27-0015 Attachment E- Estimated Schedule.PDF

PDF 71 KB Posted

Attached to
27-0015 General Contractor for Cass Tech Athletic Field Reno
Solicitation number
RFP DET 260000002457 2
Issued by
Wayne County, Detroit City, Michigan

About this file

This is an Estimated Schedule document for contract 27-0015, a General Contractor project for Cass Tech Athletic Field Renovation in Michigan. The project timeline spans approximately 13 months, beginning with the General Contractor procurement phase on September 30, 2026, and concluding with project closeout by October 29, 2027. Key milestones include a Board Vote scheduled for November 10, 2026, contract signing by December 22, 2026, and issuance of the purchase order also by December 22, 2026. The General Contractor onboarding period for pre-construction activities, submittals, and materials procurement is allocated 70 days, running from December 23, 2026, through March 30, 2027. The primary construction phase is scheduled for 98 days from March 31, 2027, through August 13, 2027, followed by a 55-day closeout period extending from August 16, 2027, through October 29, 2027.

The schedule document provides no specific information regarding pricing terms, funding sources, set-asides, or other financial considerations. The timeline reflects a comprehensive project management approach with distinct phases for procurement, contract execution, contractor preparation, active construction, and final closeout activities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Duration Start Finish

1 GC Procurement 130 days Wed 9/30/26 Tue 3/30/27

2 Board Vote 30 days Wed 9/30/26 Tue 11/10/26

3 Contract Signed 30 days Wed 11/11/26Tue 12/22/26

4 PO Issued 30 days Wed 11/11/26Tue 12/22/26

5 GC Onboard for Pre-Con /

Submittals / Materials

70 days Wed

12/23/26

Tue 3/30/27

6 Construction 98 days Wed 3/31/27 Fri 8/13/27

7 Closeout 55 days Mon 8/16/27 Fri 10/29/27

W T F S S M T W T F S S M T W T F

Oct 4, '26 Oct 11, '26

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Cass Tech Bidding Sche

Date: Mon 7/13/26