48 HOURS SHALL BE GIVEN TO THE OWNER'S
REPRESENTATIVE PRIOR TO THE PROPOSED SHUTDOWN OF ANY SYSTEM.
20. THE CLOSING AND OPENING OF VALVES SHALL BE WITNESSED BY THE OWNER'S REPRESENTATIVE; NOTIFY
LOCAL AUTHORITIES AS REQUIRED.
21. PROVIDE ADEQUATE FIRE PROTECTION IN THE ENTIRE CONSTRUCTION AREA FOR THE DURATION OF THE
CONSTRUCTION PERIOD. COORDINATE WITH INSTALLING FIRE PROTECTION CONTRACTOR.
22. THE ENTIRE EXISTING FIRE PROTECTION SYSTEM SHALL BE RESTORED TO FULL OPERATION AT THE END OF EACH WORKING DAY. ALL EXISTING FIRE ALARMS AND FIRE EXITS AND ANY OTHER ASPECT OF THE EXISTING FIRE ALARM SYSTEM SHALL REMAIN IN FULL OPERATION. THE COST OF RESPONSE TO ANY FALSE ALARM AS
CHARGED BY ANY LOCAL FIRE DEPARTMENT SHALL BE PAID BY THE MECHANICAL CONTRACTOR.
23. MECHANICAL CONTRACTOR SHALL NOT PENETRATE OR CUT ANY STRUCTURAL MEMBERS NOT SPECIFICALLY SHOWN ON THE DRAWINGS (E.G., JOISTS, BEAMS, ETC.). IF STRUCTURAL MEMBERS CONFLICT WITH ROUTING, CONTACT THE OWNER'S REPRESENTATIVE FOR DIRECTION BEFORE PROCEEDING. EXERCISE CAUTION IN CUTTING CONCRETE FLOORS AND WALLS TO AVOID EXISTING UTILITIES WHICH MAY BE LOCATED IN AND
UNDER CONCRETE SURFACES.
24. THE MECHANICAL CONTRACTOR SHALL PROVIDE NEW OPENINGS IN WALLS, FLOOR, AND ROOF, AND PATCH EXISTING OPENINGS IN CONJUNCTION WITH THE DEMOLITION AND INSTALLATION OF THE NEW BUILDING
COMPONENTS. ALL NECESSARY FRAMING, COUNTER-FLASHING, ETC. SHALL BE INCLUDED.
25. FOR ALL FLOOR, WALL, AND ROOF PENETRATION, VERIFY THE LOCATION OF THE EXISTING STRUCTURAL MEMBERS PRIOR TO DRILLING AND CUTTING, RELOCATE OPENINGS AS REQUIRED AND OFFSET DUCTS, PIPES, CONDUIT, ETC.
26. ALL EXISTING DUCTWORK, PIPING, CONDUIT, AND MECHANICAL EQUIPMENT NOT TO BE REUSED OR REMAIN IN SERVICE SHALL BE REMOVED FROM THE FACILITY. THE OWNER'S REPRESENTATIVE HAS THE OPTION TO RECLAIM ANY DEMOLISHED MATERIALS OR EQUIPMENT, IN WHICH CASE IT SHALL BE DELIVERED TO THE
LOCATION DESIGNATED BY THE OWNER'S REPRESENTATIVE.
27. FOR EACH PHASE AND BEFORE INTERRUPTING EACH EXISTING UTILITY, DETERMINE, IN ADVANCE, IF ANY DOWNSTREAM SERVICE BEYOND THE CONSTRUCTION AREA OF THE PHASE, WILL BE INTERRUPTED AND PROVIDE A TEMPORARY SERVICE BYPASSING THE CONSTRUCTION AREA. DETERMINE ALL SUCH TEMPORARY SERVICES PRIOR TO SUBMITTING BID. THERE WILL BE NO FUTURE CONSIDERATION TO THE MECHANICAL CONTRACTOR FOR ANY TEMPORARY SERVICES REQUIRED. PREPARE A DETAILED SHOP DRAWING SHOWING ALL OF THE EXISTING UTILITIES IN THEIR RELOCATED LOCATION AND ALL THE NEW HVAC SYSTEMS.
28. THE FLOOR AREAS BELOW OVERHEAD WORK, WHERE WELDING "HOT WORK" IS TO BE PERFORMED, SHALL BE CLEARED TO A MINIMUM DISTANCE OF 36 FEET BEYOND THE POINT DIRECTLY BELOW THE OVERHEAD "HOT WORK". ALL FLAMMABLE MATERIALS SHALL BE CLEARED TO A DISTANCE 50 FEET BEYOND THE POINT
DIRECTLY BELOW THE OVERHEAD "HOT WORK".
29. EXISTING DUCTWORK, DOMESTIC COLD WATER PIPING, DOMESTIC HOT WATER PIPING, CHILLED AND HEATING HOT WATER PIPING, WASTE, VENT, FIRE SPRINKLER LINES, FIRE ALARM EQUIPMENT, ELECTRICAL CONDUIT, TELEPHONE CONDUIT, COMMUNICATION CONDUIT, PNEUMATIC TUBING, ETC., MAY HAVE TO BE RELOCATED TO FACILITATE THE INSTALLATION OF THE NEW WORK. THE CONTRACTOR SHALL DETERMINE ALL EXISTING SERVICES THAT REQUIRE RELOCATION PRIOR TO SUBMITTING HIS BID AND INCLUDE ALL COSTS IN THE BID.
