27ROB0150 Vendor Quote.pdf
PDF 137 KB Posted
- Contract number
- 26-416CMS-BOPM4-P-88370
- Issued by
- Illinois
About this file
This is a Proposal - Itemized Breakdown for a construction project submitted by Schomburg & Schomburg Construction, Inc., the prime contractor. The project involves the Robinson Correctional Facility located at 13423 E 1150th Ave, Robinson, Illinois 62454. The proposal was prepared by estimator Marie Hardin on 8/13/2026.
The scope of work consists of removing and replacing a caustic door entirely. The total proposal cost is $8,898.00, comprised of prime contractor direct labor costs of $2,240.00 for 16 hours of carpenter journeyman work at $140.00 per hour and 16 hours of carpenter foreman work at $145.00 per hour totaling $2,320.00, combined with prime contractor miscellaneous costs of $1,640.00, direct material costs of $2,388.00, and equipment rental of $310.00. The miscellaneous costs include 4 hours of mobilization time, dump fees, and spoil haul-off expenses. No subcontractor proposals, direct overhead, insurance and taxes, bonding, or prime contractor fees are indicated on this proposal. All line items for added work are shown with costs, while omitted work credit line items are blank, indicating this is an added work change order or proposal.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LINE NO.
OMITTED WORK
(CREDIT) - (B)
ADDED WORK
(COST) - (C)
1A -$ -$
1B -$ -$
1C -$ -$
1D -$ -$
1E -$ -$
2 -$ -$
3 -$
4A 0.0% $ - -$
4B 0.0% $ - -$
4C 0.0% $ - -$
5 -$
LINE NO.
OMITTED WORK
(CREDIT) - (B)
ADDED WORK
(COST) - (C)
6 -$ 2,320.00$
PRIME CONTRACTOR DIRECT LABOR CARPENTER JOURNEYMAN __16___ HRS @ $140.00/ HR 2,240.00$
PRIME CONTRACT MISCELANEOUS COSTS 1,640.00$
7 -$ 2,388.00$
8 -$ 310.00$
9 -$ -$
10 8,898.00$
11A 0.0% $ - -$
11B 0.0% $ - -$
11C 0.0% $ - -$
12A 0.0% $ - -$
12B 0.0% $ - -$
12C 0.0% $ - -$
13 0.0% -$ -$
14 0.0% -$ -$
15 -$ -$
16 -$
17 0.0% -$
18 8,898.00$
Robinson Correctional Facility Caustic Door Replacement
Schomburg & Schomburg Inc.
PROPOSAL - ITEMIZED BREAKDOWN
(Prime Contractor)
CONTRACT NUMBER PROJECT NAME
PROJECT LOCATION
13423 E 1150th Ave Robinson Illinois 62454
PROJECT NUMBER NAME OF PRIME CONTRACTOR
Schomburg & Schomburg Construction, Inc.
DESCRIPTION OF WORK
Remove and replace Caustic Door entirely
REQUEST FOR PROPOSAL NUMBER CHANGE ORDER NUMBER (i.e. - Mod #)
SUBCONTRACTOR PROPOSAL SUMMARY
ITEM - (A)
SUBCONTRACTOR(S) PROPOSAL
Sub #1
Sub #2
Sub #3
Sub #4
Sub #5
PRIME CONTRACTOR DIRECT MATERIAL
(Lines 1A - 1E) -
(Column C, Line 2 minus Column B, Line 2) -
PRIME CONTRACTOR
FEE*
PRIME CONTRACTOR PROPOSAL SUMMARY
ITEM - (A)
PRIME CONTRACTOR DIRECT LABOR CARPENTER FOREMAN ____16_____ HRS @ $145.00/ HR
PRIME CONTRACTOR EQUIPMENT RENTAL
(Lines 6, 7, & 8) -
(Column C, Line 9 minus Column B, Line 9) -
DIRECT
OVERHEAD*
INSURANCE AND TAXES** (for Line 6)
TAXES ON MATERIAL AND EQUIPMENT*** (for Lines 7 & 8)
Bonding (for Line 16)
(to include Line 5 above) -
PRIME CONTRACTOR ESTIMATOR Marie Hardin 8/13/2026
Notes
MISC COSTS INCLUDE 4 HRS MOBILIZATION TIME, DUMP FEES, SPOIL HAUL OFF, ETC.