36C24219B0031-005.pdf

PDF 92 KB Posted

Attached to
528A5-18-529 REPLACE WINDOWS B36 GROUND AND FIRST FLOORS | Federal contract opportunity
Solicitation number
36C24219B0031
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

36C24219B0031 P07-Wage Determination-Ontario County-Replace Windows.pdf

View the file

Other files for this federal contract opportunity

Other files attached to 528A5-18-529 REPLACE WINDOWS B36 GROUND AND FIRST FLOORS |, newest first.
File Type Posted
36C24219B0031-0004000.docx DOCX document
36C24219B0031-0003002.pdf PDF
36C24219B0031-0003000.docx DOCX document
36C24219B0031-0003001.pdf PDF
36C24219B0031-0002001.pdf PDF
36C24219B0031-0002000.docx DOCX document
36C24219B0031-0001001.pdf PDF
36C24219B0031-0001000.docx DOCX document
36C24219B0031-0001002.pdf PDF
36C24219B0031-0001003.pdf PDF
36C24219B0031-004.pdf PDF
36C24219B0031-002.pdf PDF
36C24219B0031-001.docx DOCX document
36C24219B0031-003.pdf PDF
36C24219B0031-000.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

https://www.wdol.gov/wdol/scafiles/davisbacon/NY32.dvb?v=1[3/28/2019 3:02:49 PM]

General Decision Number: NY190032 03/01/2019 NY32

Superseded General Decision Number: NY20180032

State: New York

Construction Types: Building, Heavy and Highway

County: Ontario County in New York.

BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories), HEAVY AND HIGHWAY CONSTRUCTION

PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/04/2019 1 03/01/2019

CARP0276-007 07/01/2018

Rates Fringes

Carpenters (HEAVY & HIGHWAY CONSTRUCTION)....................$ 30.40 22.18+a Carpenters, including Drywall Hanging (BUILDING CONSTRUCTION

Entire County, excluding the Towns of Phelps, Seneca and Geneva)..........................$ 29.42 21.40+a

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day.

CARP0276-010 07/01/2018

Rates Fringes

Carpenters (BUILDING

CONSTRUCTION

ONTARIO COUNTY (Towns of Phelps, Seneca and Geneva))......$ 29.42 21.40

ELEC0086-005 05/28/2018

REMAINDER OF COUNTY

Rates Fringes

ELECTRICIAN......................$ 33.20 5.25%+22.73

ELEC0840-002 06/01/2018

TOWNSPHIP OF FARMINGTON, MANCHESTER, PHELPS, HOPEWELL, GENEVA,

GORHAM, SENECA AND CANANDAIGUA

Rates Fringes

ELECTRICIAN......................$ 32.25 22.54

ELEC1249-003 05/07/2018

Rates Fringes

ELECTRICIAN (LINE

CONSTRUCTION: LIGHTING AND

TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems) Flagman.....................$ 26.28 6.75%+23.40+a Groundman (Truck Driver)....$ 35.04 6.75%+23.40+a Groundman Truck Driver (tractor trailer unit)......$ 37.23 6.75%+23.40+a Lineman & Technician........$ 43.80 6.75%+23.40+a Mechanic....................$ 35.04 6.75%+23.40+a

FOOTNOTE:

a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.

ELEC1249-004 05/07/2018

Rates Fringes

ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :

Flagman....................$ 30.36 6.75%+23.40+a Groundman digging machine operator...................$ 45.54 6.75%+23.40+a Groundman truck driver (tractor trailer unit).....$ 43.01 6.75%+23.40+a Groundman Truck driver.....$ 40.48 6.75%+23.40+a Lineman and Technician.....$ 50.60 6.75%+23.40+a Mechanic...................$ 40.48 6.75%+23.40+a Substation:

Cable Splicer..............$ 55.66 6.75%+23.40+a Flagman....................$ 30.36 6.75%+23.40+a Ground man truck driver....$ 40.48 6.75%+23.40+a Groundman digging machine operator...................$ 45.54 6.75%+23.40+a Groundman truck driver (tractor trailer unit).....$ 43.01 6.75%+23.40+a Lineman & Technician.......$ 50.60 6.75%+23.40+a Mechanic...................$ 40.48 6.75%+23.40+a Switching structures;

railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 57.11 6.75%+23.40+a Flagman....................$ 31.15 6.75%+23.40 Groundman Digging Machine Operator...................$ 46.73 6.75%+23.40+a Groundman Truck Driver (tractor-trailer unit).....$ 44.13 6.75%+23.40+a Groundman Truck Driver.....$ 44.13 6.75%+23.40+a Lineman & Technician.......$ 51.92 6.75%+23.40+a Mechanic...................$ 41.54 6.75%+23.40+a

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.

* ELEC1249-008 01/01/2019

Rates Fringes

ELECTRICIAN (Line Construction)

TELEPHONE, CATV

FIBEROPTICS CABLE AND

EQUIPMENT

Cable splicer..............$ 32.78 3%+4.93 Groundman..................$ 16.49 3%+4.93 Installer Repairman- Teledata Lineman/Technician- Equipment Operator.........$ 31.12 3%+4.93 Tree Trimmer................$ 23.95 3%+9.98+a

a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.

ENGI0832-001 07/01/2018

Rates Fringes

Operating Engineer:

EXCAVATING AND PAVING

GROUP 1....................$ 31.45 27.55+a GROUP 2....................$ 30.98 27.55+a GROUP 3....................$ 30.29 27.55+a GROUP 4....................$ 26.80 27.55+a MASTER MECHANIC............$ 33.45 27.55+a

HEAVY AND HIGHWAY

GROUP 1....................$ 41.51 28.25+a GROUP 2....................$ 40.80 28.25+a GROUP 3....................$ 37.94 28.25+a GROUP 4....................$ 45.51 28.25+a GROUP 5....................$ 44.51 28.25+a GROUP 6....................$ 43.51 28.25+a GROUP 7....................$ 42.94 28.25+a

TUNNEL AND SHAFT

GROUP 1....................$ 44.24 28.35+a GROUP 2....................$ 43.02 28.35+a

GROUP 3....................$ 40.23 28.35+a GROUP 4....................$ 37.22 28.35+a MASTER MECHANIC............$ 46.65 28.35+a

For EXCAVATION AND PAVING:

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Christmas Day, regardless of the day of the week on which the holiday may fall, provided the employee works either on the work day immediately preceding the holiday or on the scheduled work day immediately following the holiday.

EXCAVATION AND PAVING CLASSIFICATIONS

GROUP 1: Asphalt paver; automatic fine grader; backhoe (except tractor mounted, rubber tired); blacktop plant (automated); cableway; caisson auger; central mix concrete plant (automated); cherry picker- over 5 ton capacity;

crane; cranes and derricks (steel erection); dragline; dual drum paver; front end loader (4 cu. yd. and over);

hoist,(Tow or 3 drum); pile driver; power grader with elevation loader attachment; quarry master (or equivalent);

shovel; slip form paver; tractor drawn belt-type loader;

truck crane tunnel shovel; excavator, all purpose hydraulically operated

GROUP 2: Backhoe (tractor mounted, rubber tired); bituminous spreader and mixer; blacktop plant (non automated); boring machine; cage hoist; central mix plant (non automated) and all concrete batching plants; cherry picker, 5 tons and under; compressor (4 or less) exceeding 2000 CFM combined capacity; concrete paver over 16s; concrete pump; crusher;

drill rigs (tractor mounted); front end loader (under 4 cu.