THERE WILL BE NO EXTRA COMPENSATION TO THE CONTRACTOR FOR THIS WORK.
30. THE CONTRACTOR IS HEREBY NOTIFIED THAT SOME WORK MAY BE REQUIRED OUTSIDE OF THE AREAS SHOWN ON THESE DRAWINGS. THIS COULD INCLUDE ELECTRICAL WORK, REFRIGERANT LINE ROUTING, CONTROL MODIFICATIONS OR CONNECTIONS AT REMOTE LOCATIONS, CONTROL PANELS, CPU'S, ETC.
31. THE CONTRACTOR SHALL PAY FOR ALL DAMAGE, INCLUDING WATER DAMAGE, TO PROPERTY AND EQUIPMENT
CAUSED BY HIS WORK THROUGHOUT THE CONSTRUCTION AND WARRANTEE PERIOD.
32. ALL CEILING DEMOLITION WORK SHALL BE DONE AFTER NORMAL WORKING HOURS. THE INSTALLATION OF THE NEW CEILING SHALL BE DONE AFTER NORMAL WORKING HOURS. THE WORK AREA SHALL BE CLEANED
BEFORE THE START OF EACH WORKING DAY.
33. REMOVE T-BARS AND 2X4 CEILING PANELS AS REQUIRED FOR THE DEMOLITION AND THE INSTALLATION OF THE NEW WORK. REINSTALL EXISTING OR REPLACE WITH NEW AS REQUIRED TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE. FOR ANY HARD CEILING AREA, CUT AND DEMOLISH ENOUGH OF THE HARD CEILING TO DO THE WORK REQUIRED. REBUILD AND PATCH THE DEMOLISHED. FINISH AND PAINT TO MATCH
EXISTING TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE.
34. ANY DEVICE THAT REQUIRES ACCESS FOR ADJUSTMENT OR ROUTINE MAINTENENANCE, SUCH AS BUT NOT LIMITED TO VALVES, VOLUME DAMPERS, CONTROL DEVICES, VAVS, ETC. SHALL BE INSTALLED IN AN
ACCESSIBLE LOCATION.
35. PATCH AND PAINT TO MATCH EXISTING, ALL SURFACES DAMAGED BY THE DEMOLITION AND ALL
OPENINGS NOT TO BE REUSED.
36. REPAIR DAMAGE TO CEILING, WALLS, ETC. TO THE SATISFACTION OF THE OWNER'S
REPRESENTATIVE.
37. WHEN A DETAIL OR NOTE IS IDENTIFIED AS TYPICAL, THE MECHANICAL CONTRACTOR IS TO APPLY
THE DETAIL OR NOTE TO EVERY SIMILAR CONDITION, WHETHER OR NOT THE REFERENCED
DETAIL OR NOTE IS REPEATED OR REFERENCED.
38. WHERE NO CONSTRUCTION DETAIL IS INDICATED, SUCH WORK SHALL BE SIMILAR TO
COMPARABLE WORK DETAILED OR NOTED ELSEWHERE OR TO MATCH EXISTING CONDITIONS,
SUBJECT TO THE APPROVAL OF THE OWNER'S REPRESENTATIVE.
39. ALL HOLES, VOIDS, AND DAMAGED OR UNEVEN SURFACES WHICH ARE CAUSED BY THE
MECHANICAL CONTRACTOR'S WORK AND WHICH REMAIN EXPOSED IN THE WALL, FLOOR,
CEILING, OR OTHER SURFACES SHALL BE PATCHED, REPAIRED, AND BROUGHT FLUSH WITH THE
ADJACENT CONSTRUCTION. SUCH SURFACES, NOT CONCEALED BY THE NEW CONSTRUCTION,
SHALL MATCH IN EVERY RESPECT THE EXISTING NON-DAMAGED CONSTRUCTION. REMOVE
EXISTING UTILITIES BACK BEHIND EXISTING SURFACES AND CAP SO AS NOT TO INTERFERE WITH
NEW PATCHES.
40. WHEREVER NEW WALL, FLOOR, OR CEILING FINISHES ARE INDICATED, THE MECHANICAL
CONTRACTOR SHALL BRING EXISTING MECHANICAL COMPONENTS FLUSH WITH THE NEW
FINISHED SURFACES IF APPROPRIATE.
41. THE DEMOLITION SHALL INCLUDE ALL ASSOCIATED ANCHORAGES, HANGERS, SUPPORTS,
BRACES, FASTENERS, MASTIC, MORTAR, LATH, AND RELATED ITEMS. THE EXISTING SUBSTRATE, INCLUDING CONCRETE, MASONRY, METAL FRAMING AND FURRING SHALL BE REPAIRED WHERE
DAMAGE BY THE CONTRACTOR'S WORK.
42. PROVIDE ALL VALVES, INSTRUMENTS, FITTINGS, ETC. AS SHOWN ON THE PIPING DIAGRAMS, SCHEMATICS, ETC. IT IS NOT POSSIBLE TO SHOW ALL VALVES, INSTRUMENTS, ETC. ON THE
PLANS, HOWEVER, SELECTED VALVES HAVE BEEN SHOWN FOR REFERENCE. ALL VALVES SHALL
BE ACCESSIBLE FROM THE FLOOR OR FROM FIXED PLATFORMS.
