36C10F19R0010-0002000.docx
DOCX document 25 KB Posted
- Attached to
- Presolicitation Notice - Great Lakes Construction Updated 5/15/2019 Federal contract opportunity
- Solicitation number
- 36C10F19R0010
About this file
36C10F19R0010 0002 36C10F19R0010 0002.docx
View the file
Other files for this federal contract opportunity
Show all 50
Presolicitation Notice - Great Lakes Construction Updated 5/15/2019 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C10F19R0010 Amendment 0002
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 06-21-2019
923CM2006.11
003C4D Department of Veterans Affairs Office of Construction and Facilities Management (003C4D) 1425 Tri State Pkwy, Suite 140 Gurnee
IL
60031 101F Department of Veterans Affairs Office of Construction and Facilities Management (003C4D) 1425 Tri State Pkwy, Suite 140 Gurnee
IL
60031 To all Offerors/Bidders
36C10F19R0010 05-30-2019
X X X
X Amendment 0002 contains the following:
1. Responses to Technical RFI's Received by VA as of 4pm 6/21/19
End of Amendment 0002
Jeffrey C Gerbensky Contracting Officer
GREAT LAKES NATIONAL CEMETERY
PHASE 2 EXPANSION
PRE- PROPOSAL AMENDMENT 0002
RFI RESPONSES
JUNE 21, 2019
VA Responses (in bold italics)
RFI #1
Section 32 33 00, 2.3 Gravesite Layout Markers reference Bronze makers.
Plan Sheet DT501 (79 of 238) Notes forged aluminum monument markers, which are consistent with the monuments at this cemetery.
Which type should be provided?
Forged Aluminum Monument Markers consistent with existing monuments will be used.
RFI #2
Section 11 83 00, 2.1, E.
Regarding the Trimble TSC3. The TSC3s operate on older windows mobile technology. We recommend moving to a more modern system for ease of use and improved syncing and integration with GIS system. Would a Trimble TSC7 be a suitable option in lieu of the TSC3?
Per specification section 11 83 00 2.1E requires a Trimble R2 (RTK) with TerraFlex as the collection software.
RFI #3
Section 11 83 00, 2.1, E., 9.
Regarding the 24 Month Pre-Paid Data Plan - Is there WiFi Service onsite that can be utilized in lieu of this. Typically Upload and Download of data would be done within the office/building upon days begin or end.
There is no Wi-Fi available, data will be synced all day long to TerraFlex servers using provided cellular data plan.
RFI #4
The Plans indicate the Coordinate system to be in US Feet. Michigan operates in international feet. The original survey performed by us (MEGA) was provided in international feet. This translation difference could result in significant errors across the site. Plans should be corrected to indicate International Feet and confirm that the design was performed in this coordinate system.
International feet are acceptable, provided the projection being used for the GIS dataset is correctly defined. See 11 83 01, GeoData for requirements
RFI #5
Section 11 83 00 1.1.A Currently RTK and GNSS systems are capable of operating at centimeter-level accuracy assuming site conditions allow it. Use of these systems degrade when close to overhead cover, buildings, tree cover and other tall vertical surfaces. Is this understood and accepted by the government?
Yes, this is understood and accepted.
RFI #6
Section 11 83 00 1.1.A.2 Need an estimate of number of internments per day that are estimated for site.
Based on the 2017 and 2018 total interment count, the interment rate is roughly 16 interments/day requiring the contractor to provide 4 rover units.
RFI #7
Section 11 83 00 1.1.A.3 Number of RAF (repeater stations) is to be determined by a radio survey. Not possible to know how many are needed prior to submitting bid. Will change orders be allowed for this if needed?
Offerors will base their proposal on utilizing no repeater stations. Should additional stations be required as a result of the radio study a contract modification will be issued.
RFI #8
Section 01 91 00, 1.7, B “Equipment: GIS - Software user interface” There does not appear to be a section describing the Software requirements. Will the contractor be responsible for providing the software and licensing? Or does the VA have existing software and computers in place already?
The only software subscription is Trimble TerraFlex running on the data collectors. The software subscription is to be provided as stated in the spec. This subscription will be added to NCA’s existing TerraFlex account. Be mindful, the subscription activates/starts when cut; so don’t order this prior to turnover. We can work with the GPS subcontractor to ensure the equipment is working before providing a temp license for testing. No computer terminal is required.