yds); hi- pressure boiler (15 lbs and over); hoist (one drum); Kolman plant loader and similar type loaders;

maintenance engineer; maintenance grease man; mechanical slurry machine; mixer for stabilized base self propelled;

monorail machine; plant engineer; power broom; power grader; pump crete; ready mix concrete plant; road widener;

roller (all above sub-grade); side boom; tractor scraper;

tractor with dozer and or pusher; trencher; winch

GROUP 3: Compressors (4 not to exceed 2000 CFM combined capacity; or 3 or less with more than 1200 CFM but not to exceed 2000 CFM); compressors (any size but subject to other provisions for compressors); dust collectors;

generators; welding machines (4 of any type or combination); concrete pavement spreaders and finishers;

conveyor; drill (core); drill (well); electric pump used in conjunction with well point systems; farm tractor with accessories; fine grade machine; fork lift; gunite machine;

hammers-hydraulic-self propelled; locomotive; post hole digger and post driver; pumps (regardless of motive power, not more than 4 in number not to exceed 20" in total capacity); submersible electric pumps when used in lieu of well points, tractor with towed accessories; vibratory compactor; vibro tamp; well point

GROUP 4: Compressor (any size, but subject to other provisions for compressors); dust collectors; generators;

welding machines (3 or less of any type or combination);

concrete mixer (16s and under), concrete saw-self propelled; fireman; form tamper; mulching machine; power heaterman; pumps regardless of motive power no more than 3 in number not to exceed 12" in total capacity; revinius widener; steam cleaner; tractor

GROUP 5: Master Mechanic

For HEAVY AND HIGHWAY CONSTRUCTION:

FOOTNOTE:

b. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day provided the employee works the working day before and the working day after the holiday

POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY/HIGHWAY):

GROUP 1: Asphalt Curb Machine, Self Propelled, Slipform, Automated Concrete Spreader (CMI Type), Automatic Fine Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Back Filling Machine, Belt Placer (CMI Type), Blacktop Plant (Automated), Boom truck , Cableway, Caisson Auger, Central Mix Concrete Plant (Automated), Concrete Curb Machine, Self Propelled, Slipform, Concrete Pump, Crane, Cherry Picker, Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane, Directional Drilling Machine, Dredge, Dual Drum Paver, Excavator (All Purpose Hydraulically Operated) (Gradall or Similar), Front End Loader ( 4 cu. yd. and Over), Head Tower (Sauerman or Equal), Hoist (Two or Three Drum), Holland Loader, Maintenance Engineer, Mine Hoist, Mucking Machine or Mole Pavement Breaker(SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P.)

Quad 9, Quarry Master (or equivalent), Scraper, Fireman, Fork Lift, Form Tamper, Grout Pump, Gunite Machine, Hammers (Hydraulic self-propelled), Hydra-Spiker, ride-on, Hydraulic Pump (jacking system), Hydro-Blaster (Water), Mulching Machine, Oiler, Parapet Concrete or Pavement, Shovel, Side Boom, Slip Form Paver, Tractor Drawn, BeltType Loader, Truck or Trailer Mounted Log , Chipper (Self Feeder), Tug Operator (Manned Rented Equipment Excluded), Tunnel Shovel

GROUP 2: Asphalt Paver, Backhoe (Tractor Mounted, Rubber Tired), Bituminous Recycler Machine, Bituminous Spreader and Mixer, Blacktop Plant (NonAutomated), Blast or Rotary Drill (Truck or Tractor Mounted), Boring Machine, Cage Hoist, Central Mix Plant (NonAutomated) and All Concrete Batching Plants, Cherry Picker (5 tons capacity and under), Concrete Paver (Over 16S), Crawler Drill, Self-contained, Crusher, Diesel Power Unit, Drill Rigs, Tractor Mounted, Front End Loader (Under 4 cu. yd.), Greaseman/Lubrication Engineer, HiPressure Boiler (15 lbs. and over), Hoist (One Drum), Hydro-Axe, Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive Mixer (for stabilized base selfpropelled), Monorail Machine, Plant Engineer, Profiler (105 H.P. and under), Grinder, Post Hole Digger and Post Driver, Power Broom (towed), Power Heaterman, Power Sweeper, Revinius Widener, Roller (Grade and Fill), Scarifier, ride-on, Shell Winder, Skid steer loader (Bobcat or similar), Span-Saw, ride-on, Steam Cleaner, Pug Mill, Pump Crete Ready Mix Concrete Plant Refrigeration Equipment (for soil stabilization)Road Widener, Roller (all above subgrade), Sea Mule, Self-contained Ride-on Rock Drill, Excluding Air-Track Type Drill, Skidder, Tractor with Dozer and/or Pusher, Trencher.

Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat

GROUP 3: A Frame Winch Hoist on Truck , Articulated Heavy Hauler, Aggregate Plant, Asphalt or Concrete Grooving, Machine (ride on), Ballast Regulator, Ride-on Boiler (used in conjunction with production), Bituminous Heater, self-propelled, Boat (powered), Cement and Bin Operator, Compressors, Dust Collectors, Generators, Pumps, Welding Machines, Light Plants, Heaters (hands-off equipment), Concrete Pavement Spreader and Finisher, Concrete Paver or Mixer (16S and under), Concrete Saw (self-propelled), Conveyor, Deck Hand, Directional Drill Machine Locator, Drill, (Core), Drill, (Well,) Farm Tractor with accessories, Fine Grade Machine, Tamper, ride-on, Tie Extractor, ride-on, Tie Handler, ride-on, Tie Inserter, ride-on, Tie Spacer, ride-on, Tire Repair, Track Liner, ride-on, Tractor, Tractor (with towed accessories), Vibratory Compactor, Vibro Tamp, Well Point

GROUP 4: Tower Cranes

GROUP 5: Cranes 50 tons and over

GROUP 6: Cranes 49 tons and below

GROUP 7: Master Mechanic

For TUNNEL AND SHAFT:

FOOTNOTE:

b. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, regardless of the day of the week on which the Holiday may fall, provided the employee works the working day before and the working day after the holiday

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Automated concrete spreader (CMI or equivalent);

automated fine grade machine (cmi); backhoe; belt placer (cmi or similar); blacktop spreader (automated); cableway;

caisson auger; central mix plant (automated); cherry picker (5 tons); concrete curb machine (self-propelled slipform);

concrete pump; crane; crane shaft; crane underground;

cranes and derricks (steel erection); dragline; dredge;

dual drum paver; excavator (all purpose-hydraulicly operated gradall or similar); fork lift (factory rated 15' and over); front end loader (4cu yd and over); head tower (sauerman or equal); hoist; shaft; hoist (two or three drum); holland loader; maintenance engineer (shaft and tunnel); mine hoist; mining machine (mole and similar types); mucking machine or mose; overhead crane (gantry or straddle type); pile driver; power grader; Quad 9, quarry master (or equivalent); scraper; shovel; side boom; slip form paver; tripper/maintenance engineer (shaft and tunnel); tractor drawn belt-type loader; truck crane; truck or trailer mounted log chipper (self feeder); tug operator (manned rented equipment excluded); tunnel shovel

GROUP 2: Automated central mix concrete plant; backhoe (topside); backhoe (tractor mounted,rubber tired);

bituminous spreader and mixer; blacktop plant (non automated); blast or rotary drill (truck or tractor mounted); boring machine; cage hoist; central mix plant (non automated) and all concrete batching plants; cherry picker (5 tons capacity and under); compressors (4 or less exceeding 2000 CFM combined capacity); concrete paver (over 16s); concrete pump; crane (topside); crusher; diesel power unit; drill rigs, tractor mounted; front end loader (under 4 cu. yds); grayco epoxy machine; hi-pressure boiler (15 lbs and over); hoist (one drum); hoist (two or three drum) (topside); kolman plant loader and similar type loaders;