43. ALL EQUIPMENT AND MATERIALS SUBJECT TO THE WEATHER THAT ARE NOT FACTORY PAINTED SHALL BE FIELD PAINTED AND WEATHER PROOFED WITH PRIMER, AND TWO COATS OF EXTERIOR PAINT. MATCH THE COLOR OF THE EXISTING BUILDING EXTERIOR. THE COLOR AND QUANTITY OF
THE PAINT IS SUBJECT TO THE APPROVAL OF THE OWNER'S REPRESENTATIVE. SUBMITTAL
REQUIRED.
44. THE CONTROLS CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR MAKING THE CONTROL
SYSTEM COMPLETE AND FULLY OPERABLE. THE CONNECTION TO THE EXISTING CONTROL
SYSTEM SHALL BE COMPLETE SUCH THAT ALL NEW MONITORING AND CONTROL POINTS ARE
RECOGNIZED BY THE EXISTING CONTROL SYSTEM AND THAT ALL NEW POINTS CAN BE READ,
ACTUATED, AND RESET FROM THE EXISTING FRONT END, AND VICE-VERSA. IT IS THE
CONTRACTOR’S RESPONSIBILITY TO DETERMINE IF THERE IS ENOUGH SPACE AND/OR
COMPATABILITY EXISTS TO USE EXISTING CONTROLLERS OR OTHER ASSOCIATED EXISTING
CONTROLS EQUIPMENT. IF COMPATIBILITY AND/OR SPACE DOES NOT EXIST, IT IS THE CONTROLS
CONTRACTOR RESPONSIBILITY TO PROVIDE THE REQUIRED CONTROLLERS, BRIDGES, ETC. TO
ALLOW FULL INTEGRATION OF REQUIRED POINTS AND TO SATISFY THE SEQUENCE OF
OPERATIONS. THE ENGINEER SHALL BE NOTIFIED WHEN EACH PHASE OF THE SYSTEM HAS BEEN COMPLETELY CHECKED OUT, ADJUSTED, CALIBRATED, AND PUT INTO FINAL WORKING CONDITION
WITH ALL THE TROUBLESHOOTING COMPLETED. A SUBSEQUENT JOBSITE MEETING WILL BE
SCHEDULED WITH TWO WEEKS NOTICE AT WHICH TIME THE CONTROLS CONTRACTOR WILL
DEMONSTRATE THE OPERATION OF THE CONTROL SYSTEMS TO ALL CONCERNED. IF ANY ITEMS
OF THE CONTROL SEQUENCE CANNOT BE SUCCESSFULLY DEMONSTRATED OR REQUIRE
FURTHER TROUBLESHOOTING, A SUBSEQUENT CONTROLS INSPECTION WILL BE REQUIRED AND
WILL BE AT THE CONTRACTOR'S EXPENSE. THIS PROVISION SHALL BE A CONDITION OF FINAL
ACCEPTANCE. THE CONTRACTOR SHALL BE PREPARED TO DEMONSTRATE ALL ITEMS IN THE
SEQUENCE OF OPERATION. SUBSEQUENT CONTROLS DEMONSTRATIONS AND VERIFICATIONS
WILL BE REQUIRED AT THE COMPLETION OF THE PROJECT.
45. UNLESS THE OWNER CHOOSES TO USE THEIR OWN THIRD-PARTY TEST, ADJUST, AND BALANCE
AGENCY, THE MECHANICAL CONTRACTOR SHALL UTILIZE A THIRD PARTY TAB AGENCY FOR ALL
NECESSARY FINAL TAB AND PROVIDE COORDINATION WITH EQUIPMENT MANUFACTURER FOR
TYPICAL STARTUP SERVICES. FULL DOCUMENTATION, TO INCLUDE NECESSARY FACILITY STAFF
TRAINING, SHALL BE COMPLETED AND SUBMITTED TO ALLOW FOR REQUIRED CONTINUED
OPERATION AND MAINTENANCE.
DESCRIPTION OF MECHANICAL WORK:
1. CONDITIONED SQUARE FOOTAGE: 7114 SQUARE FEET
2. EXISTING SYSTEM(S): SEVERAL SPACES ON THE FIRST FLOOR CONTAIN A 4 PIPE FAN COIL UNIT.
THESE FAN COIL UNITS UTILIZE HOT AND CHILLED WATER, FANS FOR FORCED AIR AND A
CONDENSATE DRAIN. THESE FAN COIL UNITS ARE NEAR THE END OF THERE USEFUL LIFE AND
HAVE BEEN DEEMED ELIGIBLE FOR REPLACEMENT.
3. REMOVALS: SPECIFIED FCU'S SHALL BE DEMOLISHED. THE EXISTING MECHANICAL PIPING SHALL
BE DEMOLISHED BACK TO THEIR RESPECTIVE SHUT-OFF VALVES. THE EXISTING CONDENSATE
DRAIN SHALL BE DEMOLISHED TO DIRECTLY AFTER THE CONDENSATE TRAP. ALL ELECTRICAL
CIRCUITS CONNECTED TO THE FCU SHALL BE DEMOLISHED BACK TO ITS CORRESPONDING
PANEL.
