36C24220Q0367 Roof Replacement BLDG 2 Evaluation Questions.docx

View the file

Other files

File Type Posted
36C24220Q0367-001.docx DOCX document
36C24220Q0367-003.pdf PDF
36C24220Q0367-002.docx DOCX document
36C24220Q0367-004.zip ZIP file
36C24220Q0367-005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roof Replacement BLDG 2 Project 528-20-116 Contractor Evaluation Questions

MARGINAL
Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weakness which are not offset by strengths. Risk of unsuccessful performance is high.
ACCEPTABLE
Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance, Risk of unsuccessful performance is moderate.
GOOD
Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strength which outweigh any weakness. Risk of unsuccessful performance is low.

Questions below will be rated using the scale set out above. Questions are listed in order of importance. Responses are limited to one page, double spaced using Calibri 12 font.

1. State whether key personnel responsible for installing new roofing material are prime or subcontracted employees.

2. Provide three references for similar projects in the past 5 years installing ‘EPDM’ roofing material. Include a point of contract, phone number and contract number, if applicable.

3. Material warranty period.

This procurement will be utilizing a tradeoff process. When taking these three factors into consideration, they are more important than price. However, price remains an important factor. In the event of a tie, selection will be made by the lowest price. Scoring will be based on an adjectival assessment by the Contracting Officer’s Representative (COR). The COR will be the sole evaluator.