L.C.M. work boat operator; locomotive; maintenance engineer (topside); maintenance greaseman; mixer (for stabilized base self-propelled); monorial machine; plant engineer;

personnel hoist; pump crete; ready mix concrete plant;

refrigeration equipment (from soil stabilization); road widener; roller (all above sub-grade); sea mule; shotcrete machine; shovel (topside); tractor with dozer and/or pusher; trencher; tugger hoist; tunnel locomotive; welder;

winch; winch cat

GROUP 3: "A" frame truck; ballast regulator (ride on);

compressors (4 not to exceed 2000 cfm combined capacity; or 3 or less with more than 1200 cfm but not to exceed 2000 cfm); compressors (any size but subject to other provisions for compressors; dust collectors; generators; pumps;

welding machines; light plants (4 of any type or combination); concrete pavement spreaders and finishers;

conveyor; drill (core); drill (well); electric pump used in conjunction with well point system; farm tractor with accessories; fine grade machine; fork lift (under 15 ft);

ground pump over 5 cu. ft (manufacturers rating); gunite machine; hammers (hydraulic self propelled); hydra-spiker (ride on); hydra blaster (water); hydra blaster; motorized form carrier; post hole digger and post driver; power sweeper; roller (grade and fill); scarifer (ride on); span saw (ride on); submersible electric pump (when used in lieu of well points); tamper (ride on); tie extractor (ride on);

tie handler (ride on); tie inserter (rider on); tie spacer (ride on); track liner (ride on); tractor with towed accessories; vibratory compactor; vibro tamp; well point aggregate plant; boiler (used in conjunction with production); cement and bin operator; compressors (3 or less not to exceed 1200 cfm combined capacity); compressors (any size; but subject to other provisions for compressors); dust collectors; generators; pumps; welding machines; light plants (3 or less of any type or combination); concrete paver or mixer (16s and under);

concrete saw (self propelled); fireman; form tamper;

greaseman; hydraulic pump (jacking system); junior engineer; light plants; mulching machine; oiler; parapet concrete or pavement grinder; power broom (towed); power heaterman (when used for production); revinius widener;

shell winder; steam cleaner; tractor

GROUP 4: Crane, friction or lattice type with boom length 200 feet and over

ENGI0832-004 07/01/2018

Rates Fringes

Power equipment operators:

BUILDING CONSTRUCTION

GROUP 1....................$ 33.27 27.90+a GROUP 2....................$ 32.47 27.90+a GROUP 3....................$ 29.77 27.90+a GROUP 4....................$ 25.21 27.90+a GROUP 5....................$ 36.85 27.90+a GROUP 6....................$ 38.32 27.90+a GROUP 7....................$ 39.19 27.90+a GROUP 8....................$ 35.27 27.90+a

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day, provided the employee works on the work day immediately preceding the holiday or on the scheduled work day immediately following the holiday.

BUILDING CONSTRUCTION CLASSIFICATIONS

GROUP 1: Air Tugger, All terrain telescoping material handler, Clamshell, Dragline, Shovel and similar machines over three eighths cu.yd. capacity (Fact. rating);Carrier mounted backhoes that swing 360 degrees Big Generator Plant Hoist (on steel erection) Bridge Crane (all types), Cableway, Caisson auger and similar type machine, Crane, Derrick, Dredge, Excavator all purpose hydraulically operated, Forklift (with Factory rating of Fifteen ft. or more of lift),Hoist (on steel erection), Hydraulic/Krupp Drill Type Mucking Machines, Remote controlled excavator with attachments (Brokk type or similar), Ross Carrier (and similar type), Three-Drum Hoist(when all three drums are in use)

GROUP 2: A-Frame Truck, Backfilling Machine, Backhoe -tractor mounted, Barber Green and similar type machines, Belt Crete and similar type machines, Bituminous spreading machine 3/8 yd. capacity or less(Factory Rating), Bulldozer, Carry-all type scraper, Compressors: Four (4) not to exceed 2000 CFM combined capacity; or three (3) or less with more than1200 CFM but not to exceed 2000 CFM, Concrete Mixer, Concrete Placer, Concrete Pump, Dinky Locomotives (all types), Elevating Grader, Elevator Fine Grade and Finish, Rollers, Fine Grade Machines(all kinds), Forklift with Factory rating of less than fifteen(15) feet of lift, Front End Loader, Gunite Pumping Machine, High Pressure Boiler, Hoist (1 or 2 drums), Maintenance Engineer (Mechanic), Mechanical Slurry Machine (all kinds), Mega Mixers and similar type machines, Motor Grader, Post Hole Digger, Pumps (regardless of motive power) no more than four (4) in number not to exceed twenty (20) inches in total capacity, Shot Crete Pumping Machine, Side Boom Tractor, Skid Steer Loader with Attachments, Stone Crusher Tournadozer and similar types Tournapull and similar types, Trenching Machines, Well Drill, WellPoint System EXCEPTION: Single electric pumps up to and including four (4) inches need not be manned.

GROUP 3: Any combination (Not to exceed three (3) pieces of equipment) Compressors ¬three (3) or less, or not to exceed 1200 CFM combined capacity, Fireman, Longitudinal Float, Mechanical Heater Pumps (regardless of motive power) No more than three (3) in number, not to exceed twelve (12) inches total capacity, Roller (Fill and Grade)Rubber Tired Tractor Welding Machine or Mechanical Conveyor (over 12ft.

in length) EXCEPTION: Single gasoline driven welding machine up to 300amps need not be manned.

GROUP 4: Oilers

GROUP 5: Cranes up to and including 25 tons

GROUP 6: Cranes 25-250 tons

GROUP 7: Cranes 251 and over tons

GROUP 8: Tower Cranes

IRON0033-010 07/01/2018

Rates Fringes

Ironworkers:

Sheeter.....................$ 27.65 25.99 Structural, ornamental, rodman machinery mover rigger, fence erector, precast concrete erector, reinforcing, stone derrickman..................$ 27.40 25.99

LABO0435-006 07/01/2018

Rates Fringes

Laborers:

BUILDING

Asbestos removal...........$ 27.14 17.99 Blaster....................$ 27.47 17.99 Chuck Tender...............$ 26.34 17.99 Concrete vibrators.........$ 26.58 17.99 Drillers and asphalt raker.$ 26.54 17.99 Jack Hammer, mortar mixer..$ 26.44 17.99 Pipe layers, burners and cutters....................$ 26.44 17.99 Powder Monkey..............$ 27.01 17.99 Unskilled laborer..........$ 26.14 17.99 Yardman, clean-up..........$ 23.29 17.99

HEAVY AND HIGHWAY

GROUP 1....................$ 28.54 19.92

GROUP 2....................$ 29.24 19.92

GROUP 3....................$ 29.44 19.92

GROUP 4....................$ 30.27 19.92

GROUP 5....................$ 30.04 19.92

FOOTNOTES:

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee has worked the working day before and the working day after the holiday.

HEAVY AND HIGHWAY LABORER CLASSIFICATIONS

GROUP 1: Flaggers GROUP 2: Laborers GROUP 3: Rakers, drillers, pipelayers and torch operators GROUP 4: Blasters GROUP 5: Hazardous waste removal

* PAIN0004-028 05/01/2018

Rates Fringes

Painters:

BUILDING CONSTRUCTION

Brush & Roll...............$ 23.22 20.68 Drywall Taper..............$ 24.56 20.74 Sandblasting...............$ 23.97 20.68 Spray......................$ 23.82 20.68 Wallcovering...............$ 23.52 20.68

HEAVY & HIGHWAY

CONSTRUCTION:

Bridge Work................$ 38.00 27.75

PLUM0013-004 05/01/2018

Rates Fringes

Plumber and Steamfitter (Including HVAC Work)............$ 33.13 22.68

ROOF0022-001 05/31/2018

Rates Fringes

ROOFER...........................$ 28.90 20.29

SHEE0046-003 05/01/2017

Rates Fringes

Sheet Metal (Including HVAC Work)............................$ 32.13 23.40

SUNY1993-002 10/04/1993

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 15.75 .59

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

wdol.gov
https://www.wdol.gov/wdol/scafiles/davisbacon/NY32.dvb?v=1

File details come from the government source that posted it.