4. NEW SYSTEM(S): NEW SPECIFIED FCU'S SHALL BE INSTALLED IN THE SAME LOCATION(S) AS THE
EXISTING FCU'S. FCU'S SHALL BE CONNECTED TO THE EXISTING HYDRONIC PIPING AT THE
EXTENT OF DEMOLITION AND CONDENSATE DRAIN AT THE EXTENT OF DEMOLITION. NEW
CIRCUITS WILL BE BROUGHT TO EACH UNIT. THE FCU'S WILL BE POWERED FROM PANEL PP-EP1A.
EACH SPACE CONTAINING A FCU SHALL HAVE A DEDICATED THERMOSTAT. THE PROJECT SHALL
IMPLEMENT CONTROLS INTEGRATION INTO THE EXISTING BAS. A TYPICAL SEQUENCE OF
OPERATION AND POINTS LIST SHALL BE SPECIFIED FOR ALL NEW MECHANICAL EQUIPMENT.
SUMMARY OF ENGINEERING CALCULATION AND ANALYSIS
1. THE SCOPE OF ENGINEERING ANALYSIS AND CALCULATIONS INCLUDE: COOLING LOAD
CALCULATIONS, HEATING LOAD CALCULATIONS, VENTILATION CALCULATIONS, CHILLED WATER
HYDRONIC PUMP, PIPING HEATING LOAD CALCULATIONS, VENTILATION CALCULATIONS, CHILLED WATER HYDRONIC PUMP, PIPING AND EQUIPMENT SIZING, HEATING HOT WATER HYDRONIC PUMP
PIPING AND EQUIPMENT SIZING, AND HUMIDIFICATION.
2. TOTAL CONDITIONED AREA: 7114 SQUARE FEET
3. AVERAGE FLOOR TO CEILING HEIGHT: 8 FEET
4. TOTAL CONDITIONED VOLUME: 56912 CUBIC FEET
5. SYSTEM CHILLED WATER DESIGN SUPPLY TEMP AND RETURN TEMP: 45 F/ 55 F
6. SYSTEM CHILLED WATER DESIGN FLOW: 92.6 GPM
7. SYSTEM DESIGN CHILLED WATER CHEMICAL / %: N/A
8. SYSTEM HEATING HOT WATER DESIGN SUPPLY TEMP AND RETURN TEMP: 180 F/ 160 F
9. SYSTEM HEATING HOT WATER DESIGN FLOW: 22 GPM
10. SYSTEM DESIGN HEATING HOT WATER CHEMICAL / %: N/A
11. QUANTITY OF HVAC ZONES: 17 ZONES
MECHANICAL CODE SUMMARY:
1. WHEN MULTIPLE CODES ARE LISTED, THE MOST STRINGENT REQUIREMENTS SHALL BE FOLLOWED.
2. MECHANICAL WORK: VA HVAC DESIGN MANUAL-2017
3. VENTILATION: VA HAVAC DESIGN MANUAL-2017
4. ENERGY CODE: ASHRAE 90.1-2019
5. MECHANICAL EQUIPMENT EFFICIENCY: ASHRAE 90.1-2019. TABLE 6.8.1
6. FAN POWER LIMITATION: ASHRAE 90.1-2019
A. TABLE 6.5.3.1-1: FAN NAMEPLATE HORSEPOWER < DESIGN CFM X 0.0015
B. TABLE 6.5.3.1-1: FAN POWER LIMITATION PRESSURE DROP ADJUSTMENT CREDITS
7. FAN CONTROL: VARIABLE PER ASHRAE 90.1-2019, SECTION 6.5.3.2
8. PUMP CONTROL: VARIABLE PER ASHRAE 90.1-2019, SECTION 6.5.4.2
9. CLIMATE ZONE: (5A)
10. PIPE SUPPORT BRACING: PER TABLE 305.4, 2018 IMC
A. SEISMIC BRACING REQUIRED? NO
B. MAX HORIZONTAL SPACING: STEEL PIPE-12FT; COPPER PIPE-12FT; PVC PIPE-4FT; POLY-2.5FT
C. MAX VERTICAL SPACING: STEEL PIPE-15FT; COPPER-10FT, PVC PIPE-10FT, POLY-10FT
D. ALL OTHER PIPING AND TUBING SEE TABLE 305.4, 2018 IMC
MECHANICAL EQUIPMENT SUPPORTING FUNCTIONAL SPACES
ROOM NO. ROOM NAME VA ROOM CODE
DEDICATED
VAV
PERIMETER
HEAT
EXHAUST
FAN
UNIT
HEATER
FAN COIL
UNIT
PRESSURIZATION
MONITORING NOTES
H-105 CONFERENCE ROOM SALG2: STAFF LOUNGE AND LOCKERS X
H-107 FAMILY ROOM CLHBD: RESIDENT BEDROOM X
H-113 STAFF LOUNGE CLHBD: RESIDENT BEDROOM X
H-117 4 BEDROOM CFR01: CONFERENCE ROOM X
H-119 2 BEDROOM CFR01: CONFERENCE ROOM X
H-120 2 BEDROOM CFR01: CONFERENCE ROOM X
H-123 2 BEDROOM CLHBD: RESIDENT BEDROOM X
H-124 2 BEDROOM CLHBD: RESIDENT BEDROOM X
H-125 SINGLE BEDROOM CLHBD: RESIDENT BEDROOM X
H-126 SINGLE BEDROOM CLHBD: RESIDENT BEDROOM X
H-128 2 BEDROOM CLHBD: RESIDENT BEDROOM X
H-129 DAYROOM CFR01: CONFERENCE ROOM X
H-129 DAYROOM CLNMR: MULTIPURPOSE ROOM X
H-130 2 BEDROOM CLHLR: LIVING ROOM X
H-132 SINGLE BEDROOM CLHBD: RESIDENT BEDROOM X
H-133 SINGLE BEDROOM CLHBD: RESIDENT BEDROOM X
H-135 2 BEDROOM CLHBD: RESIDENT BEDROOM X
H-136 2 BEDROOM CLHBD: RESIDENT BEDROOM X
H-138 4 BEDROOM CLHBD: RESIDENT BEDROOM X
24" X 24" EXHAUST
HOOD.