RFI #9
Section 11 83 02 What Version of ArcGIS is the government utilizing/ what version will the GIS database need to be delivered in?
Database is 10.3.1 or newer.
RFI #10
Section 11 83 02 Is the ArcGIS end product for Desktop or intended for online use?
The File Geodatabase required in Spec 11 83 02 will be used to ETL into our Enterprise GIS.
RFI #11
Section 11 83 02 Is the ArcGIS database local or are they using a server-based database?
The File Geodatabase required in Spec 11 83 02 will be used to ETL into our Enterprise GIS.
RFI #12
Section 11 83 00, 6, B Is the cemetery/government already licensed by the FCC to use the 406-420 MHz range on a 24/7 basis?
Yes the Cemetery is licensed by FCC but will require a designated frequency by the VA Spectrum Office.
RFI #13
Section 11 83 00, 6, B Will the contractor be able to install 3 radios on the GPS base station, for the duration of the construction?
One at 406-420 MHZ for cemetery internal use.
One at 430-470 MHZ for surveyor onsite to use for layout.
One at 900 MHZ for contractors to use for machine control.
Having a single base for all users provide many benefits.
The required base station for use by the cemetery must operate in the government range. If the contractor is able to use the base station additionally for construction by broadcasting other frequencies, and there is no interference with multiple frequencies broadcasting in close proximity, then that should not be problem. Keep in mind the location of where the base station is, how/where the additional radio antennas are going to be mounted, and VA is not responsible for maintaining the radio transmitters. Locations must be approved by CFM and the cemetery.
RFI #14
Section 11 83 00, 2.1, E., 9.
Regarding the 24 Month Pre-Paid Data Plan. Will it be acceptable to the government to have these SIM Cards tied to the consultants account?
Verizon and AT&T must register the SIM Cards to an account to pre-pay for 2 years.
That is fine, at the end of two years NCA will provide replacement sim cards.
RFI #15
Section 11 83 00, 6, C Regarding Antenna Mount and Support Hardware. Plans Sheet CS108 indicates the location on the maintenance building for a building mount method. Is there a location approved and suggested if the building mount not be available? The spec indicate that it is shown in the plans but a location (off building) was not found.
The mounting location, antenna mount and support hardware shop drawings and cut sheets will be submitted to the SRE for review as part of the project submittal process.
RFI #16
Section 11 83 00, 6, C Regarding Antenna Mount and Support Hardware. Please confirm that the maintenance building is an approved building to mount the GPS.
The maintenance building is the designated location for the Antenna.
RFI #17
Section 11 83 00 If repeater radios are needed for signal coverage of the site, does the government recommend other buildings onsite where radios and antennas may be mounted? Power supply would need to be available for these systems.
See response to RFI # 7.
RFI #18
Section 03 30 53, 2.3 Concrete Mixes.
Concrete spec’d for cast in place monuments is 3500 PSI. Please provide a 3500 PSI Cement/Water factor.
If proration on the provided table can be assumed please indicate so.
Please use the concrete/water ratio as noted in the chart below.
TABLE I - CEMENT AND WATER FACTORS FOR CONCRETE
| Concrete: Strength |
| Non-Air-Entrained |
| Air-Entrained |
Min. 28 Day Comp. Str.
psi Min. Cement lbs./cy
| Max. Water Cement Ratio |
| Min. Cement |
lbs./cy Max. Water Cement Ratio
| 50001,3 |
| 630 |
| 0.45 |
| 650 |
| 0.40 |
| 40001,3 |
| 550 |
| 0.55 |
| 570 |
| 0.50 |
| 35001,3 |
| 520 |
| 0.60 |
| 520 |
| 0.55 |
| 30001,3 |
| 470 |
| 0.65 |
| 490 |
| 0.55 |
| 30001,2 |
| 500 |
| * |
| 520 |
| * |
1. If trial mixes are used, the proposed mix design must achieve a compressive strength 1200 psi in excess of f'c. For concrete strengths above 5000 psi, the proposed mix design must achieve a compressive strength 1400 psi in excess of f’c.
2. For concrete exposed to de-icing salts, maximum water: cement ratio 0.40.
3. For concrete exposed to high sulfate content soils maximum water cement ratio is 0.44.
End of Response