SOW Flooring Replacement at Station Golden Gate REV 1.pdf

PDF 232 KB Posted

Attached to
Flooring Replacement at Station Golden Gate
Solicitation number
30467PR250000018
Issued by

About this file

This Statement of Work (SOW) details flooring replacement at the US Coast Guard Station Golden Gate in Sausalito, CA. The project involves removing and replacing first and second-floor flooring, with specific requirements including removing 3,500 square feet of first-floor carpet and polishing the underlying concrete, and removing 3,200 square feet of second-floor carpet and installing Luxury Vinyl Plank (LVP) flooring. Contractor responsibilities include providing all labor, materials, and equipment, ensuring daily cleanup, minimizing impact to Coast Guard operations, and working between 7:00 AM and 5:00 PM Monday through Friday. The government will provide electricity, parking, and a laydown area, with Francisco Rivera serving as the Technical Point of Contact. The project requires adherence to industry standards for installation, waste disposal, and environmental regulations, with final acceptance to be determined by the Coast Guard Technical POC.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

REPLACE FLOORING US COAST GUARD STATION GOLDEN GATE

PART 1 - GENERAL

The intent of this Statement of Work (SOW) is to have the contractor remove and replace the first and second-floor flooring at Station Golden Gate in Sausalito, CA. The contractor will provide all labor, materials, and equipment required to complete the installation. The color of the flooring will be chosen by the customer.

PART 2 - FACILITY AND SECURITY REQUIRMENTS

1. Contractor vehicles must have valid registration and insurance, and vehicle operators must have a valid driver license. All personnel shall have valid photo identification.

2. The contractor shall clean up all areas to ensure they are clear of debris daily. At completion of the project all construction areas will be returned to their original condition. The contractor shall remove all waste material generated and dispose of in accordance with industry standards and applicable environmental rules and regulations.

3. Minimizing impact to Coast Guard operations. Work performed at San Diego, CA shall be completed between the hours of 7:00AM and 5:00PM, Monday thru Friday (excluding Federal Holidays) unless authorized by the Contracting Officer.

PART 3 - GOVERNMENT FURNISHED MATERIAL

1. Contractor will provide all materials to complete the work necessary. The government will provide electricity, parking, and laydown area as available from the unit. Bathroom facilities will not be available for contractor personnel.

PART 4 - TECHNICAL POINT OF CONTACT DESIGNATION

1. Technical POC for this task is:

Francisco Rivera Office: 909-973-3879 E-mail: Francisco.P.Rivera@uscg.mil

PART 5 – TASKS

1. Mobilization

a. Mobilize all necessary equipment and personnel to safely execute the flooring removal and installation tasks.

b. The government will ensure the worksite is cleared of furniture and other items prior to removal and installing of flooring.

First Floor Flooring

2. Removal of Carpet

a. Remove 3,500 square feet of existing carpet.

b. Ensure thorough cleaning and preparation of the underlying surface for polishing.

3. Concrete Polishing

a. Polish the exposed concrete floor to the specified finish as selected by the Technical POC.

Second Floor Flooring

4. Removal of Carpet

a. Remove 3,200 square feet of existing carpet.

b. Prepare the underlying surface for the installation of new flooring.

5. Installation of Luxury Vinyl Plank (LVP)

a. Install 3,200 square feet of LVP flooring as chosen by the Technical POC.

b. Ensure proper adhesive and installation techniques are used as per industry standards.

6. Disposal

a. Remove and dispose of all carpet and other waste materials in accordance with industry standards and applicable environmental rules and regulations.

7. Demobilization

a. Remove all equipment from government facilities.

b. Return all work areas to their original condition, ensuring proper cleanup and restoration.

PART 6 – ACCEPTANCE

1. Completion of work under this contract will be monitored and accepted by Coast Guard Technical POCs listed in

PART 4.

END