4 BEDROOM
H-117
2 BEDROOM
H-119
2 BEDROOM
H-120
2 BEDROOM
H-123
2 BEDROOM
H-124
SINGLE
BEDROOM
H-125
SINGLE
BEDROOM
H-126
2 BEDROOM
H-128
DAYROOM
H-129
2 BEDROOM
H-130
SINGLE
BEDROOM
H-132
SINGLE
BEDROOM
H-133
2 BEDROOM
H-135
2 BEDROOM
H-136
4 BEDROOM
H-138
CONFERENCE
ROOM
H-105
FAMILY ROOM
H-107
STAFF LOUNGE
H-113
ELECT. CL.
H-137
MECH. EQUIP
ROOM
H-103
EQPM. CLOSET
H-118
STORAGE
H-146
CLEAN UTIL.
STORAGE
H-116
TOILET
H-117A
BATH
H-119A
BATH
H-120A
BATH
H-123A
BATH
H-124A
BATH
H-125A
BATH
H-126A
WC STOR.
H-127
TOILET
H-128A
STOR.
H-131
TOILET
H-130A
BATH
H-132A
BATH
H-133A
BATH
H-135A
BATH
H-136A
TOILET
H-138A DATA CLOSET
H-139
LOUNGE
H-100
ELEVATOR
LOBBY
C1-01
ELEVATOR
ELEVATOR
CLEAN LINEN
H-101
TOILET
H-105A
TOILET
H-107A
FEMALE
LOCKERS
H-114
TOILET
H-114A
SHOWER
H-114B
TOILET
H-115B
SHOWER
H-115
DIST SUPPLY CL.
H-143
BATHROOM
H-142
OFFICE
H-111
STORAGE
H-109
TOILET
H-108
NUTRITION ROOM
H-110
MED ROOM
H-112
OFFICE
H-106A
OFFICE
H-106
SOILED UTILITY
H-104 WHEEL CHAIR
STORAGE
H-102
E.M.S. CL
H-141
STORAGE
H-140
1 1 1 1 11 1
30-MINUTE SMOKE BARRIER
2-HR FIRE BARRIER
FIRST FLOOR KEY PLAN
105063
ST
ATE
OF NEW YORK
MA
T TH
EW LLOYD
LICENSED PROFESSIONAL
EN
GI
NE
ER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTSOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Watson Engineering, P.C.
1112 State Rte. 434 Owego, NY 13827 (607)223-4334
REPLACE FAN COIL UNITS
CASTLE POINT VAMC, WAPPINGERS FALLS, NEW YORK
620A4-19-203
15H
08/25/2023 MPL AMR
10/5/2022
BI
M
VA
-2
R ep la ce
F an
C oi l U ni ts /R ep la ce F an C oi l U ni ts
.rv t
4/ 4/
:4
9:
P M
MD101
MECHANICAL 1ST FLOOR
DEMOLITION PLAN
1/8" = 1'-0"1 MECHANICALDEMOLITION PLAN
MECHANICAL DEMOLITION NOTES
1. ALL AREAS OF THE BUILDING AFFECTED BY MECHANICAL DEMOLITION WORK SHALL BE PATCHED AND
REPAIRED TO MATCH ADJACENT FINAL FINISHES. THE REPAIR WORK SHALL BE DONE TO THE
OWNER'S SATISFACTION.
2. DEMOLITION WORK SHALL INCLUDE REMOVAL OF EXISTING BUILDING CONSTRUCTION TO EXTENT
REQUIRED TO PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
3. REMOVE ALL EXISTING MECHANICAL SYSTEM COMPONENTS, MATERIALS , APPARATUS, AND
APPLIANCES WITHIN THE DESIGNATED PROJECT AREA, UNLESS OTHERWISE NOTED. COORDINATE WITH ARCHITECTURAL, MECHANICAL, ELECTRICAL, FIRE PROTECTION, AND PLUMBING CONTRACT
DOCUMENTS FOR ADDITIONAL SCOPE OF WORK FOR SYSTEMS TO BE REMOVED OR RETAINED TO
EXTENT REQUIRED TO PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
4. THE DEMOLITION PROCEDURES SHALL PROVIDE FOR SAFE CONDUCT OF THE WORK, PROTECTION OF
PERSONNEL, CAREFUL REMOVAL AND OTHER DISPOSITION OF MATERIALS SPECIFIED TO BE
SALVAGED. PROTECTION OF PROPERTY TO REMAIN UNDISTURBED, COORDINATION WITH OTHER
WORK IN PROGRESS, AND TIMELY DISCONNECTION OF UTILITY SERVICES.
5. EXISTING WORK SHALL BE CUT, DRILLED, ALTERED, REMOVED, OR TEMPORARILY REMOVED AND
REPLACED FOR PERFORMANCE OF WORK UNDER THE CONTRACT. WORK REPLACED SHALL MATCH
SIMILAR EXISTING WORK. STRUCTURAL MEMBERS OF CONCRETE OR STRUCTURAL STEEL SHALL NOT
BE CUT OR ALTERED, EXCEPT AS SHOWN, WITHOUT AUTHORIZATION OF THE ENGINEER. WORK
REMAINING IN PLACE DAMAGED OR DEFACED DURING THIS CONTRACT SHALL BE RESTORED TO THE CONDITION AT TIME OF AWARD OF CONTRACT. CUT, ALTER, REMOVE, OR TEMPORARILY REMOVE AND
REPLACE EXISTING WORK FOR INSTALLATION OF ELECTRICAL WORK.
6. A PRE-TAB SHALL BE CONDUCTED TO MEASURE THE FOLLOWING: SERVICEABILITY OF ALL ISOLATION VALVES SERVING FAN COIL UNITS AND RELEVANT HOT AND CHILLED WATER LOOPS, LOOP FLOW OF CHW AND HW WITH FAN COIL UNITS AT MAX FLOW, FLOW OF CHW AND HW AT EACH FAN COIL UNIT WITH FAN COIL UNITS AT MAX FLOW, EWT AND LWT FOR CHW AND HW LOOPS, % GLYCOL, LOCATION OF HYDRONIC PUMPS AND PUMP RATINGS SERVING EACH LOOP, AND DP AND FLOW MEASUREMENTS
ACROSS HYDRONIC PUMPS SERVING EACH LOOP.
KEYED NOTES
EXISTING 4-PIPE FAN COIL UNIT TO BE DEMOLISHED. DEMOLITION SHALL INCLUDE REMOVAL
OF FAN COIL UNITS, HYDRONIC HEATING AND CHILLED WATER PIPING DOWN TO ISOLATION
VALVES IN BASEMENT, CONDENSATE DRAIN PIPING DOWN TO BASEMENT, AND UNIT
CONTROLS (INCLUDING CONTROL VALVE AND SPACE THERMOSTAT). CONTRACTOR SHALL
BE RESPONSIBLE FOR INSTALLATION OF TEMPORARY PROVISIONS, IF NECESSARY, IN
ORDER TO ISOLATE THE SYSTEM AND PERFORM WORK. ALL ISOLATION VALVES WITHIN
BOUNDARY OF WORK SHALL BE REPLACED WITH NEW BALL VALVES.
CH
D
ELEVATOR
ELEVATOR
CHIEF
OFFICE
046I
OCCUPATIONAL
THERAPY
EMPLOYEE FITNESS AND
WELLNESS CENTER
H-047
EDUCATION
OFFICE
H-047A
OFFICE
H-048
DATA-TELE
CL.
H-04
E.M .S.
CLO
SET
H-05
ELE
CTRIC
AL
ROOM
H-05
1A
ELE
CTRIC
AL
ROOM
H-05
OFFIC
E H-05
ELE
VATOR
MECHANIC
AL
ROOM
H-05
MECHANIC
AL
EQUIPMENT
ROOM
H-05
PHYSICAL
THERAPY
CLINIC
H-046
ADL
KITCHEN
H-046G
SPLINT
RM
H-046F
CORRID
OR
STOR.
ROOM
H-001
STAIR
HALL "A"
TOILET
H-043
TELE. CL.
H-044
VENDING
AREA
H-026A
OT
OFFICES
H-046D
KT OFFICE
H-046E
NEW
OFFICE
H-046C
TOILET
H-046A
TOILET
VACANT
H-045
AGENT
CASHIER
H-042
TRAVEL
CLERK
H-041
TOILET
H-046B
STARBUCK'S
STORAGE
H-040 OFFIC
E
H-02 4A
OFFIC
E
H-02 4B
OFFIC
E
H-02 4C
OFFIC
E
SUPPORT
H-02
SWIN
G
OFFIC
E
H-02 4D
VESTIBULE
CB-03A
MAIN
LOBBY
CB-03
DINING
H-026
FOOD
SERVIC
E H-02
KITCHEN
H-03
FOOD
STORAGE
H-03
1A
DISHWASHIN
G
H-03 1B
FEMALE
LO
CKER
ROOM
H-02
MALE
LO
CKER
ROOM
H-02
H-03
1C
OFFICE
H-034A
ELE
C. C
L.
H-03
OFFICE
H-034
RETAIL
STORAGE
H-033
RETAIL
STORE
H-035
STARBUCK'S
H-025
MECHANICAL
EQUIPMENT
ROOM
H-032
CANTEEN
PASSAGE
CB-05
CORRID
OR
CB-02
ELE
VATOR
LO
BBY
CB-01
CORRIDOR
CB-06
SERVICE
LOBBY
CB-04
LEAD
OFFICE
046H
CONFERENCE
AREA
OT
AREA
PT OFFICE
H-046J
PT
STORAGE
H-046D1
Rehab. Entry
VESTIBULE
H02
GENERAL
ISOLA
TIO
N H01
2G
EXAM
ROOM
H01 2H
EXAM
ROOM
H01 2I
EXAM
ROOM
H01 2J
ISOLA
TIO
N R
OOM
H01 2K
OBSERVATIO
N R
OOM
H01 2L
EXAM / C
VT
ROOM
H01
2M
PAT. T
OILE
T H01
SOILE
D
UTILI
TY
ROOM
H01
CLE
AN
UTILI
TY
ROOM
H01
MED.
ROOM
H01 2A
MULT
I-P
URPOSE R
OOM
H02
MULT
I-P
URPOSE R
OOM
H00
MULT
I-P
URPOSE R
OOM
H02 2A
OFFIC
E
H01
NURSE
STATIO
N H01
2N
OBSERVATIO
N R
OOM
H01 2B
OBSERVATIO
N R
OOM
H01 2C
PATIENT
TOILE
T H01
2B
MECHANIC
AL
ROOM
H00
TOILE
T
H00 8A
TOILE
T
H02 0A
CIR
CULA
TIO
N
H01
PATIENT
TOLE
T H01
2D
FEMALE
E
XAM/
OBSERVATIO
N
H01 2D
NURSE TRIAGE
H01 2E
GIP C
LE
AN
SUPPLY
STOR.
H01 2F
CLE
AN LI
N.
H01
MULT
I-P
URPOSE STORAGE
H00
AMBULA
NCE
BAY
STAIR
H
ALL
H01
CORRID
OR
H02
CONFERANCE
ROOM
H01
STAFF
TOILE
T H01
CORRID
OR
TRAVEL
ROOM
H02
L
OU
VE
R
FD
FD
CH
D
L
OU
VE
R
HWR
HWS
CHR
CHS
D D
D
D
HWR
HWS
CHR
CHS
3/4"ø D 3/4"ø HWR 3/4"ø HWS
1"ø CHR 1"ø CHS
3/4"ø D 3/4"ø HWR 3/4"ø HWS
1"ø CHR 1"ø CHS
3/4"ø D 3/4"ø HWR 3/4"ø HWS
1"ø CHR 1"ø CHS
3/4"ø D 3/4"ø HWR 3/4"ø HWS
1 1/4"ø CHR 1 1/4"ø CHS
C H
S C
H R
H W
S H
W R
D
H W
S H
W R
1"ø CHS 1"ø CHR 3/4"ø HWS 3/4"ø HWR 3/4"ø D
1"ø CHS 1"ø CHR 3/4"ø HWS 3/4"ø HWR 3/4"ø D
3/4"ø D 3/4"ø HWR 3/4"ø HWS
1 1/4"ø CHR 1 1/4"ø CHS
1 1/4"ø CHS 1 1/4"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
1"ø CHS 1"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
C H
R C
H S
1"ø CHS 1"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
CHR
HWR
1"ø CHS 1"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
D
1"ø CHS 1"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
1"ø CHS 1"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
1"ø CHR 1"ø CHS
3/4"ø HWS 3/4"ø HWR
3/4"ø D
1"ø CHR 1"ø CHS
3/4"ø HWS 3/4"ø HWR
3/4"ø D
1"ø CHR 1"ø CHS
3/4"ø HWS 3/4"ø HWR
3/4"ø D
C H
R C
H S
H W
S H
W R
D
CHR
CHS
HW
S
HW
R
D
CHR
CHS
HW
S
HW
R
D
1"ø CHR
1"ø CHR
1"ø CHR
CHR
CHS
HWS
HWR
H W
S H
W R
CHR HW
R
HW
R
HW
S
CHS
CHR
HW
S HW
R
CHS
CHR
C H
S
D
D
D C
H S
H W
S H
W R
CHS
HW
S
HW
RC
H S
H W
S
D
CHR
1"ø CHS 1"ø CHR
3/4"ø HWS 3/4"ø HWR
3/4"ø D
3/4"ø D 3/4"ø HWR 3/4"ø HWS 1"ø CHR 1"ø CHS
3/4"ø D 3/4"ø HWR 3/4"ø HWS 1"ø CHR 1"ø CHS
30-MINUTE SMOKE BARRIER
2-HR FIRE BARRIER
CV-2
CV-1
11111
BASEMENT KEY PLAN
105063
ST
ATE
OF NEW YORK
MA
T TH
EW LLOYD
LICENSED PROFESSIONAL
EN
GI
NE
ER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTSOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Watson Engineering, P.C.
1112 State Rte. 434 Owego, NY 13827 (607)223-4334
REPLACE FAN COIL UNITS
CASTLE POINT VAMC, WAPPINGERS FALLS, NEW YORK
620A4-19-203
15H
08/25/2023 MPL AMR
10/5/2022
BI
M
VA
-2
R ep la ce
F an
C oi l U ni ts /R ep la ce F an C oi l U ni ts
.rv t
4/ 4/
:4
8:
P M
M-101
MECHANICAL BASEMENT NEW
WORK PLAN
1/8" = 1'-0"1 MECHANICAL PLAN BASEMENT
MECHANICAL NOTES
1. ALL MECHANICAL WORK SHALL BE DONE IN ACCORDANCE WITH ALL LOCAL AND STATE
REGULATIONS FOR THE STATE OF NEW YORK.
2. DRAWINGS ARE DIAGRAMMATIC AND GENERALLY INDICATIVE OF THE WORK. ALL SYSTEMS SHALL
FOLLOW ARRANGEMENT AS MUCH AS POSSIBLE, HOWEVER, ACTUAL FIELD CONDITIONS SHALL
DICTATE. PROVIDE NECESSARY MODIFICATIONS TO MEET FIELD CONDITIONS AND AVOID
CONFLICT WITH OTHER IF RESOLUTION CANNOT BE REACHED WITHOUT COMPROMISING THE
DESIGN, THESE CONFLICTS SHALL BE PRESENTED TO THE ENGINEER FOR RESOLUTION. IN
CONFLICT AREAS, COMPLETE ONLY WORK NOT AFFECTED BY THE CONFLICT PRIOR TO
RESOLUTION.
3. CONNECTIONS TO EQUIPMENT SHALL CONFORM TO MANUFACTURER'S SPECIFICATIONS.
4. ALL HANGER SYSTEMS FOR PIPING AND EQUIPMENT SHALL BE SECURED TO BUILDING
STRUCTURAL SYSTEM.
KEYED NOTES
1 CHILLED/HOT WATER SUPPLY/RETURN AND SANITARY PIPES UP THROUGH FLOOR SHALL CONNECT ALL TO NEW FAN COIL UNIT. INSTALL NEW ISOLATION VALVES ON CWS, CWR, HWS, AND HWR LINES
CONNECTING TO NEW FAN COIL UNITS. REFER TO SHEET M-501 FOR CONNECTION DETAILS.
2 EXISTING CHILLED WATER CONTROL VALVE SHALL BE REPLACED WITH NEW ENERGY METERING CONTROL VALVE. REFER TO SCHEDULE ON DRAWING SHEET M-601 FOR ADDITIONAL INFORMATION.
Revisions: Date:
ADDENDUM 01 4/4/2024
3 INSTALL THERMOWELL ON SUPPLY PIPING FOR INSTALLATION OF ENERGY METERING CONTROL VALVE
MANUFACTURER PROVIDED TEMPERATURE PROBE.
4 BEDROOM
H-117
2 BEDROOM
H-119
2 BEDROOM
H-120
2 BEDROOM
H-123
2 BEDROOM
H-124
SINGLE
BEDROOM
H-125
SINGLE
BEDROOM
H-126
2 BEDROOM
H-128
DAYROOM
H-129
2 BEDROOM
H-130
SINGLE
BEDROOM
H-132
SINGLE
BEDROOM
H-133
2 BEDROOM
H-135
2 BEDROOM
H-136
4 BEDROOM
H-138
CONFERENCE
ROOM
H-105
FAMILY ROOM
H-107
STAFF LOUNGE
H-113
ELECT. CL.
H-137
MECH. EQUIP
ROOM
H-103
EQPM. CLOSET
H-118
T
T
T
T
T
T
T
T
T
T T T T T T
T
T
T
STORAGE
H-146
CLEAN UTIL.
STORAGE
H-116
TOILET
H-117A
BATH
H-119A
BATH
H-120A
BATH
H-123A
BATH
H-124A
BATH
H-125A
BATH
H-126A
WC STOR.
H-127
TOILET
H-128A
STOR.
H-131
TOILET
H-130A
BATH
H-132A
BATH
H-133A
BATH
H-135A
BATH
H-136A
TOILET
H-138A DATA CLOSET
H-139
LOUNGE
H-100
ELEVATOR
LOBBY
C1-01
ELEVATOR
ELEVATOR
CLEAN LINEN
H-101
TOILET
H-105A
TOILET
H-107A
FEMALE
LOCKERS
H-114
TOILET
H-114A
SHOWER
H-114B
MALE LOCKERS
H-115A
TOILET
H-115B
SHOWER
H-115
DIST SUPPLY CL.
H-143
BATHROOM
H-142
OFFICE
H-111
STORAGE
H-109
TOILET
H-108
NUTRITION ROOM
H-110
MED ROOM
H-112
OFFICE
H-106A
OFFICE
H-106
SOILED UTILITY
H-104 WHEEL CHAIR
STORAGE
H-102
E.M.S. CL
H-141
STORAGE
H-140
FCU
FCU6
FCU6
FC
U6
FC
U6
FC
U6
FC
U6
FC
U6
FC
U6
FC
U6
FC
U8
FC
U
FCU
FCU
FCU
FCU
FCU
FCU
FCU
15H-FCU-4
15H-FCU-5
15H-FCU-6
15H-FCU-7
15H-FCU-8
15H-FCU-9
15H-FCU-10
15H-FCU-11
15H-FCU-12
15H-FCU-13 15H-FCU-14 15H-FCU-15 15H-FCU-16 15H-FCU-17 15H-FCU-18 15H-FCU-19
15H-FCU-2
15H-FCU-3
15H-FCU-1
1 1
30-MINUTE SMOKE BARRIER
2-HR FIRE BARRIER
FIRST FLOOR KEY PLAN
105063
ST
ATE
OF NEW YORK
MA
T TH
EW LLOYD
LICENSED PROFESSIONAL
EN
GI
NE
ER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTSOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Watson Engineering, P.C.
1112 State Rte. 434 Owego, NY 13827…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .